Luna Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is P3,168,000, of which P864,000 is fixed overhead. The actual results for the year are as follows:
Q: Franklin manufactures pipes and applies manufacturing overhead costs to production at a budgeted…
A: The amount of manufacturing overhead allocated to all the jobs during June 2020 is $72000
Q: Aneto productions uses a predetermined overhead recovery rate based on hours. A summary of the…
A: This question deals with the calculation of budgeted level of machine hour. We have been given…
Q: The following information relates to the Finishing department of Tom company for the fourth quarter:…
A: The question is based on the concept of Cost Accounting.
Q: The company budgeted for production of 2,600 units in September, but actual production was 2,500…
A: Labor rate variance = (Standard rate - Actual rate) * Actual hours
Q: Vin Diesel Company uses a standard costing system in which it applies manufacturing overhead to…
A: Total budgeted fixed factory overhead = Total applied factory overhead - Total Variable factory…
Q: XYZ Corporation uses a predetermined overhead application rate of P.30 per direct labor hour. During…
A: The predetermined overhead rate is calculated as estimated overhead cost divided by budgeted…
Q: Mona moobl3 Ltd operates a standard costing system and absorbs overheads on the basis of standard…
A: Option b is correct.
Q: Botosan Factory has budgeted factory overhead for the year at $666,573, and budgeted direct labor…
A: Overhead allocation refers to the distribution of the indirect costs for the produced goods and in…
Q: Antuan Company set the following standard costs per unit for its product. $ 12.00 Direct materials…
A: When the actual price is higher than the standard price the price variance is unfavorable .…
Q: World Company expects to operate at 80% of its productive capacity of 50,000 units per month. At…
A: Overheads Volume Variance = Applied Fixed Overhead - Budgeted Fixed Overhead Overhead Controllable…
Q: Avery Company uses a predetermined overhead rate based on direct labor hours. For the month of…
A: Manufacturing overhead: It is the indirect cost incurred as a part of manufacturing the products.…
Q: egan, Incorporated uses the following standard costs per unit for one of its products: Direct labor…
A: The difference between the actual amount of an expense and the expected (or budgeted) amount of an…
Q: Vin Diesel Company uses a standard costing system in which it applies manufacturing overhead to…
A: Formula: Total budgeted fixed factory overhead = Total applied factory overhead - Total Variable…
Q: herokee Company applies factory overhead on the basis of direct labor hours. Budget and actual data…
A: Budgeted Factory overhead cost per unit = Budgeted Factory overhead cost / Budgeted Direct labor…
Q: Newark Plastics Corporation developed its overhead application rate from the annual budget. The…
A: The question is based on the concept of Cost Accounting. As per the Bartleby guidelines we are…
Q: The data below relate to the month of November for Badong, Inc. which uses a standard cost system:…
A: Labor usage variance= Actual hours * Standard rate per hour - Actual hours * Actual rate per hou
Q: NEW JERSEY CORP. uses a standard cost system in which manufacturing overhead is applied to units of…
A: Denominator level of activity is calculated by dividing the total budgeted overhead with the…
Q: XYZ Corporation uses a predetermined overhead application rate of P.30 per direct labor hour. During…
A: Actual hours = applied overhead / predetermined overhead application rate = P363,000 /0.30 =…
Q: Dubberly Corporation's cost formula for its manufacturing overhead is $32,400 per month plus $54 per…
A: Formulas; Budgeted Manufacturing Overhead = Manufacturing overhead + (Rate per Machine hours x…
Q: Acme Company's production budget for August is 19,100 units and includes the following component…
A: The variation between actual results and the budget or standard is referred as variance.
Q: Newbill Enterprises recently used 34,000 labor hours to produce 11,200 completed units. According to…
A: Variance refers to a change between the expected value and the actual result. This term is usually…
Q: World Company expects to operate at 80% of its productive capacity of 50,000 units per month. At…
A:
Q: Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current…
A: Variance is the difference between the actual and budgeted figures. These can be both Favorable (F)…
Q: Oerstman, Inc. uses a standard costing system and develops its overhead rates from the current…
A: 1. Compute fixed overhead spending variance: Fixed overhead spending variance = Actual fixed…
Q: Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current…
A: Fixed overhead Spending variance = Budgeted Fixed overhead - Actual Fixed Overhead Fixed overhead…
Q: During the year, 5,600 units were produced, 18,340 hours were worked, and the actual manufacturing…
A: Variable manufacturing overhead rate = Budgeted variable manufacturing overhead / Budgeted hours =…
Q: Antuan Company set the following standard costs per unit for its product. Direct materials (6 pounds…
A: Calculation of Direct labor rate variance :- Direct labor rate variance = (Standard rate - Actual…
Q: The following data pertains to the month of October for Elm. Co. when production was budgeted to be…
A: Direct material quantity variance is calculated by taking the difference between actual quantity at…
Q: In October, Pine Company reports 20,600 actual direct labor hours, and it incurs $257,000 of…
A: overhead volume variance = Standard hours - normal hours) × fixed overhead rate
Q: The following data pertains to the month of October for ElmCo. when production was budgeted to be…
A: Direct Material Quantity Variance It's the variance which occurs due to the change in the quantity…
Q: World Company expects to operate at 80% of its productive capacity of 50,000 units per month. At…
A: Fixed overhead per labor hour=$50,00025,000=$2
Q: Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for…
A: Favorable variance means the actual expenditure are lower than the budgeted expenditure.
Q: Zepol Company is planning to produce 600,000 power drills for the coming year. The company uses…
A: Overhead rates in the given case needs to be determined based on budgeted direct labor hours.
Q: Mona moobl3 Ltd operates a standard costing system and absorbs overheads on the basis of standard…
A: Overheads are the indirect costs related with the production and manufacturing. These costs can not…
Q: Langley Manufacturing Ltd. has budgeted fixed manufacturing overhead at $100,000 and per unit…
A: The question is based on the concept of Cost Accounting.
Q: Acme Company's production budget for August is 23,000 units and includes the following component…
A: The variance is the difference between the actual data and standard data.
Q: The following information relates to the Finishing department of Tom company for the fourth quarter:…
A:
Q: Vin Diesel Company uses a standard costing system in which it applies manufacturing overhead to…
A: Total budgeted fixed factory overhead = Total applied factory overhead - Total Variable factory…
Q: Justine Company budgeted total variable overhead costs at P180,000 for the current period. In…
A: Formula: Overhead rate per hour = Total estimated overhead / Total estimated Machine hours
Q: Are the answers correct?
A: Variances are computed by subtracting the budgeted costs from actual costs. When actual…
Q: Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current…
A: Actual overhead = $241,400 + $556,200 = $797600 Budgeted Fixed Overhead = Standard variable overhead…
Q: Acme Company's production budget for August is 17,500 units and includes the following component…
A: Formula: Variable overhead spending variance = (Standard variable overhead rate per hour - Actual…
Q: The Ring The Bells, Co. collected the following data regarding production of one of its products.…
A: Variable overhead cost variance = Actual variable overhead - standard overhead for actual output
Q: At the beginning of the year, Smith Company budgeted overhead of $129,600 as well as 13,500direct…
A: As per the honor code, we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit…
Q: The data below relate to the month of November for Badong, Inc. which uses a standard cost system:…
A: Two-way analysis takes into account two variances: Overhead controllable variance and overhead…
Q: Zepol Company is planning to produce 600,000 power drills for the coming year. The company uses…
A: Overhead refers to the ongoing costs to operate a business but excludes the direct costs associated…
Q: Ribo Company’s budgeted total variable overhead is at P180,000 for the current period. In addition,…
A: SOLUTION- OVERHEAD RATE = TOTAL VARIABLE OVERHEADS +FACTORY RENT +DEPRECIATION ON FACTORY…
Q: Overhead rate is 42 per machine hour based on budgeted OH of 745,000. During the period, direct…
A:
Please put down the solution. Thank you!
Step by step
Solved in 3 steps
- Moleno Company produces a single product and uses a standard cost system. The normal production volume is 120,000 units; each unit requires 5 direct labor hours at standard. Overhead is applied on the basis of direct labor hours. The budgeted overhead for the coming year is as follows: At normal volume. During the year, Moleno produced 118,600 units, worked 592,300 direct labor hours, and incurred actual fixed overhead costs of 2,150,400 and actual variable overhead costs of 1,422,800. Required: 1. Calculate the standard fixed overhead rate and the standard variable overhead rate. 2. Compute the applied fixed overhead and the applied variable overhead. What is the total fixed overhead variance? Total variable overhead variance? 3. CONCEPTUAL CONNECTION Break down the total fixed overhead variance into a spending variance and a volume variance. Discuss the significance of each. 4. CONCEPTUAL CONNECTION Compute the variable overhead spending and efficiency variances. Discuss the significance of each.At the beginning of the year, Lopez Company had the following standard cost sheet for one of its chemical products: Lopez computes its overhead rates using practical volume, which is 80,000 units. The actual results for the year are as follows: (a) Units produced: 79,600; (b) Direct labor: 158,900 hours at 18.10; (c) FOH: 831,000; and (d) VOH: 112,400. Required: 1. Compute the variable overhead spending and efficiency variances. 2. Compute the fixed overhead spending and volume variances.A company estimates its manufacturing overhead will be $840,000 for the next year. What is the predetermined overhead rate given each of the following Independent allocation bases? Budgeted direct labor hours: 90,615 Budgeted direct labor expense: $750000 Estimated machine hours: 150,000
- Shinto Corp. uses a standard cost system and manufactures one product. The variable costs per product follow: Budgeted fixed overhead costs for the month are $4,000, and Shinto expected to manufacture 2,000 units. Actual production, however, was only 1,800 units. Materials prices were 10% over standard, and labor rates were 5% over standard. Of the factory overhead expense, only 80% was used, and fixed overhead was $100 over budget. The actual variable overhead cost was $4,800. In materials usage, 8% more parts were used than were allowed for actual production by the standard, and 6% more labor hours were used than were allowed. Required: Calculate the materials and labor variances. Calculate the variances for overhead by the four-variance method. (Hint: First compute the fixed and variable overhead rates per hour.)Nashler Company has the following budgeted variable costs per unit produced: Budgeted fixed overhead costs per month include supervision of 98,000, depreciation of 76,000, and other overhead of 245,000. Required: 1. Prepare a flexible budget for all costs of production for the following levels of production: 160,000 units, 170,000 units, and 175,000 units. 2. What is the per-unit total product cost for each of the production levels from Requirement 1? (Round each unit cost to the nearest cent.) 3. What if Nashler Companys cost of maintenance rose to 0.22 per unit? How would that affect the unit product costs calculated in Requirement 2?Business Specialty, Inc., manufactures two staplers: small and regular. The standard quantities of direct labor and direct materials per unit for the year are as follows: The standard price paid per pound of direct materials is 1.60. The standard rate for labor is 8.00. Overhead is applied on the basis of direct labor hours. A plantwide rate is used. Budgeted overhead for the year is as follows: The company expects to work 12,000 direct labor hours during the year; standard overhead rates are computed using this activity level. For every small stapler produced, the company produces two regular staplers. Actual operating data for the year are as follows: a. Units produced: small staplers, 35,000; regular staplers, 70,000. b. Direct materials purchased and used: 56,000 pounds at 1.5513,000 for the small stapler and 43,000 for the regular stapler. There were no beginning or ending direct materials inventories. c. Direct labor: 14,800 hours3,600 hours for the small stapler and 11,200 hours for the regular stapler. Total cost of direct labor: 114,700. d. Variable overhead: 607,500. e. Fixed overhead: 350,000. Required: 1. Prepare a standard cost sheet showing the unit cost for each product. 2. Compute the direct materials price and usage variances for each product. Prepare journal entries to record direct materials activity. 3. Compute the direct labor rate and efficiency variances for each product. Prepare journal entries to record direct labor activity. 4. Compute the variances for fixed and variable overhead. Prepare journal entries to record overhead activity. All variances are closed to Cost of Goods Sold. 5. Assume that you know only the total direct materials used for both products and the total direct labor hours used for both products. Can you compute the total direct materials and direct labor usage variances? Explain.
- Douglas Davis, controller for Marston, Inc., prepared the following budget for manufacturing costs at two different levels of activity for 20X1: During 20X1, Marston worked a total of 80,000 direct labor hours, used 250,000 machine hours, made 32,000 moves, and performed 120 batch inspections. The following actual costs were incurred: Marston applies overhead using rates based on direct labor hours, machine hours, number of moves, and number of batches. The second level of activity (the right column in the preceding table) is the practical level of activity (the available activity for resources acquired in advance of usage) and is used to compute predetermined overhead pool rates. Required: 1. Prepare a performance report for Marstons manufacturing costs in the current year. 2. Assume that one of the products produced by Marston is budgeted to use 10,000 direct labor hours, 15,000 machine hours, and 500 moves and will be produced in five batches. A total of 10,000 units will be produced during the year. Calculate the budgeted unit manufacturing cost. 3. One of Marstons managers said the following: Budgeting at the activity level makes a lot of sense. It really helps us manage costs better. But the previous budget really needs to provide more detailed information. For example, I know that the moving materials activity involves the use of forklifts and operators, and this information is lost when only the total cost of the activity for various levels of output is reported. We have four forklifts, each capable of providing 10,000 moves per year. We lease these forklifts for five years, at 10,000 per year. Furthermore, for our two shifts, we need up to eight operators if we run all four forklifts. Each operator is paid a salary of 30,000 per year. Also, I know that fuel costs about 0.25 per move. Assuming that these are the only three items, expand the detail of the flexible budget for moving materials to reveal the cost of these three resource items for 20,000 moves and 40,000 moves, respectively. Based on these comments, explain how this additional information can help Marston better manage its costs. (Especially consider how activity-based budgeting may provide useful information for non-value-added activities.)Flaherty, Inc., has just completed its first year of operations. The unit costs on a normal costing basis are as follows: During the year, the company had the following activity: Actual fixed overhead was 12,000 less than budgeted fixed overhead. Budgeted variable overhead was 5,000 less than the actual variable overhead. The company used an expected actual activity level of 12,000 direct labor hours to compute the predetermined overhead rates. Any overhead variances are closed to Cost of Goods Sold. Required: 1. Compute the unit cost using (a) absorption costing and (b) variable costing. 2. Prepare an absorption-costing income statement. 3. Prepare a variable-costing income statement. 4. Reconcile the difference between the two income statements.USD Inc. has established the following standard cost per unit: Although 10,000 units were budgeted, 12,000 units were produced. The Purchasing department bought 50,000 lb of materials at a cost of $237,500. Actual pounds of materials used were 46,000. Direct labor cost was $287,500 for 25,000 hours worked. Required: Make journal entries to record the materials transactions, assuming that the materials price variance was recorded at the time of purchase. Make journal entries to record the labor variances.
- Georgia Gasket Co. budgets 8,000 direct labor hours for the year. The total overhead budget is expected to amount to 20,000. The standard cost for a unit of the companys product estimates the variable overhead as follows: The actual data for the period follow: Using the four-variance method, calculate the overhead variances. (Hint: First compute the budgeted fixed overhead rate.)Adam Corporation manufactures computer tables and has the following budgeted indirect manufacturing cost information for the next year: If Adam uses the step-down (sequential) method, beginning with the Maintenance Department, to allocate support department costs to production departments, the total overhead (rounded to the nearest dollar) for the Machining Department to allocate to its products would be: a. 407,500. b. 422,750. c. 442,053. d. 445,000.Jillian Manufacturing Inc. manufactures a single product and uses a standard cost system. The factory overhead is applied on the basis of direct labor hours. A condensed version of the company’s flexible budget follows: The product requires 3 lb of materials at a standard cost of $5 per pound and 2 hours of direct labor at a standard cost of $10 per hour. For the current year, the company planned to operate at the level of 6,250 direct labor hours and to produce 3,125 units of product. Actual production and costs for the year follow: Required: For the current year, compute the factory overhead rate that will be used for production. Show the variable and fixed components that make up the total predetermined rate to be used. Prepare a standard cost card for the product. Show the individual elements of the overhead rate as well as the total rate. Compute (a) standard hours allowed for production and (b) under- or overapplied factory overhead for the year. Determine the reason for any under- or overapplied factory overhead for the year by computing all variances, using each of the following methods: Two-variance method Three-variance method (appendix) Four-variance method (appendix)