Draw Gantt chart for the following project and determine the duration of the project, where the working hours (4 hours in day) and the production efficiency (52%). Precedence Quantity or volume Standard Production No. of Activity Activity of the Activity (ton) Rate (ton/hour.man) workers A 10 0.4 4 В A 8 0.22 C 37 0.35 6. D B 55 0.49 20 E В, С 17 0.63 2 F A, C 88 0.71 12

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
icon
Concept explainers
Topic Video
Question
Draw Gantt chart for the following project and determine the duration of
the project, where the working hours (4 hours in day) and the production efficiency
(52%).
Precedence
Quantity or volume
Standard Production
No. of
Activity
Activity
of the Activity (ton)
Rate (ton/hour.man)
workers
A
10
0.4
4
A
8
0.22
C
37
0.35
6.
D
В
55
0.49
20
E
В, С
17
0.63
2
F
A, C
88
0.71
12
Transcribed Image Text:Draw Gantt chart for the following project and determine the duration of the project, where the working hours (4 hours in day) and the production efficiency (52%). Precedence Quantity or volume Standard Production No. of Activity Activity of the Activity (ton) Rate (ton/hour.man) workers A 10 0.4 4 A 8 0.22 C 37 0.35 6. D В 55 0.49 20 E В, С 17 0.63 2 F A, C 88 0.71 12
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,