Problem 4 On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. revenue over time. Data on this project for 2022-2024 follow: The company recognizes construction Contract Costs Est'd Costs Billings 10,500,000 12,500,000 14,440,000 incurred to Complete 20,540,000 5,460,000 9,984,000 15,756,000 2022 2023 13,156,000 2024 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks What is the gross profit for 2024? A. 1,164,000 в. c. 1,724,000 1,824,000 1,466, 400 D. Problem 5 PIR
Q: M6-16 Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a…
A: a.Calculate the gross profit under percentage of completion method as follows:
Q: [2] In May 2021, Oliver Queen Company began work on a project that has a contact price of…
A: Lets discuss two methods. In percentage of completion method, revenue gets recognized based on the…
Q: Q3/A cement manufacturing company has a sales value for the first half of the year in the company's…
A: "As per the policy of our company, we are allowed to answer only the first three sub-parts in case…
Q: The Leto Construction Company began work on a $12.000 contract on 1/1/20. Planned completion was in…
A:
Q: 16. West Construction company recognized gross profit of P 31,500 on it: long term project what has…
A: Solution: Total revenue recognized till date = Accumulated costs + Gross profit = P61,250 + P31,500…
Q: In 20x1, XYZ Company enters into a construction contract with a customer. The contract price is…
A: Step 1 “Since you have posted a question with multiple sub-parts, we will solve first three subparts…
Q: Problem 3 BUILDERS Construction is constructing an office building under contract. The contract…
A: A company has to recognize revenue and expenses in the year they are earned and incurred,…
Q: 11 NANGUTANG started constructing a building for its own use on January 1, 2020. NANGUTANG provided…
A: Borrowing cost means where the assets like building , take substantial time to build , then interest…
Q: BUILDERS Construction is constructing an office building under contract. contract calls for progress…
A: The construction contract seems to be a consensual or contractually enforceable contract between two…
Q: Problem on Longterm Construction On January 1, 2018, Builders Enterprises obtained a contract to…
A: calculation of above requirement are as follows
Q: Assume that Pearl completed the office and warehouse building on December 31, 2020, as planned at a…
A: a. Weighted Average Interest rate on general borrowings = 2240000/3840000* 10% +…
Q: 57. Wynn, Inc. has a contract to construct a large hotel for P12,000,000. The contract was signed on…
A: 57) As per the percentage completion method the entity recognized contract revenue based on the…
Q: Question 4 On 22 February 2018, Sun Company entered into a contract to build an apartment building.…
A: The amount of gross profit in contract process is recognised on the basis of percentage of work…
Q: Problem 4: Strong Construction Company was contracted on July 1, 2018 to construct a medium rise…
A: Construction Contract: A construction contract is a contract between a customer and a general…
Q: TABLE Q3 Description Design A (RM) 8,000,000 60,000 Design B (RM) 10,000,000 Design C (RM) 9,000,000…
A: The Life Cycle Cost Analysis (LLCA) method is used to study and estimate the total cost of resource…
Q: Question 2. Debackere Construction Corp. contracted with Aggretsuko Inc. to build a karaoke machine…
A: Journal- Journalizing is the process by which businesses record their transactions in an orderly…
Q: Problem 2 CONSTRUCTION COMPANY is executing a construction project, which is expected to take three…
A: Revenue on construction contracts is determined based on the percentage of completion and the…
Q: On June 30, 2020, Zendaya purchased a special machinery to conduct its oil drilling operations in…
A: IAS 37 says that the provision for a future liability should be recognized ony if satisfies the…
Q: 7. Realized gross profit in 20x2 _____________ 8. The balance of "Contract Liability" at the end of…
A: “Since you have posted a question with many sub-parts, we will solve three sub-parts for you. To get…
Q: Start up expenses: To start the gym, the initial total investment required is $162,544.55EC. This…
A: Balance Sheet The purpose of preparing the balance sheet is to know the actual position of assets…
Q: Problem 4 On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is…
A: In the given question We are provided with the total cost of building the hotel ie. P 3,12,00,000 We…
Q: 33.Sta. Clara Construction Company has used the cost to cost the percentage of completion method of…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: In 20x1, XYZ Company enters into a construction contract with a customer. The contract price is…
A: There are 2 methods of accounting for long-term construction contracts: 1. Percentage of contract…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Solution: Under percentage of completion method of revenue recognition for long term construction…
Q: Required information [The following information applies to the questions displayed below] In 2021,…
A: This is the question of contract costing wherein we are provided with the data for three years. We…
Q: Problem 2 On July 1, 2015, DreamDad Inc., which has a calendar year accounting period, received a…
A: Government Grants is the government’s way to fund your projects. Government includes Local…
Q: PROBLEM 2 Lahar Construction Corporation contracted with the City of Pampanga to construct a dam at…
A: The percentage of completion is calculated on the basis of total estimated costs and costs incurred…
Q: n March 1, 2022, AGGREGATES Company enters a contract to build a hotel which The cost P31,200,000.…
A: It is observed that the given problem relates to percentage of completion method. In this method…
Q: ABC Construction Company began work on a contract in 2022 and completed the contract in 2023. The…
A: Balance of Accounts Receivable = Progress billings done during the year 2022 - Amount collected from…
Q: Problem 6-10 (Static) Long-term contract; revenue recognition over time (LO6-8, 6-9] [The following…
A: The question is based on the concept of Financial Accounting.
Q: 40. Silvanna has a contract starting January 1, 2021 to construct a Supermarket that is expected to…
A: Income will be recognised on the basis of percentage of work completed in the given contract. Detail…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Solution 5: Under percentage of completion method of revenue recognition for long term construction…
Q: VI - Methods of Construction Accounting 2eck Construction Company bęgan work on a new building…
A: 1) Answer: Thus gross Profit for each year is 20x4 = P6,000,000, 20x5 = P3,000,000, 20x6 =…
Q: ABC Construction Company began work on a contract in 2022 and completed the contract in 2023. The…
A: Construction Contract: The term "construction contract" refers to agreements to do architectural,…
Q: Q3/A cement manufacturing company has a sales value for the first half of the year in the company's…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: 36 Construction is constructing an office building under contract for Election Cafe. The contract…
A: Construction Contracts means a contract between two parties for a construction of an asset where in…
Q: 15. In 20x1, Espresso Co. started work on a long-term construction contract. Espresso Co.…
A: In construction contracts revenue recognised on the basis of cost of completion method.
Q: On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a…
A: Fixed Price Contract is the contract where two parties agree for a fixed price for the agreement. To…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- 1.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow:Contract BillingsCosts incurredEst’d Costs to Complete2022 10,500,000 5,460,000 20,540,0002023 12,500,000 9,984,000 13,156,0002024 14,440,000 15,756,000 -The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeksWhat is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000 2.MOC Construction Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below:Site Contract PriceCost IncurredEstimated Costs to CompleteBillings on ContractCollections on Billings1 5,000,000 3,750,000 - 5,000,000 5,000,0002 7,000,000 1,000,000 4,000,000 900,000…Problem 2CONSTRUCTION COMPANY is executing a construction project, which is expectedto take three years. The company has signed a fixed price contract forP12,000,000. The details of the costs incurred to date 2020 are as follows:Site labor costs 1,000,000Costs of construction material 3,000,000Depreciation of PPE used in construction 500,000Marketing and selling costs 1,000,000Total 5,000,000Total contract costs estimated to complete 5,500,000Determine the revenue, costs and profits to be recognized overtime in 2020.REVENUE COSTS GROSSPROFIT/(LOSS)A. 5,400,000 4,500,000 900,000B. 5,400,000 5,500,000 (100,000)C. 6,000,000 4,500,000 1,500,000D. 6,000,000 5,500,000 900,000On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow: Contract Billings Costs incurred Est'd Costs to complete 2022 10,500,000 5,460,000 20,540,000 2023 12,500,000 9,984,000 13,156,000 2024 14,440,000 15,756,000 - The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks. What is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000
- 49. ABC Construction Company began work on a contract in 2022 and completed the contract in 2023. The total contact price was P8,500,000. Information related to the construction project are as follows: 2022 2023 Costs incurred during the year P1,200,000 P6,250,000 Estimated costs to complete 4,800,000 - Progress billings during the year 1,450,000 7,050,000 Collections during the year 800,000 6,000,000 How much is the receivable balance as of December 31, 2022?55 On March 1, 2022, ABC Co. was contracted to construct a building for a customer at a total contract price of P16,500,000. The building was estimated to be completed in 2024. The following data were made available: 2022 2023 2024 Contract costs incurred P6,400,000 P5,200,000 P2,900,000 Estimated costs to complete 6,400,000 2,900,000 - Progress billings each year 6,400,000 7,000,000 3,100,000 How much is the realized gross profit for 2024?43. On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022?
- 41. On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the gross profit to be recognized in 2023?4SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract:December 31, 2021December 31, 2022Percentage of completion30%82.5%Estimated cost to complete1,960,000840,0001.What is the total cost incurred in year 2022? 1.What is the total cost incurred in year 2022? A.4,073,750 C. 1,680,000. B.840,000. D. 3,120,000 2.The realized gross profit (loss) in year 2022 is A.650,000. C. (. 245,000) B.405,000 D. (1,055,000) 3.What is the construction cost of sales for year 2022? A.3,960,000. C. 3,233,750 B.3,120,000. D. 4,478,750 4.What is the construction-in-progress as of 2022? A.3,423,750. C. 2,065,000 B.3,310,000. D. 2,470,000Assume Avaya contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Question: Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.
- 56 On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022? On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022?Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time.3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to…6) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Costs incurred…