The estimated times and immediate predecessors for the activities in a project at Howard Umrah's rotinal scanning company are given in tho following tablo. Assume that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity b Predecessor(s) Activity Predecessor(s) a m a 7. 10 13 10 12 A B 6 12 18 5 14 This exercise contains only parts a, b, c. d. and e a) Based on the activity time estimates, the expected timos and variance for each of the activities are (round your response to two decimal plačes) Expected Time Activity Variance A B It the time to complete the activitios on the critical path is nomaly distnbuted, thern the probabilty that the critical path will be finished in 22 weeks or less - (enter as a probability and round your response to two decimal places) 0 of 1 ques the time to complete the activites on the non critical path in normally distributed, then the probability that the non critical path will be finished in 22 weeks ar less (enter as a probability and round your response to two decimal places) a of t ques

Precision Machining Technology (MindTap Course List)
2nd Edition
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Chapter2: Measurement, Materials, And Safety
Section2.5: Quality Assurance, Process Planning, And Quality Control
Problem 10RQ: If an X-bar chart graph falls below the LCL or rises above the UCL, a machining process is said to...
icon
Related questions
Question
The estimated times and immediate predecessors for the activities in a project at Howard Umrah's rotinal scanning company are given in the following tablo. Assume
that the activity times are independent.
Time (weeks)
Immediate
Time (weeks)
Immediate
Activity
b
Predecessor(s) Activity
b.
Predecessor(s)
a
a
7.
10
13
10
12
A
B
6
12
18
14
This exercise contains only parts a, b, c, d, and e
a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places)
Expected
Time
Activity
Variance
A
B
If the time to complete the activitios on the critical path is nomally distributed, thern the probabilty that the critical path will be finished in 22 weeks or less -
(enter as a probability and round your response to two decimal places)
0 of 1 ques
the time to complete the activities on the non critical path in normaly distributed, then the probability that the non criical path will be finished in 22 weeks ar less
(enter as a probability and round your response to two decimal places).
0 of t ques
Transcribed Image Text:The estimated times and immediate predecessors for the activities in a project at Howard Umrah's rotinal scanning company are given in the following tablo. Assume that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity b Predecessor(s) Activity b. Predecessor(s) a a 7. 10 13 10 12 A B 6 12 18 14 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places) Expected Time Activity Variance A B If the time to complete the activitios on the critical path is nomally distributed, thern the probabilty that the critical path will be finished in 22 weeks or less - (enter as a probability and round your response to two decimal places) 0 of 1 ques the time to complete the activities on the non critical path in normaly distributed, then the probability that the non criical path will be finished in 22 weeks ar less (enter as a probability and round your response to two decimal places). 0 of t ques
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Project Management Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Precision Machining Technology (MindTap Course Li…
Precision Machining Technology (MindTap Course Li…
Mechanical Engineering
ISBN:
9781285444543
Author:
Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:
Cengage Learning