HiTech Products manufactures three types of remote-control devices: Economy, Standard, and Deluxe. The company, which uses activity-based costing, has identified five activities (and related cost drivers). Each activity, its budgeted cos and related cost driver is identified below. Activity Material handling Cost Cost Driver Number of 2$ 225,000 2,475,000 parts Number of parts Material insertion

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter4: Activity-based Costing
Section: Chapter Questions
Problem 11E: Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in...
icon
Related questions
Question
100%

Please help me get the correct and complete solutions for each item. Answer are already provided but I couldn't figure out what's wrong in my solutions. Please help me. For nos. 8-13 only

HiTech Products manufactures three types of remote-control devices: Economy,
Standard, and Deluxe. The company, which uses activity-based costing, has
identified five activities (and related cost drivers). Each activity, its budgeted cost,
and related cost driver is identified below.
Activity
Material handling
Cost
$
225,000
2,475,000
Cost Driver
Number of
parts
Number of
parts
Machine hours
Material insertion
Automated machinery
Finishing
840,000
170,000
Direct labor
hours
Orders shipped
Packaging
170,00
Total
$3,880,00
The following information pertains to the three product lines for next year:
Standar
d
5,000
500
15
Economy
Deluxe
Units to be produced
Orders to be shipped
Number of parts per
unit
Machine hours per unit
Labor hours per unit
10,000
1,000
10
2,000
200
25
1
3
2
2
2
5. What is HiTech's cost application rate for the material-handling activity?
A. $1.00 per part.
B. $2.25 per part.
C. $6.62 per labor hour.
D. $13.23 per part.
E. A rate other than those listed above.
6. What is HiTech's cost application rate for the automated machinery activity?
A. $24.00 per machine hour.
B. $24.50 per labor hour.
C. $49.42 per unit.
D. $50.00 per machine hour.
E. A rate other than those listed above.
7. What is HiTech's cost application rate for the finishing activity?
A. $5.00 per labor hour.
B. $5.00 per machine hour.
C. $5.00 per unit.
D. $7.50 per unit.
E. A rate other than those listed above.
Transcribed Image Text:HiTech Products manufactures three types of remote-control devices: Economy, Standard, and Deluxe. The company, which uses activity-based costing, has identified five activities (and related cost drivers). Each activity, its budgeted cost, and related cost driver is identified below. Activity Material handling Cost $ 225,000 2,475,000 Cost Driver Number of parts Number of parts Machine hours Material insertion Automated machinery Finishing 840,000 170,000 Direct labor hours Orders shipped Packaging 170,00 Total $3,880,00 The following information pertains to the three product lines for next year: Standar d 5,000 500 15 Economy Deluxe Units to be produced Orders to be shipped Number of parts per unit Machine hours per unit Labor hours per unit 10,000 1,000 10 2,000 200 25 1 3 2 2 2 5. What is HiTech's cost application rate for the material-handling activity? A. $1.00 per part. B. $2.25 per part. C. $6.62 per labor hour. D. $13.23 per part. E. A rate other than those listed above. 6. What is HiTech's cost application rate for the automated machinery activity? A. $24.00 per machine hour. B. $24.50 per labor hour. C. $49.42 per unit. D. $50.00 per machine hour. E. A rate other than those listed above. 7. What is HiTech's cost application rate for the finishing activity? A. $5.00 per labor hour. B. $5.00 per machine hour. C. $5.00 per unit. D. $7.50 per unit. E. A rate other than those listed above.
8. What is HiTech's cost application rate for the packaging activity?
A. $4.86 per machine hour.
B. $5.00 per labor hour.
C. $10.00 per unit.
D. $100.00 per order shipped.
E. A rate other than those listed above.
9. Under an activity-based costing system, what is the per-unit cost of
Economy?
A. $141.
B. $164.
C. $225.
D. $228.
E. An amount other than those listed above.
10. Under an activity-based costing system, what is the per-unit cost of
Standard?
A. $164.
B. $228.
C. $272.
D. $282.
E. An amount other than those listed above.
11. Under an activity-based costing system, what is the per-unit cost of Deluxe?
A. $272.
B. $282.
C. $320.
D. $440.
E. An amount other than those listed above.
12. Assume that HiTech is using a volume-based costing system, and the
preceding manufacturing costs are applied to all products based on direct
labor hours. How much of the preceding cost would be assigned to Deluxe?
A. $456,471.
B. $646,471.
C. $961,176.
D. $1,141,176.
E. An amount other than those listed above.
13. Assume that HiTech is using a volume-based costing system, and the
preceding manufacturing costs are applied to all products based on direct
labor hours. How much of the preceding cost would be assigned to Standard?
A. $456,471.
B. $646,471.
C. $961,176.
D. $1,141,176.
E. An amount other than those listed above.
Transcribed Image Text:8. What is HiTech's cost application rate for the packaging activity? A. $4.86 per machine hour. B. $5.00 per labor hour. C. $10.00 per unit. D. $100.00 per order shipped. E. A rate other than those listed above. 9. Under an activity-based costing system, what is the per-unit cost of Economy? A. $141. B. $164. C. $225. D. $228. E. An amount other than those listed above. 10. Under an activity-based costing system, what is the per-unit cost of Standard? A. $164. B. $228. C. $272. D. $282. E. An amount other than those listed above. 11. Under an activity-based costing system, what is the per-unit cost of Deluxe? A. $272. B. $282. C. $320. D. $440. E. An amount other than those listed above. 12. Assume that HiTech is using a volume-based costing system, and the preceding manufacturing costs are applied to all products based on direct labor hours. How much of the preceding cost would be assigned to Deluxe? A. $456,471. B. $646,471. C. $961,176. D. $1,141,176. E. An amount other than those listed above. 13. Assume that HiTech is using a volume-based costing system, and the preceding manufacturing costs are applied to all products based on direct labor hours. How much of the preceding cost would be assigned to Standard? A. $456,471. B. $646,471. C. $961,176. D. $1,141,176. E. An amount other than those listed above.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College