Critical Path Method (CPM) helps project manager to plan all tasks that must be completed as part of a project. They act as the basis both for preparation of a schedule, and of resource planning. A further benefit of CPM is that it heips to identify the minimum length of time needed to complete a project Given the following task lists for planning a custom-written computer project as in Table 1: Table 1: Task List Length Predecessor Task A. High level analysis 1 week B. Selection of hardware platform 1 day A C. Installation and commissioning of hardware 2 weeks B D. Detailed analysis of core modules 2 weeks A E. Detailed analysis of supporting modules 2 weeks D F. Programming of core modules 2 weeks D G. Programming of supporting modules 3 weeks E H. Quality assurance of core modules 1 week F 1. Quality assurance of supporting modules 1 week G J.Core module training 1 day CH K Development and QA of accounting reporting 1 week E L Development and QA of management reporting 1 week E M. Development of Management Information System 1 week L N. Detailed training 1 week 1. J. K. M You are required to: (a) Prepare a Critical Path Analysis. Determine the early start and early finish and late start and late finish. (b) Define the critical path and state the reasons, why you choose that path.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Critical Path Method (CPM) helps project manager to plan all tasks that must be completed as part of a
project. They act as the basis both for preparation of a schedule, and of resource planning. A further benefit
of CPM is that it helps to identify the minimum length of time needed to complete a project.
Given the following task lists for planning a custom-written computer project as in Table 1:
Table 1: Task List
Task
Length Predecessor
A. High level analysis
1 week
B. Selection of hardware platform
1 day
A
C. Installation and commissioning of hardware
2 weeks B
D. Detailed analysis of core modules
2 weeks A
E. Detailed analysis of supporting modules
2 weeks D
F. Programming of core modules
2 weeks D
G. Programming of supporting modules
3 weeks E
H. Quality assurance of core modules
1 week F
1. Quality assurance of supporting modules
1 week G
J.Core module training
1 day
C,H
K. Development and QA of accounting reporting
1 week E
L. Development and QA of management reporting
1 week
M. Development of Management Information System
1 week L
N. Detailed training
1 week . J. K, M
You are required to:
(a) Prepare a Critical Path Analysis. Determine the early start and early finish and late start and late finish.
(b) Define the critical path and state the reasons, why you choose that path.
Transcribed Image Text:Critical Path Method (CPM) helps project manager to plan all tasks that must be completed as part of a project. They act as the basis both for preparation of a schedule, and of resource planning. A further benefit of CPM is that it helps to identify the minimum length of time needed to complete a project. Given the following task lists for planning a custom-written computer project as in Table 1: Table 1: Task List Task Length Predecessor A. High level analysis 1 week B. Selection of hardware platform 1 day A C. Installation and commissioning of hardware 2 weeks B D. Detailed analysis of core modules 2 weeks A E. Detailed analysis of supporting modules 2 weeks D F. Programming of core modules 2 weeks D G. Programming of supporting modules 3 weeks E H. Quality assurance of core modules 1 week F 1. Quality assurance of supporting modules 1 week G J.Core module training 1 day C,H K. Development and QA of accounting reporting 1 week E L. Development and QA of management reporting 1 week M. Development of Management Information System 1 week L N. Detailed training 1 week . J. K, M You are required to: (a) Prepare a Critical Path Analysis. Determine the early start and early finish and late start and late finish. (b) Define the critical path and state the reasons, why you choose that path.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.