following. Given the diagram above, please answer the following. 7. How many possible paths are there from the start to the end of the project? 8. Which tasks are on the critical path of the PERT chart above? 9. What is the slack time for tasks C, D and G? 10. The person working on task C tells the project manager he can't start work until one day

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Part II-A. Given the activity table below, prepare its
corresponding Gantt Chart and PERT diagram.
Activity Predecessor Days
A
1
B
4
C
2
D
1
E
1
F
5
G
3
H
3
I
1
J
2
K
1
L
3
M
2
A
A
C
B, D
E
E
E
H
G, I
J
J
L
Part II-B. Based on your illustration, please answer the
following.
Given the diagram above, please answer the following.
7. How many possible paths are there from the start to the end of the project?
8. Which tasks are on the critical path of the PERT chart above?
9. What is the slack time for tasks C, D and G?
10. The person working on task C tells the project manager he can't start work until one day
after the scheduled starting date. What impact would this have on the completion date of the
project? Why?
11. Task A will be delayed by 2 days because some equipment has arrived late. If the project
manager still wants to finish the project within the original time frame, he will need to
shorten the time for one or more of the tasks. What steps can he take to reduce the number of
days allocated to a task?
12. The project manager decides to reduce the time needed for tasks D and F by one day each.
How effective will this reduction be in achieving his aim of maintaining the original finish
time for the project?
Transcribed Image Text:Part II-A. Given the activity table below, prepare its corresponding Gantt Chart and PERT diagram. Activity Predecessor Days A 1 B 4 C 2 D 1 E 1 F 5 G 3 H 3 I 1 J 2 K 1 L 3 M 2 A A C B, D E E E H G, I J J L Part II-B. Based on your illustration, please answer the following. Given the diagram above, please answer the following. 7. How many possible paths are there from the start to the end of the project? 8. Which tasks are on the critical path of the PERT chart above? 9. What is the slack time for tasks C, D and G? 10. The person working on task C tells the project manager he can't start work until one day after the scheduled starting date. What impact would this have on the completion date of the project? Why? 11. Task A will be delayed by 2 days because some equipment has arrived late. If the project manager still wants to finish the project within the original time frame, he will need to shorten the time for one or more of the tasks. What steps can he take to reduce the number of days allocated to a task? 12. The project manager decides to reduce the time needed for tasks D and F by one day each. How effective will this reduction be in achieving his aim of maintaining the original finish time for the project?
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.