Meiger Mining, Inc., has just discovered two new mining sites for iron ore. Geologists and engineers have come up with the estimates on the following page regarding costs and ore yields if the mines are opened. Variable extraction costs per ton Fixed costs over the life of the mine: Blasting Construction Maintenance Restoration costs Total fixed costs Total tons of ore that can be extracted over the life of the mine: $ Site A 3.80 $150,000 225,000 25,000 40,000 $440,000 200,000 Site B $ 4.00 $185,000 240,000 20,000 35,000 $480,000 160,000 Meiger's owners currently demand a return of 20 percent of the market price of iron ore. Required: a. If the current market price of iron ore is $8.5 per ton, what is Meiger's target cost per ton? b-1. Given the $8.5 market price, compute the total cost per ton for Site A and Site B if fixed overhead costs are assigned to products on the basis of estimated tons of ore that can be extracted over the life of the mine. b-2. Should either of the mines be opened? c-1. The engineer working on Site B believes that if a custom conveyor system is installed, the variable extraction cost could be reduced to $3 per ton. The purchase price of the system is $25,000, but the costs to restore the site will increase to $45,000 if it is installed. Given the current $8 market price, compute the total cost per ton for site B. c-2. Should Meiger install the conveyor and open Site B?

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter14: Capital Structure Management In Practice
Section14.A: Breakeven Analysis
Problem 8P
icon
Related questions
Question
Meiger Mining, Inc., has just discovered two new mining sites for iron ore. Geologists and engineers have come
up with the estimates on the following page regarding costs and ore yields if the mines are opened.
Variable extraction costs per ton
Fixed costs over the life of the mine:
Blasting
Construction
Maintenance
Restoration costs
Total fixed costs
Total tons of ore that can be extracted over the life of the mine:
Site A
$ 3.80
$150,000
225,000
25,000
40,000
$440,000
200,000
Site B
$ 4.00
$185,000
240,000
20,000
35,000
$480,000
160,000
Meiger's owners currently demand a return of 20 percent of the market price of iron ore.
Required:
a. If the current market price of iron ore is $8.5 per ton, what is Meiger's target cost per ton?
b-1. Given the $8.5 market price, compute the total cost per ton for Site A and Site B if fixed overhead costs are
assigned to products on the basis of estimated tons of ore that can be extracted over the life of the mine.
b-2. Should either of the mines be opened?
c-1. The engineer working on Site B believes that if a custom conveyor system is installed, the variable extraction
cost could be reduced to $3 per ton. The purchase price of the system is $25,000, but the costs to restore the
site will increase to $45,000 if it is installed. Given the current $8 market price, compute the total cost per ton for
site B.
c-2. Should Meiger install the conveyor and open Site B?
Transcribed Image Text:Meiger Mining, Inc., has just discovered two new mining sites for iron ore. Geologists and engineers have come up with the estimates on the following page regarding costs and ore yields if the mines are opened. Variable extraction costs per ton Fixed costs over the life of the mine: Blasting Construction Maintenance Restoration costs Total fixed costs Total tons of ore that can be extracted over the life of the mine: Site A $ 3.80 $150,000 225,000 25,000 40,000 $440,000 200,000 Site B $ 4.00 $185,000 240,000 20,000 35,000 $480,000 160,000 Meiger's owners currently demand a return of 20 percent of the market price of iron ore. Required: a. If the current market price of iron ore is $8.5 per ton, what is Meiger's target cost per ton? b-1. Given the $8.5 market price, compute the total cost per ton for Site A and Site B if fixed overhead costs are assigned to products on the basis of estimated tons of ore that can be extracted over the life of the mine. b-2. Should either of the mines be opened? c-1. The engineer working on Site B believes that if a custom conveyor system is installed, the variable extraction cost could be reduced to $3 per ton. The purchase price of the system is $25,000, but the costs to restore the site will increase to $45,000 if it is installed. Given the current $8 market price, compute the total cost per ton for site B. c-2. Should Meiger install the conveyor and open Site B?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage
Principles of Accounting Volume 1
Principles of Accounting Volume 1
Accounting
ISBN:
9781947172685
Author:
OpenStax
Publisher:
OpenStax College
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning