Question No 3 A small project is composed of 7 activities whose time estimates are listed in the table below. activities are identified by their beginning (i) and ending (i) node numbers. Activity (i- j) Optimistic Time (Weeks) Most Likely Time (Weeks) Pessimistic Time (weeks) 7 1-2 1 1 1-3 7 1-4 2 2 8 2- 5 1 1 1 3-5 2 14 4-6 8 5-6 3 15 a) Draw the network diagram of activities in the project. b) Find the expected duration and variance of each activity .What is the expected project length? c )Calculate the variance and standard deviation of the project length. What is the probability that the project will be completed ? i) at least 4 weeks earlier than expected time. i1) no more than 4 weeks later than expected time.

Linear Algebra: A Modern Introduction
4th Edition
ISBN:9781285463247
Author:David Poole
Publisher:David Poole
Chapter2: Systems Of Linear Equations
Section2.4: Applications
Problem 2EQ: 2. Suppose that in Example 2.27, 400 units of food A, 500 units of B, and 600 units of C are placed...
icon
Related questions
Topic Video
Question
Question No 3
A small project is composed of 7 activities whose time estimates are listed in the table below.
activities are identified by their beginning (1) and ending (j) node numbers.
Activity
(i- j)
Optimistic Time
(Weeks)
Most Likely Time
(Weeks)
Pessimistic Time
(weeks)
1-2
1
1
7
1-3
1
4
7
1-4
2
8
2- 5
1
1
1
3-5
2
14
4-6
2
8
5-6
3
15
a) Draw the network diagram of activities in the project.
b ) Find the expected duration and variance of each activity .What is the expected project
length?
c )Calculate the variance and standard deviation of the project length. What is the
probability that the project will be completed ?
i) at least 4 weeks earlier than expected time.
i1) no more than 4 weeks later than expected time.
d) If the project due date is 19 weeks, what is the probability of not meeting the due date.
Given:
:
0.05
0.67
1.00
1.33
2.00
Area:
0.3085
0.2514
0.1587
0.0918
0.0228
Transcribed Image Text:Question No 3 A small project is composed of 7 activities whose time estimates are listed in the table below. activities are identified by their beginning (1) and ending (j) node numbers. Activity (i- j) Optimistic Time (Weeks) Most Likely Time (Weeks) Pessimistic Time (weeks) 1-2 1 1 7 1-3 1 4 7 1-4 2 8 2- 5 1 1 1 3-5 2 14 4-6 2 8 5-6 3 15 a) Draw the network diagram of activities in the project. b ) Find the expected duration and variance of each activity .What is the expected project length? c )Calculate the variance and standard deviation of the project length. What is the probability that the project will be completed ? i) at least 4 weeks earlier than expected time. i1) no more than 4 weeks later than expected time. d) If the project due date is 19 weeks, what is the probability of not meeting the due date. Given: : 0.05 0.67 1.00 1.33 2.00 Area: 0.3085 0.2514 0.1587 0.0918 0.0228
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Hypothesis Tests and Confidence Intervals for Means
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Linear Algebra: A Modern Introduction
Linear Algebra: A Modern Introduction
Algebra
ISBN:
9781285463247
Author:
David Poole
Publisher:
Cengage Learning