Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $104,720. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 3,000 units 0.5 Clarinets 400 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide overhead rate. 28 V per direct labor hour b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products. Total Per Unit Factory Overhead Cost Factory Overhead Cost Flutes 42,000 14 Clarinets 15,680 39 Oboes 47,040 34 Total $ 104,720

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter4: Activity-based Costing
Section: Chapter Questions
Problem 2E: Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted...
icon
Related questions
Question

(2) ABC:

Single plantwide factory overhead rate
Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $104,720. Overhead is allocated to the three products on the basis of direct labor
hours. The products have the following budgeted production volume and direct labor hours per unit:
Budgeted Production
Direct Labor Hours Per
Volume
Unit
Flutes
3,000 units
0.5
Clarinets
400
1.4
Oboes
1,400
1.2
If required, round all per unit answers to the nearest cent.
a. Determine the single plantwide overhead rate.
2$
28
per direct labor hour
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products.
Total
Per Unit
Factory Overhead Cost
Factory Overhead Cost
Flutes
$
42,000
$4
14
Clarinets
15,680 V
39
Oboes
47,040 V
34
Total
$ 104,720
Transcribed Image Text:Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $104,720. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 3,000 units 0.5 Clarinets 400 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide overhead rate. 2$ 28 per direct labor hour b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products. Total Per Unit Factory Overhead Cost Factory Overhead Cost Flutes $ 42,000 $4 14 Clarinets 15,680 V 39 Oboes 47,040 V 34 Total $ 104,720
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning