Q/ The figure below shows the arrow diagram of the major events (A, B, C, D, E, F, G, H, I) of project, where each of them has the three estimates of duration (optimistic OP, most likely ML, pessimistic PE). Plan the project using PERT method and then answer the following questions: C(6,4,8), 3 I(2,5,8) G F |(1,2,3) 4,7,7) D B(6,5,7) (1,5,6) A 1 2 (1,2,3) H 6. (3,5,7) (2.4.6) 1) Indentify the critical path of network diagram and the mean time for the total duration of the project implementation. 2) Calculate the variance and the standard deviation of the mean time for the total duration of the project implementation. 3) What is the optimistic estimate and pessimistic estimate for the total duration of the project implementation.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Q/ The figure below shows the arrow diagram of the major events (A, B, C, D, E, F, G,
H, I) of project, where each of them has the three estimates of duration (optimistic
OP, most likely ML, pessimistic PE). Plan the project using PERT method and
then answer the following questions:
C(6,4,8),
I(2,5,8)
G
F
X4,7,7)(1,2,3)
D
B(6,5,7) (1,5,6)
A
E
2
(1,2,3)
H
6.
(3,5,7)
(2.4.6)
1) Indentify the critical path of network diagram and the mean time for the total
duration of the project implementation.
2) Calculate the variance and the standard deviation of the mean time for the total
duration of the project implementation.
3) What is the optimistic estimate and pessimistic estimate for the total duration of
the project implementation.
Transcribed Image Text:Q/ The figure below shows the arrow diagram of the major events (A, B, C, D, E, F, G, H, I) of project, where each of them has the three estimates of duration (optimistic OP, most likely ML, pessimistic PE). Plan the project using PERT method and then answer the following questions: C(6,4,8), I(2,5,8) G F X4,7,7)(1,2,3) D B(6,5,7) (1,5,6) A E 2 (1,2,3) H 6. (3,5,7) (2.4.6) 1) Indentify the critical path of network diagram and the mean time for the total duration of the project implementation. 2) Calculate the variance and the standard deviation of the mean time for the total duration of the project implementation. 3) What is the optimistic estimate and pessimistic estimate for the total duration of the project implementation.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.