DURATION АCTIVITY SUCESSOR (WEEK) А-В (S-S),L-5 А-С (F-S),L-4 В-Е (F-S),L-3 С-Е (F-S),L31 D-E (F-S),L=0 E-F (F-S),L=0 А В 1 C 2 D 2 E F 2 1. Draw the precedence diagram for the schedule shown next. 2. Determine the duration of project required. 3. Determine the Total Float for each activities and give the critical path for this project. 4. Draw a bar chart.
DURATION АCTIVITY SUCESSOR (WEEK) А-В (S-S),L-5 А-С (F-S),L-4 В-Е (F-S),L-3 С-Е (F-S),L31 D-E (F-S),L=0 E-F (F-S),L=0 А В 1 C 2 D 2 E F 2 1. Draw the precedence diagram for the schedule shown next. 2. Determine the duration of project required. 3. Determine the Total Float for each activities and give the critical path for this project. 4. Draw a bar chart.
Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter3: Collection
Section: Chapter Questions
Problem 3.7P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781337402415
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781337402415
Author:
Gregory W Fletcher
Publisher:
Cengage Learning