Q: Please explain why large initial separations on the EV S-Curve between the lines for ACWP and BCWP…
A: EV S-Curve: In EV S curve (Earned Value S curve), the cost data is plotted on the graph cost vs time…
Q: Pertaining to the time-between-events control chart, which statement is INcorrect? Select one: O a.…
A: A control chart can be defined as a graph that is used to study how a process changes over time.…
Q: Consider a project with seven tasks. Three tasks - tasks 3, 4, and 5 - require a specific resource…
A: Project duration is described as the time taken up to complete a project and it is measured in terms…
Q: (d) Determine and state the critical path for this project. (e) What are the expected time and the…
A:
Q: What is achieved when multiple methods are used in combination with one another yielding more…
A: Marketing communication often called Marcom can be stated as the messages and media that the…
Q: Given the following Product Structure Record, the number of G's required for each A is A B D E (2)…
A: A product structure record is described as the classification of items in a hierarchical manner,…
Q: What comprises a Project Management Plan? What is the link with the Project Feasibility Study? What…
A: The purpose of a project management plan is to determine the outcome of the project and to determine…
Q: The decline of rail travel started for two main reasons cars and airplanes. Explain this statement,…
A: A transportation system could be described as a collection of elements and their interconnections…
Q: Item X is a standard item stocked in a company's inventory of component parts. Each year the firm,…
A: Storage cost is the cost incurred when the inventory or the finished products are managed and stored…
Q: . Solve the following linear programming model graphically: minimize Z = 3x, + 6x2 kubject to 3x +…
A: Linear programming is used to find the maximised profits or minimum costs for the resources which…
Q: A supplier ships goods from Richmond, VA to three market places in 3 cities (Chicago, IL; Athens,…
A: Here in this case we are provided with 3 market place and rates according to the weight. Also…
Q: Calculate the EVPI. Show clear workings piease Cost Either 0 or 1 Failiure SO Leave the plant open…
A: EVPI is known as expected monetary vale. It is calculated simply the sum of the maximum payoff…
Q: What decision should be made by the optimist? What decision should be made by the conservative? What…
A: Solution 1:- Step 1:- Find the maximum value from each row. Step 2:- Find the maximum value from all…
Q: following outcomes over the last seven months: Quantity Sold Price Advertising 8500 $ 2 $ 2,800 4700…
A: given,
Q: 3,000 3,000 The marketing department of the company forecasts a demand of 80,000 bottles of A,…
A: Let x= T1 town Let y= T2 town
Q: 1. LIST ANY FIVE DIFFERENCES BETWEEN TWO TYPES OF PRODUCTION SYSTEMS. “MAKE TO ORDER" AND “ MAKE TO…
A:
Q: Required: 1. Prepare a production cost report for the molding department. 2. Prepare a production…
A: Process costing: It is a type of costing method, where the direct costs are accumulated and indirect…
Q: Item А C D E F G H Lead 4 4 5 6 4 3 time What is the customer response time if all purchased items…
A: Detailed solution is given in Step 2
Q: QI: Draw the arrow diagram for the following activities and show the critical path activity duration…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES =…
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
Q: There should be a list of the five risk-control methodologies, with short descriptions of each.
A: Risk control or commonly known as the risk response planning can be classified into five steps which…
Q: entence - Defect arrival pattern during machine testing : - Phase-based defect removal pattern :…
A: Some businesses use quality metrics in-process to keep track of when defects first appear during…
Q: (ou are working in a small, student-run company that sends out merchandise with university pranding…
A:
Q: Examine, how the destination can benefit local community and the government (Tourism impacts) and…
A: Tourism can be stated as the cultural and economic event or occurrence which generally requires of…
Q: Prove the following using strong induction. Suppose you are gifted a collection of 3n pokéballs; all…
A: A ball is a roundabout item that can be utilized in an assortment of ways. It is used in ball games…
Q: Each day, northern, central, and southern California use 120, 140, and 160 billion gallons of water…
A: Water is comprised of hydrogen and oxygen, and it exists in vaporous, fluid, and strong states.…
Q: subject to X, - 2x, + x, 2 20 2x1 + 4x2 + X3 = 50 and X, 2 0, X 2 0, X3 2 0. (a) Using the Big M…
A: “Since you have posted a question with multiple sub-parts, we will solve first three subparts for…
Q: a) Draw the project network and determine the critical path(s) using AOA method and determine the…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Provide a detailed discussion on the impact of time-based strategies in obtaining efficient supply…
A: In the corporate environment of the firm, although the business has realized the status of…
Q: What is the risk analysis for a Restaurant (culture restaurant)?
A: The term risk can be understood as an occurrence of undesirable outcome. Risk is a negative outcome…
Q: What the main material handling equipments used in warehouse and inventory managemen?.
A: An inventory or a warehouse is the production and storage unit of a company and it comprises many…
Q: Differentiate supply chain management to demand chain management. Explain thoroughly.
A: Supply chain management (SCM) is the one of the utmost important purposes of business that emphasis…
Q: To remain competitive, several fast food businesses began to diversify their menus. While this has…
A: To be determined: what ways does expanding menu selections complicate inventory management.…
Q: How would a company as successful at foreign market entry as IKEA could have failed in Japan?
A: IKEA, a Swedish multinational corporation that develops and distributes ready-to-assemble furniture…
Q: he production function q = 9K0.8L0.1 exhibits [increasing return to scale, constant return to scale,…
A: given, The production function q = 9K0.8L0.1
Q: consider the following reliability analysis for the variable customer difference. What could you…
A: Consistency over the course of time (test-retest unwavering quality), between things (interior…
Q: Barry’s Brakes is looking to hire workers to assemble the brake assemblies it produces. Barry has…
A: The basic concept behind the selection of a right number of employees indicating the highest unit…
Q: Case Study: Strategic Workforce Planning at Dutch Railway Infrastructure Manager- ProRail Traffic…
A: To be determined: The recommendations can be made in this situation by the legal services manager.…
Q: Solve using: 1. Pure/Mixed Strategy 2. Domination
A:
Q: A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and…
A: Utilization measuring the proportion between actual usable time and total available time. A…
Q: The Demand for the 50 Kg Maize meal bag at Shoprite is 4000 units per month, Shoprite incurs a fixed…
A:
Q: a. Develop a network model of the distribution system for this problem. b. Solve the problem to…
A: Steps for part b
Q: Lovely Apparel must decide how many sets of assorted summer wear to order for its three stores.…
A: given,
Q: How does managing project management relationships the key to improving project management skills?
A: The business environment is getting hyper competitive day by day and it is leading to a huge demand…
Q: Discuss the differences between rigid and nonrigid containers. Discuss the importance of load…
A: Rigid containers are gadgets inside which the master containers or individual items are safely put…
Q: Bricfly describe TPS pillar 1
A: Quality manufacturing is essential for attracting customers. Such manufacturing practices help to…
Q: The following statement was included in a letter that went out to all employees of a certain…
A: Here the individual has simply stated his position and introduces her/him with all his staffs and…
Q: QI: Draw the arrow diagram for the following activities and show the critical path: activity…
A: Activity Immediate Predecessors Duration A - 5 B A 4 C A 7 D B 5 E B 4 F C 8 G C 3 H…
Q: a. ABC reports annual sales of $ 5 million, annual cost of goods sold is $ 2 million. Inventory is $…
A:
Q: 4. ( and deluxe. The estimated unit price on the standard, professional and deluxe model is $40,…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Step by step
Solved in 3 steps
- Case Study SMT’s Negotiation with IBM SMT and one other, much larger company were asked by IBM to bid on 80 more units of a particular computer product. The RFQ (request for quote) asked that the overall bid be broken down to show the hourly rate, the parts and materials component in the price, and any charges for subcontracted services. SMT quoted $1.62 million and supplied the cost breakdown as requested. The second company submitted only one total figure, $5 million, with no cost breakdown. The decision was made to negotiate with SMT. The IBM negotiating team included two purchasing managers and two cost engineers. One cost engineer had developed manufacturing cost estimates for every component, working from engineering drawings and cost-data books that he had built up from previous experience and that contained time factors, both setup and run times, for a large variety of operations. He estimated materials costs by working both from data supplied by the IBM corporate purchasing…Case Study SMT’s Negotiation with IBM SMT and one other, much larger company were asked by IBM to bid on 80 more units of a particular computer product. The RFQ (request for quote) asked that the overall bid be broken down to show the hourly rate, the parts and materials component in the price, and any charges for subcontracted services. SMT quoted $1.62 million and supplied the cost breakdown as requested. The second company submitted only one total figure, $5 million, with no cost breakdown. The decision was made to negotiate with SMT. The IBM negotiating team included two purchasing managers and two cost engineers. One cost engineer had developed manufacturing cost estimates for every component, working from engineering drawings and cost-data books that he had built up from previous experience and that contained time factors, both setup and run times, for a large variety of operations. He estimated materials costs by working both from data supplied by the IBM corporate purchasing…Ongoing Clients 75 Client Attrition Rate for MRR: 30% Avg MRR from New Business per Rep $ 15,000 Average Deal Size (MRR) $ 12,000 % of SQLs that Close 16% % MQLs that Become SQLs 9% # of Reps on Team 5 Avg Growth Deals per Rep per Month 2 Avg MQL per Month 600 Avg MRR from Growth Deals per Rep $ 20,000 What is the NEW BUSINESS MRR Current Year $ per Rep?
- 1) constuct a scatter diagram 2) Estimate fixed costs and variable costs3. ere the firm works with the customer to design the product, which is then made from purchased material, parts, and components? Multiple Choice Assemble-to-order Custom order Make-to-stock Engineer-to-order Make-to-orderWHAT IS THE PARETO DIAGRAM FOR BELOW TABLE? S.N. MAJOR PROBLEMS JUNE 1 JUNE 8 JUNE 15 JUNE 22 JUNE 29 JULY 6 JULY 13 JULY 20 JULY 27 TOTAL 1 Out of stock 4 4 5 8 7 9 8 13 12 70 2 Pricing error 3 3 7 1 2 3 4 3 1 27 3 Maintenance layout 3 5 5 3 5 7 6 6 7 48 4 Quality issue 7 7 5 4 2 0 0 0 0 25 5 Employee behavior 2 1 1 0 1 1 1 0 1 8 total 19 20 23 16 17 20 19 22 22
- QUESTION 3 Mr. John produces a special type of shoes on an assembly line. The process involves eightdifferent tasks. Mr. John would like to increase productivity on this line and asked you for someassistance. He would like to balance the assembly line in order to reduce idle time and increaseefficiency. a. What information would you need in order to demonstrate to Mr. John how to balancethe assembly line? b. Setup an example that will be used to demonstrate to Mr. John how to balance the line.c. Using the example that you setup in “b” above, demonstrate to Mr. John how tobalance the line using the LOT heuristics.d. Based on the example above, calculate the efficiency of the line.Question 2: a) If the three activities of System Engineering Management are expressed in the form of a Venn Diagram, then the intersection between "Systems Engineering process" and "Lifecycle Integration" is termed as what? Draw the Venn diagram and discuss the different sections. b) From the System Engineering perspective, what criteria should a life cycle meet? And when is a system’s state said to have attained equilibrium and stability?NO GPT, HAND WRITTEN PLEASE
- 23.May I know the correct option?Question 4 Using a relevant diagram, analyse and discuss the determination of effective and efficient processesTOPIC 5 - PRODUCT & SERVICE DESIGN a.Elaborate the elements for an effective design process.b. Discuss with an appropriate diagram, the meaning of design simplification in the production design.c. MAFTech assembles smart devices part from four major components arranged as follows:(image added)i. If MAFTech has decided only to use one vendor to supply all four components, analyze for which vendor should be selected.ii. Define the decision made, if all the components were assembled in series. (sequence of A-B-C-D and not sub-process B feed to C as above)d. Elaborate service concept and service package with a relatable example from any service type/industry.