Salman signs a contract to build a warehouse in Sydney for his client. They agree on the price and time frame for the completion of the project. Salman hires two apprentices on lower wages than qualified tradespeople; he also hires another two labourers on a daily basis. Work is about to commence. But digging the foundation takes much longer than expected because Salman and his crew had to extract some large rocks embedded within the soil. The labourers he hired leave him and there are no other labourers he can hire on such short notice to replace them. One of the apprentices completes his apprenticeship and will not have to be paid full trade wages. The other apprentice leaves for Adelaide. Salman now has no labourers to finish building the warehouse. The cost of employing new tradespeople will mean that he will lose money in building the warehouse. He wants to terminate the contact and believes that he has grounds to do so due to frustration of contract. He then tells the client that he cannot proceed with building the warehouse but would like to be paid for the foundation work. (a)        Can Salman correctly argue that the contract is frustrated? (b)       Can he ask for payment for the foundation work done on the building

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter9: Acquisitions Of Property
Section: Chapter Questions
Problem 93TPC
icon
Related questions
Question

Salman signs a contract to build a warehouse in Sydney for his client. They agree on the price and time frame for the completion of the project. Salman hires two apprentices on lower wages than qualified tradespeople; he also hires another two labourers on a daily basis.

Work is about to commence. But digging the foundation takes much longer than expected because Salman and his crew had to extract some large rocks embedded within the soil. The labourers he hired leave him and there are no other labourers he can hire on such short notice to replace them. One of the apprentices completes his apprenticeship and will not have to be paid full trade wages. The other apprentice leaves for Adelaide.

Salman now has no labourers to finish building the warehouse. The cost of employing new tradespeople will mean that he will lose money in building the warehouse. He wants to terminate the contact and believes that he has grounds to do so due to frustration of contract. He then tells the client that he cannot proceed with building the warehouse but would like to be paid for the foundation work.

(a)        Can Salman correctly argue that the contract is frustrated?

(b)       Can he ask for payment for the foundation work done on the building?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Fair labor standards act (FLSA)
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
SWFT Essntl Tax Individ/Bus Entities 2020
SWFT Essntl Tax Individ/Bus Entities 2020
Accounting
ISBN:
9780357391266
Author:
Nellen
Publisher:
Cengage