Q1- The schedule for one of the projects was as in Table No. (1), answer the following- 1- Draw the sagittal grid diagram of the project 2-Find the late start time for activity No. (5) 3- Find the early end time for activity No. (9) 4- The project completion period. 5- Select the eritical path
Q: Table 1: Expected time, standard deviation and cost associated with each activity of a project…
A: From the above network diagram and table: a) critical path is the path with maximum expected time:…
Q: Q1) The project schedule has the following characteristics: Activity Time (weeks) Activity…
A: Given information, Activity Predecessors Durations A 10 B 7 C B 5 D B 6 E A 9…
Q: Construct a network diagram for this project?
A: Find the Duration Calculation below:
Q: B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the…
A: In this question, I would construct the Gantt chart based on the given Activity ID, Activity…
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Q1) by using Bar chart planning technique find the following a- Total duration for the project b-…
A: The detailed solution of the given question is in Step 2.
Q: 01) The utility data for a network are given below: Activity Duration (Days) 0-1 1-2 8 1 -3 10 2-4…
A: Note: - Since we can answer only up to 3 subparts we will answer subparts 1, 2, and 3 for your…
Q: Ql: For activitices shown in table below, find the new time of project after updating, if the…
A: Given data is
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: 1. Draw the network diagram for the above project. 2. What is the critical path? 3. What is the…
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: 1- The network below represents a project being analyzed by Critical Path Methods. Activity…
A: Since you have submitted questions with multiple subparts, as per guidelines we have answered the…
Q: activity predecessor optimistic time(days) Most likely time(days) Pessimistic time(days) A - 4 8 24…
A: Find the Given details below: Activity Predecessors Optimistic Time(To) a(Days) Pessimistic…
Q: Use this table as inputs to answer the questions below: Activity Total Budgeted Duration (months)…
A: Possible paths and duration: A-G = 4 B-E-F = 9 A-D = 5 C = 2 The critical path would be B-E-F with 9…
Q: As the pandemic waned, an educational institution was faced with the imperative of refurbishing and…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Calculate the total float, free float and independent float for the project whose activities are…
A: Given data is
Q: (a) What is the critical path? (b) How long will it take to complete this project? (c) Can…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: a) Draw an AON diagram of the project, including activity durations. b) Define the critical path,…
A: In project management, there are two types of networks. One is AON and the second is AOA. AON…
Q: Task Duration (Weeks) Follows A 3 B 7 A C 9 A D 3 C E 11 B, D F 3 E G 2 F H 3 C F I 5…
A: We use the forward and backward methods to calculate the critical path.
Q: c. What is the expected project completion time? (Do not round intermediate calculations. Round your…
A: Find the duration calculations below:
Q: Find the total cost associated with the project as Data is given in Table 1)
A: Given that: Activity Expected Time Standard deviation Cost A 3 0.3 $2,000 B 2 0.5 $3,000…
Q: Q1: For activitics shown in table below, find the new time of project after updating, if the project…
A:
Q: Q1,Draw the network. Q2,what is the critical path Q3,how many weeks will it take to complete the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Calculate ES, EF, LS, LF and slack for the following: Activity Task Predecessor Duration A Policies…
A: Given data is
Q: 3.1 Draw the project Gantt Chart 3.2 Determine the project duration 3.3 Describe the project…
A: Below is the solution:-
Q: Q3.When we start a project how we know this project or program is feasible for our future? Explain…
A: Project selection is a critical task and therefore generally leaders or people without past…
Q: a. Develop a project network. b. Develop an activity schedule. C. What are the critical activities,…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: (a) Construct the AON network for the project. (b) Determine all paths that run from the start to…
A: Activity-on-node is a project management term that directs to a precedence diagramming technique…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the…
A: Given data- Activity A B C D E F G H I J K L M Predecessor - -…
Q: able Activities Name A E Predecessor A А, В D C, E Time (Days) 7 9 12 9.
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: Using the network diagram constructed in Problem 1,(a) Calculate the completion time for the…
A: The completion time of the project can be calculated as below:
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: The project network diagram is the diagram that shows the activity and the project duration to…
Q: Ql: For activitics shown in table below, find the new time of project after updating, if the project…
A: ANSWER IS AS BELOW:
Q: 1. Determine and provide the following information for Activity 1: Latest Finish Duration …
A: Latest finish: -5 Duration: 3 Latest start: -8 Start date: 0
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: What would a project manager have to do to crash an activity? 2. Describe the meaning of slack, and…
A: Project management is a process of coordinating all processes related with a project. A crashing…
Q: 4. How long can activity C be delayed without delaying the whole project?
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: When will the activity be finished? 9 months 10 months 11 months 1 year When will activity CC end?…
A: Explanation: Start time of Activity AA = 0 Time for Activity AA = 1 month So, End time of…
Q: Schedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 1…
A: a)
Q: 01) The utility data for a network are given below: Activity Duration (Days) 0-1 2 1-2 8 1-3 10 2-4…
A: Note: - Since we can answer only up to 3 subparts we will answer the first three subparts for your…
Q: Using an example explain the concept of project crashing
A: Project crashing is simply explained as the method in project management which aims at speeding up…
Q: The project manager of Good Public Relations gathered the data shown in Table 7.15 for a new…
A: Critical path method is one of the effective project scheduling technique in which project can be…
Q: a) Draw the project network using AON. b) Identify the critical path. c) What is the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Q5: Draw the following project and find the slack time and critical path on the network: Act 1-2 2-3…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: 1. When will the activity be finished? 9 months 10 months 11 months 1 year 2. When will activity…
A: This question is related to the topic- project management and this topic fall under the operations…
Q: Problem 2: Chicago Project You are asked to manage an upcoming project for a client based in…
A: Given data is
Q: Activity Preceding Time A 8 -- B 3 -- A 7 D А, В 3 E C 4 F 6 a. Draw the network diagram. b.…
A: given, Activity Preceding Time A - 8 B - 3 C A 7 D A,B 3 E C 4 F D 6
Step by step
Solved in 2 steps with 1 images
- Follow up to previous question: 3) A company decides to plan a project, with activities, precedences and random duration statistics given in the following table: Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks) A none 2 5 9 B A 1 6 8 C A 3 5 12 D B 2 4 12 E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 Questions: 1) What method should be used? Compute the mean and variances for each activity and add them to the table above. 2)Draw the project network and label the arcs with the activity name. 3) Assuming that the critical path is AàBàP1àEàGàH, compute the probability that this path duration is between 28 weeks and 32 weeks. 4) Assuming that the critical path is AàBàP1àEàGàH, compute the number of weeks within which the project will be completed with probability 0.95.Q2 Please help with correct answers in details: Step by step. Last submission got incorrect answers. Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 Develop an activity schedule. (Round your answers to two decimal places.) Activity EarliestStart LatestStart…Q1. Using a suitable example each, describe what the following project planningprocess activities involve:a. Establish project objective;b. Define scope;c. Create a Work Breakdown Structure (WBS);d. Estimate activity durations;e. Sequencing activities.
- [Ques 1] CEPS (name of college: Economics and political science) planned for a major project to understand the readiness of the college to conduct online learning. The readiness involves assessing to what degree are faculty, technology infrastructure and students ready for effective online learning. How can the success of this project defined?Scenario Capstone project Goal Statement: Our goal is to improve the overall mental health status of veterans of the Canadian Armed Forces and RCMP by up to 80% for those struggling with mental health challenges by facilitating real-time accessibility to a peer support platform utilizing a mobile app to fill the gap that currently exists when veterans are awaiting appointments for psychological supports that are currently funded by Veterans Affairs of Canada. We aim to reduce the strain on the general health system due to the repeated appointments with a veteran's primary care practitioner to inquire about further mental health resources and to improve a veterans quality of life while they are adjusting to civilian life in between their federally funded psychological supports. Please answer in detail 1 communication strategy for the above project 2. Pilot or stakeholder feedback outcomes 3. Recommendation for next stepsACTIVITY Immediate Predecessor Normal Duration (wks) Minimum Duration (wks) Crash Costs ($/wk) A --- 4 4 --- B --- 3 2 100 C A, B 5 3 200 D C 4 4 --- E C 2 1 300 F C 1 1 --- G D 3 2 200 H E 1 1 --- I F 1 1 --- J H, I 3 1 100 What is the slack time for Activity F and the late start for Activity H? Group of answer choices 2 weeks, 11 weeks 1 weeks, 11 weeks 3 weeks, 10 weeks 2 weeks, 12 weeks None of the above are correct.
- Question 2 2.1 Explain what resource-constrained project planning is 2.2 Explain what is meant by resource levelling or smoothing 2.3 Describe why and when resource levelling or smoothing is used 2.4 Explain how resource levelling keeps a project on scheduleQuestion 2 Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?
- I want answer with explanation... I'll upvote you... Only typed answer I want... The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Activity optimistic time most likely time pessimistic time Activity Predecessor A 1 4 7 -- B 2 6 7 -- C 3 3 6 B D 6 13 14 A E 3 6 12 A, C F 6 8 16 B G 1 5 6 E, F Table 1 Reference: Ref 1 Using Table 1, the probability that the project could be completed in 23 weeks or less is approximately A. 0.94 B. 0.87 C. 0.91 D. 0.89Q1.Activity Precedence DurationA 10B A 4C A, B 3D C 5E D 6F B, E 7Draw PDM of the above and calculate the Total and free floatQ2. What is Fast Tracking and crashingQ3. Being a PM you plan 10k for first two months for activity A, and 30K for B.For second month only activity B is planplan cost is 60K, and thrid month plan cost for Activity D is , 35k.If reporting month is 2nd month and we have spend 100k, then;(i) What is the total Budeget at completion ?(ii) What is the Earned Value?(iii) and Calculate the SPI and CPI for the aboveYou are the manager of a project to improve a billing processat your firm. Table 7.7 contains the data you will need toconduct a cost analysis of the project. Indirect costs are $1,600per week, and penalty costs are $1,200 per week after week 12.a. What is the minimum-cost schedule for this project?b. What is the difference in total project costs between the ear-liest completion time of the project using “normal” timesand the minimum-cost schedule you derived in part (a)?