The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. ✔ Click the icon to view the product structure and the time-phased product structure. In addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Level 0 Item S More Info 1 Gross req Order release The product structure. T(1) S U (2) 2 V(2) W(2) X(2) Y(1) Z(3) Q G 2 Week 4 Y The time-phased product structure. Q V 5 W X TI U 5 6 Time in weeks S Lead Time (weeks) 2

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 2
units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make
U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z.
✔ Click the icon to view the product structure and the time-phased product structure.
In addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units
are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
Level
0
Item
S
More Info
1
Gross req
Order release
The product structure.
T(1)
S
(2)
2 V(2) W(2) X(2) Y(1) Z(3)
Q
Q
3
Week
4
Y
Z
The time-phased product structure.
Q
V
5
W
X
T
U
6
Time in weeks
S
7
Lead Time
(weeks)
2
Transcribed Image Text:The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. ✔ Click the icon to view the product structure and the time-phased product structure. In addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Level 0 Item S More Info 1 Gross req Order release The product structure. T(1) S (2) 2 V(2) W(2) X(2) Y(1) Z(3) Q Q 3 Week 4 Y Z The time-phased product structure. Q V 5 W X T U 6 Time in weeks S 7 Lead Time (weeks) 2
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.