Super Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday. b. If weekly demand for the four products are A-

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
Super Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday. b. If weekly demand for the four products are A-148=180 units, B-356=310 units, B-457=280 units, and C-843=300 units, which station is the bottleneck, and is it capable of producing all the toys demanded? The bottleneck for Super Fun Industries is ▼ Station 1 Station 2 Station 3 Station 4 , with a utilization of ______%. (Enter your response rounded to one decimal place.)
Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each
toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on
Saturday
A-148
B-356
B-457
C-843
Processing Time Station 1
Processing Time Station 2
Processing Time Station 3
Processing Time Station 4
5 min
4 min
6 min
6 min
3 min
7 min
0 min
0 min
8 min
1 min
3 min
4 min
2 min
2 min
10 min
2 min
a. If only toy A-148 is produced during a specific week, 680 units could be produced. (Enter your response rounded down to the nearest whole number.)
b. If weekly demand for the four products are A-148 = 180 units, B-356 = 310 units, B-457 = 280 units, and C-843 = 300 units, which station is the bottleneck, and is it
capable of producing all the toys demanded?
The bottleneck for Super Fun Industries is
V. with a utilization of %. (Enter your response rounded to one decimal place.)
Transcribed Image Text:Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday A-148 B-356 B-457 C-843 Processing Time Station 1 Processing Time Station 2 Processing Time Station 3 Processing Time Station 4 5 min 4 min 6 min 6 min 3 min 7 min 0 min 0 min 8 min 1 min 3 min 4 min 2 min 2 min 10 min 2 min a. If only toy A-148 is produced during a specific week, 680 units could be produced. (Enter your response rounded down to the nearest whole number.) b. If weekly demand for the four products are A-148 = 180 units, B-356 = 310 units, B-457 = 280 units, and C-843 = 300 units, which station is the bottleneck, and is it capable of producing all the toys demanded? The bottleneck for Super Fun Industries is V. with a utilization of %. (Enter your response rounded to one decimal place.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,