a) Balance this operation using shortest operation time rule and compute the efficiency of the line. b) Discuss how this balance could be improved. Is it possible to improve this balance to 100%?
Q: What level of automation is appropriate? (Some operations are more suited to being automated than…
A: It is an important decision that needs consideration of some relevant issues. Those questions that…
Q: (d) Which rule should be used, in your opinion? Why? (e) The head mechanic at the production…
A: Find the Given details below: Given Details: Job Day Job received Job Processing Time (days)…
Q: Melissa’s Photo Studio offers both individual and group portrait options. The process flow diagram…
A: Bottleneck process This is that process or activity in the entire project which can prove to be a…
Q: Give your views on bottleneck. Why is it important to find the bottleneck?
A: Bottleneck is a term associated with a capacity of a process. A process capacity indicating the…
Q: given information: which step is in bottleneck=30 min for tan leather 60/30=2 briefcases per hr…
A: Annual capacity= 8*250*2 =4000 briefcases
Q: d. Use the calculated cycle time. Assign tasks to workstations on the basis of most following tasks.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Monique Food Processing Company produces light snacks that can be heated in a microwave. The…
A: Note:-We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint:…
A: Find the Calculation methods: Efficiency = Total task timeLead timeTotal task time = ∑ (Task…
Q: Every year, volunteers administer flu vaccine shots at a Medical Centre. The process involves four…
A: a) From the above given information, Capacity = Time available÷Cycle time in minutes…
Q: Operations administrators have access to clear a bottleneck? none of these reduce time to the bottom…
A: Determine how to take advantage of the system's constraint(s) – how to deal with bottlenecks. - 3…
Q: A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and…
A: Utilization measuring the proportion between actual usable time and total available time. A…
Q: A small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two…
A:
Q: Given the following line balance data in the table below. For eight hours of operating time per day…
A: Line balancing is a creation system that includes balancing administrator and machine time to…
Q: 1. An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total…
A: Note:-We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: a) Balance this operation using the shortest operation time rule and compute the efficiency of the…
A: Activity Immediate Predecessors Duration K3 - 60 K4 K3 24 K9 K3 27…
Q: a. What is the bottleneck time of the system?
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: What changes would you make to have the capacity of each step within 0.1 sheets/min of the other…
A: The answer is as below:
Q: What type of process—project, job shop, flow shop, and continuous flow—would most likely be used to…
A: The process of producing following items:
Q: What are the techniques available to operations managers to deal with a bottleneck operation? Which…
A: A bottleneck is a state of blockage in a creation system, (for example, a sequential assembly line…
Q: An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the totaltime…
A: Minimum cycle time = length of the longest task Therefore, the minimum cycle time = 2.4 minutes
Q: A small formwork subcontractor is awarded to erect formwork. It has been estimated 75labor-days. The…
A: Production is the process of converting inputs into finished products and services for the…
Q: 1.DG Fast Food has four activities in serving a customer: greet customer, take order, process order,…
A: As per Bartleby's guidelines, we only answer the first question in case multiple questions are asked…
Q: Mega Corp. is designing a product layout for a new electronic product. They plan to use this…
A: Any electrical equipment, appliance, material, system, or apparatus that conveys or is controlled by…
Q: Explain what are the techniques available to operation manager to deal with a bottleneck operation…
A: When delving into the topic, it is required to define a bottleneck operation. A bottleneck operation…
Q: The Henry Street Mission uses volunteers to assemble carepackages for needy families during the…
A: Firstly balancing the line. Therefore, A 7 B 9 C 10 D 30 This question can be solved in…
Q: a) what is the bottleneck time of the system? b) what is the bottleneck station of this work cell?…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: How is the earliest start time ( EST) and the earliest completion time (ECT) of the operation…
A: Let; Duration of an activity = Period of operation.
Q: What are the technologies used for bottleneck processes for operations managers?? And does not…
A: Bottleneck is the precondition for delaying or slowing down the whole operation by an obstruction.…
Q: a. what is the bottleneck of this process? b. what is the hourly capacity of the process?
A: Bottleneck station refers to the the one which has the lowest output per unit time. The output at…
Q: Calculate the efficiency of the newly design process.
A: A line balancing efficiency indicates the proportion between total task time and total workstation…
Q: A work center assigns tasks to 7 work stations. The total of all the task times is 24. If the cycle…
A: Remember the formulas for this problem Total time taken = No. of stations * Cycle time Efficiency =…
Q: 1. An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total…
A: Given data,Operational time (OT) = 450 minutes a dayLongest task = 2.4 minutes Total time for all…
Q: Which are the present four principles of bottleneck management?
A: A bottleneck is a stage in the manufacturing process where work is coming too fast and is difficult…
Q: 22
A: The cycle time is given by the total number of units divided by the total available time. Hence the…
Q: Compute the cycle time for Sunburn Pharmaceuticals given the following data: set-up time, 2 hours;…
A: Given, Set up time= 2 hours Process time= 10 hours Move time = 80 minutes=1.3 hours Wait time =20…
Q: Activity Greet customer Take order Process order Print receipt Activity Time per Customer 5 seconds…
A: Given data Demand rate = 20 customer per hour
Q: Draw a process fl ow diagram of your last doctor’s offi cevisit. Identify bottlenecks. Did any…
A: Small Introduction of Flow Diagram/ Flow Chart A flowchart is a two-dimensional graphic…
Q: i. Draw the precedence diagram. ii. Compute the cycle time (in seconds) to achieve the desired…
A: The solution has to be completed solved to determine the next 3 solution requested. Line Balancing…
Q: • A producer of inkjet printers is planning to add a new line of printers, and you have been asked…
A: 1) Predecessor Diagram
Q: Give an example of Bottleneck operation?
A: A bottleneck operation in a production process is the point at which the operation meets or exceeds…
Q: 18. If station #2 is replaced with two parallel stations, each one performing tasks C and E what…
A: Cycle time is a proportionate time available to complete each unit of time. Here, we can identify…
Q: What is the bottleneck time of the system?
A: A bottleneck is the most minimal cycle with the least yield in a framework. For the most part, it…
Q: The Stylish Hair Salon has three stylists who provide services to women. After checking in with the…
A: We have, Processing time per customer for receptionist = 1 +3 = 4 minutes per customer Processing…
Q: a. Construct a precedence diagram and compute the lead time for the process. b. If the demand for…
A:
Q: A small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two…
A: Given that, Q = 12,000Selling price for A = 15Selling price for B = 15Variable cost for A =…
Q: Mr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean…
A: Below is the solution:-
Step by step
Solved in 2 steps with 1 images
Hello guys, can you draw the precedence diagram please? I get really confused
- A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length(minutes) Immediate(Predecessor) a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g Click here for the Excel Data File a. Do each of the following: (1) Enter the number of following tasks for each of the tasks shown in the table below. (2) Assign tasks to stations in order of greatest number of following tasks. Use greatest positional weight as a tiebreaker rule. (3) Determine the percentage of idle time. (Round your answer to 2 decimal places.) (4) Compute the rate of output in printers per day that could be expected for this line, assuming a 420-minute working day. (Round your answer 2 decimal places.) b. Answer these questions: (1) What is the…(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 1. Check for over-allocation. Which resources are over allocated? 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?
- A local toy maker uses a manufacturing line running eight hours a day that produces a toy which needs 7 tasks in total. The regular requirements are 100 toys. Task times are 2.73,2.01,2.13,2.0.2.11,2.71 and A,B,C,D,E,F and G, respectively, 2.95 minutes. However, there are precedent laws because of the essence of the substance that must be followed. This type of task has no predecessors; task B needs the completion of task A. To begin task C and task D, each task requires the completion of task B. Mission must be done until task E is defined. Goal F has to be done with Task D and Task Finally, task G will only start until task Fis has been completed. Since we extend the remaining job rule to balance the production line with the linkage broken in the longest working period, check circle is the task allocated to the THIRD stationA local bakery makes custom cakes for special eventssuch as weddings and graduations. Making cakes is a two-step process of baking and decorating. The bakery has received eight orders, and the times required in hours for baking and decorating for each order are given in the following table:Cake Orders Baking DecoratingA 3 4B 1 2C 4 7D 2 4E 5 10F 2 6G 5 7H 6 13Determine a sequence that will minimize the makespan time.Construct a chart of the resulting sequence, and determine the idle time in te decoration process.A manufacturer is designing a product layout for a new product productionIt plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namelyABC, D, E, F, and Grespectively. Task A does not have any predecessor to startTo start Task B.it requires Task A to be completedStarting tasks needs, the task B to be completed. Also, starting task Dneeded task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed task Fto be completed. The processing times for tasks, ABC, D. E. and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8 and 4.7 minutes respectively. What should be the cycle time in minutes? a 4.7 b. None is the correct answer Oc 7.5 d6.86 e.
- If the cycle time is 65.4 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A? Task Task Time (seconds) Tasks That Must Precede Other Tasks Number of Following Tasks A 28 - 7 B 13 - 8 C 35 B 7 D 11 A 6 E 20 C 6 F 6 D, E 5 G 23 F 3 H 25 F 2 I 37 G 1 J 11 G, H 1 K 27 I, J 0 Total 236 a. 26.9 minutes b. 37.4 seconds c. 28.5 seconds d. 31.6 seconds e. 57.6 secondsCompletion of three activities is required to accomplish a job. The administrator would liketo know if differences in the arrangement of the three activities results in different jobaccomplishment times. He selects three workers and demonstrates the activities in random orderto them. Then each worker accomplishes the job with each of the activity arrangements. Thecompletion times are recorded. The following table shows the minutes for each worker toaccomplish each job. Arrangements Workers Time Consumed (minutes) Mr. X Mr. Y Mr. ZA 22.4 18.6 21.5B 19.2 20.2 20.7C 20.3 17.0 20.4 Using one percent level of significance, answer following questions:i. Is there a difference in job accomplishment times among different arrangements?ii. Is there a difference in job accomplishment times between the workers?The times required to complete each of eight jobs in a two-machine flow shop are shown in thetable that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.a. Determine a sequence that will minimize makespan time.b. Construct a chart of the resulting sequence, and find machine B’s idle time. c. For the sequence determined in part a, how much would machine B’s idle time be reduced bysplitting the last two jobs in half?TIME (hours)Job Machine A Machine Ba 16 5b 3 13c 9 6d 8 7e 2 14f 12 4g 18 14h 20 11
- Glaudious is 45 years old university internship coordinator. He is handling 80 interns and he would like to perform the following tasks in an easy and fast way. He also encountered an accident a year ago which caused his right leg to have a bone minor fracture which caused him to limit the place he can go. He would like that he can perform the tasks anytime and anywhere. Below are the tasks of Prof Glaudios. 1) He registers the students undergoing internship, this includes the term in a schoolyear, the company name where the student is undergoing internship, directsupervisor of the intern, start of duty, Number of Hours of duty per day, andthe Job of the student-intern in the company. 2) He will also view the following: a) Individual internship record in a term-sem-school year b) Interns details in a company using the Professor Glaudious Scenario, provide the requirements specification: a. Functional b. Data c. Environmental d. User e. UsabilityGlaudious is 45 years old university internship coordinator. He is handling 80 interns and he would like to perform the following tasks in an easy and fast way. He also encountered an accident a year ago which caused his right leg to have a bone minor fracture which caused him to limit the place he can go. He would like that he can perform the tasks anytime and anywhere. Below are the tasks of Prof Glaudios. 1) He registers the students undergoing internship, this includes the term in a schoolyear, the company name where the student is undergoing internship, directsupervisor of the intern, start of duty, Number of Hours of duty per day, andthe Job of the student-intern in the company. 2) He will also view the following: a) Individual internship record in a term-sem-school year b) Interns details in a company Based on the scenario above, model the tasks of Prof Glaudious by creating a Task Analysis.A manutacturer is designing a product layout for a new product production. It plans to use a production line for B hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 lasks in total. These tasks are namely, A, 8, CD, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed Starting tasks Cneeds, the tack B to be completed. Also, starting task D needed task B to be completed Task E can only start upon completion of Task C. Whescas starting lask F needs the completion of both the tasks D and E Finally, starting task G needed, task Fto be completed. 1the processing times for tasks, A BC D, E F, andG are 28, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks nule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one OaAB, and C ODAB Oc None…