company's bids for such sites have been successful. However, the company is also under pressure to refurbish some of its existing rigs for both efficiency and safety reasons. The £750 million could be used for this purpose instead. If the money is used for refurbishment, there is a 50 percent chance of increasing efficiency to generate a return on the £750 million of 5 percent, and a 50 percent chance of generating a return of 10 percent. If the decision to refurbish takes place after the bid has been made and failed, another £500 million will be required for refurbishment. a) Construct a decision tree for this problem.

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.2SB
icon
Related questions
Question
A large multinational oil company is considering its strategy in the North See. The UK
government has announced that a new drilling site in the North Sea will be offered for sale on a
competitive tender basis, the site going to the company making the highest bid. Provisional
exploration of the site indicates that, over its life, it can be expected to generate revenue of
around £1,500 million if the oil reserves turn out to be high, but only £500 million if they turn
out to be low. Seismic tests have indicated that the probability of high reserves is 0.60. If the
company is successful in its bid, it will also have to decide whether to construct a new oil rig for
the site or to move an existing oil rig which is currently operating at an uneconomic site. The
costs of the new rig are around £250 million and for moving the existing rig around £100 million.
A new rig would be able to boost production by £150 million if reserve levels turned out to be
high. The company has decided that if it is to bid for the site, the maximum bid it can afford at
present, because of its cash flow situation, is £750 million. In the past, 70 percent of the
company's bids for such sites have been successful. However, the company is also under
pressure to refurbish some of its existing rigs for both efficiency and safety reasons. The £750
million could be used for this purpose instead. If the money is used for refurbishment, there is a
50 percent chance of increasing efficiency to generate a return on the £750 million of 5 percent,
and a 50 percent chance of generating a return of 10 percent. If the decision to refurbish takes
place after the bid has been made and failed, another £500 million will be required for
refurbishment.
a) Construct a decision tree for this problem.
Transcribed Image Text:A large multinational oil company is considering its strategy in the North See. The UK government has announced that a new drilling site in the North Sea will be offered for sale on a competitive tender basis, the site going to the company making the highest bid. Provisional exploration of the site indicates that, over its life, it can be expected to generate revenue of around £1,500 million if the oil reserves turn out to be high, but only £500 million if they turn out to be low. Seismic tests have indicated that the probability of high reserves is 0.60. If the company is successful in its bid, it will also have to decide whether to construct a new oil rig for the site or to move an existing oil rig which is currently operating at an uneconomic site. The costs of the new rig are around £250 million and for moving the existing rig around £100 million. A new rig would be able to boost production by £150 million if reserve levels turned out to be high. The company has decided that if it is to bid for the site, the maximum bid it can afford at present, because of its cash flow situation, is £750 million. In the past, 70 percent of the company's bids for such sites have been successful. However, the company is also under pressure to refurbish some of its existing rigs for both efficiency and safety reasons. The £750 million could be used for this purpose instead. If the money is used for refurbishment, there is a 50 percent chance of increasing efficiency to generate a return on the £750 million of 5 percent, and a 50 percent chance of generating a return of 10 percent. If the decision to refurbish takes place after the bid has been made and failed, another £500 million will be required for refurbishment. a) Construct a decision tree for this problem.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning