Q54 ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the prominent consultation company this company required to provide excellent service to meet customer demand. Table QŠ shows the planning for the new product development project received recently by this company. Table Q5 Activity Actions Preceding |activities Time (weeks) Product Conception Material Selection Process Conception Production System Design Prototype tests Procurement Tool and machine | acquisition Product installation | and testing A 4 3 А, В F D E,F H G a. Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS), early finish (EF) and late finish (LF) in the diagram. b. Find the critical path in the network diagram

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question

engeenring managament 

answer please

Q54
ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the
prominent consultation company this company required to provide excellent service to meet
customer demand. Table Q5 shows the planning for the new product development project
received recently by this company.
Table Q5
Activity
Preceding
activities
Actions
Time (weeks)
A
Product Conception
4
В
Material Selection
3
Process Conception
Production System
Design
Prototype tests
Procurement
Tool and machine
C
А, В
5
1
E
F
E,F
H
acquisition
Product installation
G
and testing
a. Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS),
early finish (EF) and late finish (LF) in the diagram.
b. Find the critical path in the network diagram
Transcribed Image Text:Q54 ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the prominent consultation company this company required to provide excellent service to meet customer demand. Table Q5 shows the planning for the new product development project received recently by this company. Table Q5 Activity Preceding activities Actions Time (weeks) A Product Conception 4 В Material Selection 3 Process Conception Production System Design Prototype tests Procurement Tool and machine C А, В 5 1 E F E,F H acquisition Product installation G and testing a. Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS), early finish (EF) and late finish (LF) in the diagram. b. Find the critical path in the network diagram
Expert Solution
steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning