Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 120 hours will be required to complete the project. The firm's three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at least 40% of the total number of hours assigned to the two senior designers. To provide label designing experience for Sarah, the junior designer must be assigned at least 15% of the total project time. However, the number of hours assigned to Sarah must not exceed 25% of the total number of hours assigned to the two senior designers. Due to other project commitments, Lisa has a maximum of 50 hours available to work on this project. Hourly wage rates are $30 for Lisa, $25 for David, and $18 for Sarah. (a) Formulate a linear program that can be used to determine the number of hours each graphic designer should be assigned to the project to minimize total cost (in dollars). (Assume L is the number of hours Lisa is assigned to the project, D is the number of hours David is assigned to the project, and S is the number of hours Sarah is assigned to the project.) Min 30L +25D+18S s.t. Minimum Lisa Minimum Sarah L≥0.4(L+D) S≥0.15(D+L+S) Maximum Lisa L≤ 50 Maximum Sarah Total Time L, D, S≥ 0 S≤0.25(L+D) L+D+S 120 (b) How many hours should be assigned to each graphic designer? Lisa's Hours David's Hours Sarah's Hours What is the total cost (in dollars)? $ × hours × hours × hours

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter16: Government Regulation
Section: Chapter Questions
Problem 8E
icon
Related questions
Question
Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 120 hours will be required to complete the project. The firm's three graphic designers available for assignment to this project
are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at least 40% of the total number of hours assigned
to the two senior designers. To provide label designing experience for Sarah, the junior designer must be assigned at least 15% of the total project time. However, the number of hours assigned to Sarah must not exceed 25% of the total number of hours assigned to the
two senior designers. Due to other project commitments, Lisa has a maximum of 50 hours available to work on this project. Hourly wage rates are $30 for Lisa, $25 for David, and $18 for Sarah.
(a) Formulate a linear program that can be used to determine the number of hours each graphic designer should be assigned to the project to minimize total cost (in dollars). (Assume L is the number of hours Lisa is assigned to the project, D is the number of hours
David is assigned to the project, and S is the number of hours Sarah is assigned to the project.)
Min 30L +25D+18S
s.t.
Minimum Lisa
Minimum Sarah
L≥0.4(L+D)
S≥0.15(D+L+S)
Maximum Lisa
L≤ 50
Maximum Sarah
Total Time
L, D, S≥ 0
S≤0.25(L+D)
L+D+S 120
(b) How many hours should be assigned to each graphic designer?
Lisa's Hours
David's Hours
Sarah's Hours
What is the total cost (in dollars)?
$
× hours
× hours
× hours
Transcribed Image Text:Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 120 hours will be required to complete the project. The firm's three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at least 40% of the total number of hours assigned to the two senior designers. To provide label designing experience for Sarah, the junior designer must be assigned at least 15% of the total project time. However, the number of hours assigned to Sarah must not exceed 25% of the total number of hours assigned to the two senior designers. Due to other project commitments, Lisa has a maximum of 50 hours available to work on this project. Hourly wage rates are $30 for Lisa, $25 for David, and $18 for Sarah. (a) Formulate a linear program that can be used to determine the number of hours each graphic designer should be assigned to the project to minimize total cost (in dollars). (Assume L is the number of hours Lisa is assigned to the project, D is the number of hours David is assigned to the project, and S is the number of hours Sarah is assigned to the project.) Min 30L +25D+18S s.t. Minimum Lisa Minimum Sarah L≥0.4(L+D) S≥0.15(D+L+S) Maximum Lisa L≤ 50 Maximum Sarah Total Time L, D, S≥ 0 S≤0.25(L+D) L+D+S 120 (b) How many hours should be assigned to each graphic designer? Lisa's Hours David's Hours Sarah's Hours What is the total cost (in dollars)? $ × hours × hours × hours
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning