Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you ha to find the right sequence of activities in order to complete the project on time. Use Gantt (Bar) Chart and calculate total duration and determine the critical path of the project. Immediate Estimated Activity Predecessors Duration 2 weeks 4 weeks 10 weeks 6 weeks E 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks S weeks G D E, G F, I K H. K, L 2 weeks 6 weeks Immediate Predecessor (Finish to Start) Construct Gantt Chart of the project.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have
to find the right sequence of activities in order to complete the project on time. Use Gantt (Bar) Chart and calculate total duration and
determine the critical path of the project.
Immediate
Estimated
Activity
Predecessors
Duration
2 weeks
4 weeks
10 weeks
A
6 weeks
4 weeks
S weeks
7 weeks
9 weeks
7 weeks
8 weeks
G
E, G
F, 1
4 weeks
5 weeks
2 weeks
6 weeks
K
M
K, L
Immediate Predecessor (Finish to Start)
Construct Gantt Chart of the project.
Transcribed Image Text:Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have to find the right sequence of activities in order to complete the project on time. Use Gantt (Bar) Chart and calculate total duration and determine the critical path of the project. Immediate Estimated Activity Predecessors Duration 2 weeks 4 weeks 10 weeks A 6 weeks 4 weeks S weeks 7 weeks 9 weeks 7 weeks 8 weeks G E, G F, 1 4 weeks 5 weeks 2 weeks 6 weeks K M K, L Immediate Predecessor (Finish to Start) Construct Gantt Chart of the project.
Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.