Deutchlander Machine Company (DMC) makes two types of printing presses: a four-color litho and a two-color litho. Demand for both products is booming and exceeds DMC’s ability to satisfy it. Most raw materials are plentiful, but production is limited by three factors: a shortage of steel rollers, gear cutting capacity, and roller polishing capacity. Each four-color press requires 16 rollers, and each two-color press requires 8 rollers. The four-color presses require 30 hours of gear cutting and 8 hours of polishing time, and the two-color presses require 12 hours of gear cutting and 3 hours of polishing time. DMC is able to buy 100 rollers per week, and it has 160 hours of gear cutting time and 40 hours of polishing time available per week. To avoid harming long-term sales, DMC does not want to raise prices. At current prices DMC will earn a profit of DM24,000 on each four-color press made and DM10,000 on each two-color press made. So as not to abandon either product market, DMC also wants to produce at least two units of each press each week. REQUIRED a. Formulate DMC’s problem as a linear program to maximize its profit b. Solve the problem (using the simplex method) and explain in words DMC’s optimal solution

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter10: Introduction To Simulation Modeling
Section: Chapter Questions
Problem 35P: Lemingtons is trying to determine how many Jean Hudson dresses to order for the spring season....
icon
Related questions
Question
100%

Deutchlander Machine Company (DMC) makes two types of printing presses: a four-color litho
and a two-color litho. Demand for both products is booming and exceeds DMC’s ability to satisfy
it. Most raw materials are plentiful, but production is limited by three factors: a shortage of steel
rollers, gear cutting capacity, and roller polishing capacity. Each four-color press requires 16
rollers, and each two-color press requires 8 rollers. The four-color presses require 30 hours of
gear cutting and 8 hours of polishing time, and the two-color presses require 12 hours of gear
cutting and 3 hours of polishing time. DMC is able to buy 100 rollers per week, and it has 160
hours of gear cutting time and 40 hours of polishing time available per week. To avoid harming
long-term sales, DMC does not want to raise prices. At current prices DMC will earn a profit of
DM24,000 on each four-color press made and DM10,000 on each two-color press made. So as
not to abandon either product market, DMC also wants to produce at least two units of each
press each week.
REQUIRED
a. Formulate DMC’s problem as a linear program to maximize its profit
b. Solve the problem (using the simplex method) and explain in words DMC’s optimal
solution

Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,