f a person performing a task has been achieving an 75 percent learning curve and if it took 53 minutes to produce the first unit, the total time to produce 800 units will be 4165.3 minutes. True False

Survey Of Economics
10th Edition
ISBN:9781337111522
Author:Tucker, Irvin B.
Publisher:Tucker, Irvin B.
Chapter6: Proudction Costs
Section: Chapter Questions
Problem 20SQ
icon
Related questions
Question

If a person performing a task has been achieving an 75 percent learning curve and if it took 53 minutes to produce the first unit, the total time to produce 800 units will be 4165.3 minutes.

True

False

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Total Cost
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Survey Of Economics
Survey Of Economics
Economics
ISBN:
9781337111522
Author:
Tucker, Irvin B.
Publisher:
Cengage,
Economics For Today
Economics For Today
Economics
ISBN:
9781337613040
Author:
Tucker
Publisher:
Cengage Learning
Micro Economics For Today
Micro Economics For Today
Economics
ISBN:
9781337613064
Author:
Tucker, Irvin B.
Publisher:
Cengage,
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Microeconomic Theory
Microeconomic Theory
Economics
ISBN:
9781337517942
Author:
NICHOLSON
Publisher:
Cengage