common drilling contract that is based on cost per day to drill down to a contract depth is called a footage or depth contract. True or false

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter4: Measuring Site Work, Excavation, And Piling
Section: Chapter Questions
Problem 1RQ
icon
Related questions
icon
Concept explainers
Question
100%
A common drilling contract that is based on cost per day to drill down to a contract depth is called a footage or depth contract. True or false?
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Foundation Construction
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,