Question 4. The following table shows the tasks, dependencies, and estimated times a project manager might input to a PERT chart for a software development project. Activity Name Task Description Predecessor Optimistic Most Likely Pessimistic Establish project Establish customer requirements Produce software specification documents Write test plans Write code Developer testing System testing A 4 5 12 B A 2 3 4. 22 4 6. 8. C 3 4 F E 2 4 6. D, F 4 H Write manuals 5 7 15

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Table 8-5 Cumulative (Single Tail) Probabilities of the Normal Probability Distribution (Areas
under the Normal Curve from – o to Z)
Example: the area to the left of Z = 1.34 is found by following the left Z column
down to 1.3 and moving right to the .04 column. At the intersection read 9099. The
area to the right of Z- 1.34 is - 9099 - 0901. The area between the mean (center
ZX line) and Z- 1.34 is 9099-5- 4099.
01
.02
.03
.04
.Os
.06
07
.08
.09
S000
5040
SO80
5120
5160
5199
5239
5279
5319
5359
5398
5438
5478
5517
5557
5596
5636
5675
5714
5753
.2
5793
5832
5871
5910
5948
5987
6026
.6064
6103
6141
.6179
6217
.6255
6293
6331
6368
6406
6443
6480
6517
6554
6591
.6628
6664
6700
6736
6772
.6808
6844
6879
6915
6950
6985
7019
.7054
7088
7123
.7157
.7190
.7224
.7257
7291
.7324
7357
.7389
.7422
7454
.7486
.7517
7549
.7
.7580
7611
7642
7673
.7704
7734
7764
.7794
7823
7852
.7881
7910
.7939
7967
.7995
8023
S051
8078
8106
S133
8159
8186
8212
8238
8264
8289
8315
8340
8365
8389
10
8413
8438
8461
8485
8508
8531
8554
8577
8599
8621
1.1
„8643
8665
8686
8708
729צ
8749
S770
8790
8810
8880
1.2
8849
8869
8888
8907
8925
8944
8962
.8980
8997
9015
1.3
9032
9049
9066
9082
9099
9115
9131
9147
9162
9177
1.4
9192
9207
9222
9236
9251
9265
9279
.9292
9306
9319
1.5
9332
9345
.9357
9370
9382
9394
9406
9418
9429
9441
1.6
9452
9463
9474
9484
9495
9505
9515
.9525
9535
9545
1.7
.9554
9564
9573
9582
9591
9599
9608
9616
9625
9633
1.8
.9641
9649
9656
9664
9671
9678
9686
9693
9699
9706
1.9
.9713
9719
.9726
9732
9738
9744
9750
9756
9761
9767
2.0
9772
9778
9783
9788
9793
9798
9803
.9808
9812
9817
2.1
9821
9826
9830
9834
9838
9842
9846
.9850
9854
9857
2.2
9861
9864
9868
9871
9875
9878
9881
9884
9887
9890
2.3
9893
9896
9898
9901
9904
.9906
9909
.9911
9913
9916
2.4
9918
9920
9932
9925
9927
9929
9931
9932
9934
9936
2.5
9938
9940
9941
9943
9945
9946
9948
9949
9951
9952
2.6
.9953
9955
9956
9957
9959
9960
9961
.9962
9963
9964
2.7
.9965
9966
.9967
9968
9969
9970
9971
9972
9973
9974
2.8
9974
9975
9976
9977
9977
9978
9979
9979
9980
9981
29
.9981
9982
9982
9983
9984
9984
9985
9985
9986
9986
3.0
9987
9987
9987
9988
9988
9989
9989
9989
9990
9990
3.1
9990
9991
9991
9991
9992
9992
9992
9992
9993
9993
3.2
9993
9993
.9994
9994
9994
9994
9994
.9995
9995
9995
3.3
.9995
9995
9995
9996
9996
9996
9996
.9996
9996
9997
3.4
.9997
9997
9997
9997
9997
9997
9997
9997
9997
9998
Transcribed Image Text:Table 8-5 Cumulative (Single Tail) Probabilities of the Normal Probability Distribution (Areas under the Normal Curve from – o to Z) Example: the area to the left of Z = 1.34 is found by following the left Z column down to 1.3 and moving right to the .04 column. At the intersection read 9099. The area to the right of Z- 1.34 is - 9099 - 0901. The area between the mean (center ZX line) and Z- 1.34 is 9099-5- 4099. 01 .02 .03 .04 .Os .06 07 .08 .09 S000 5040 SO80 5120 5160 5199 5239 5279 5319 5359 5398 5438 5478 5517 5557 5596 5636 5675 5714 5753 .2 5793 5832 5871 5910 5948 5987 6026 .6064 6103 6141 .6179 6217 .6255 6293 6331 6368 6406 6443 6480 6517 6554 6591 .6628 6664 6700 6736 6772 .6808 6844 6879 6915 6950 6985 7019 .7054 7088 7123 .7157 .7190 .7224 .7257 7291 .7324 7357 .7389 .7422 7454 .7486 .7517 7549 .7 .7580 7611 7642 7673 .7704 7734 7764 .7794 7823 7852 .7881 7910 .7939 7967 .7995 8023 S051 8078 8106 S133 8159 8186 8212 8238 8264 8289 8315 8340 8365 8389 10 8413 8438 8461 8485 8508 8531 8554 8577 8599 8621 1.1 „8643 8665 8686 8708 729צ 8749 S770 8790 8810 8880 1.2 8849 8869 8888 8907 8925 8944 8962 .8980 8997 9015 1.3 9032 9049 9066 9082 9099 9115 9131 9147 9162 9177 1.4 9192 9207 9222 9236 9251 9265 9279 .9292 9306 9319 1.5 9332 9345 .9357 9370 9382 9394 9406 9418 9429 9441 1.6 9452 9463 9474 9484 9495 9505 9515 .9525 9535 9545 1.7 .9554 9564 9573 9582 9591 9599 9608 9616 9625 9633 1.8 .9641 9649 9656 9664 9671 9678 9686 9693 9699 9706 1.9 .9713 9719 .9726 9732 9738 9744 9750 9756 9761 9767 2.0 9772 9778 9783 9788 9793 9798 9803 .9808 9812 9817 2.1 9821 9826 9830 9834 9838 9842 9846 .9850 9854 9857 2.2 9861 9864 9868 9871 9875 9878 9881 9884 9887 9890 2.3 9893 9896 9898 9901 9904 .9906 9909 .9911 9913 9916 2.4 9918 9920 9932 9925 9927 9929 9931 9932 9934 9936 2.5 9938 9940 9941 9943 9945 9946 9948 9949 9951 9952 2.6 .9953 9955 9956 9957 9959 9960 9961 .9962 9963 9964 2.7 .9965 9966 .9967 9968 9969 9970 9971 9972 9973 9974 2.8 9974 9975 9976 9977 9977 9978 9979 9979 9980 9981 29 .9981 9982 9982 9983 9984 9984 9985 9985 9986 9986 3.0 9987 9987 9987 9988 9988 9989 9989 9989 9990 9990 3.1 9990 9991 9991 9991 9992 9992 9992 9992 9993 9993 3.2 9993 9993 .9994 9994 9994 9994 9994 .9995 9995 9995 3.3 .9995 9995 9995 9996 9996 9996 9996 .9996 9996 9997 3.4 .9997 9997 9997 9997 9997 9997 9997 9997 9997 9998
Question 4.
The following table shows the tasks, dependencies, and estimated times a project
manager might input to a PERT chart for a software development project.
Activity Name
Task Description
Predecessor Optimistic Most Likely
Pessimistic
Establish project
Establish customer requirements
Produce software specification documents
Write test plans
Write code
Developer testing
System testing
A
4
12
B
A
4
В
6.
8
22
D
6.
8.
E
3.
4
F
2
4
6.
D, F
4
6.
8
H
Write manuals
7
15
According to the above table,
a)
Find the critical path using PERT
b)
Calculate the total project duration
Calculate Project variance and standard deviation
) What is the probability of completion in 38 days
e)
)What is the completion of the project with 0.90 chance
Transcribed Image Text:Question 4. The following table shows the tasks, dependencies, and estimated times a project manager might input to a PERT chart for a software development project. Activity Name Task Description Predecessor Optimistic Most Likely Pessimistic Establish project Establish customer requirements Produce software specification documents Write test plans Write code Developer testing System testing A 4 12 B A 4 В 6. 8 22 D 6. 8. E 3. 4 F 2 4 6. D, F 4 6. 8 H Write manuals 7 15 According to the above table, a) Find the critical path using PERT b) Calculate the total project duration Calculate Project variance and standard deviation ) What is the probability of completion in 38 days e) )What is the completion of the project with 0.90 chance
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.