The iron load of 230/115V, 5KVA transformer is 200W. The copper loss at full load is 250W. Find the efficiency of transformer when delivering i). Full load power at unity power factor i1). Half full load power at 0.8 pf lagging

Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter3: Power Transformers
Section: Chapter Questions
Problem 3.32MCQ
icon
Related questions
Question
The iron load of 230/115V, 5KVA transformer is 200W. The copper loss at full load is 250W. Find the
efficiency of transformer when delivering
i). Full load power at unity power factor
ii). Half full load power at 0.8 pf lagging
Transcribed Image Text:The iron load of 230/115V, 5KVA transformer is 200W. The copper loss at full load is 250W. Find the efficiency of transformer when delivering i). Full load power at unity power factor ii). Half full load power at 0.8 pf lagging
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Maximum power transfer theorem
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning
Electricity for Refrigeration, Heating, and Air C…
Electricity for Refrigeration, Heating, and Air C…
Mechanical Engineering
ISBN:
9781337399128
Author:
Russell E. Smith
Publisher:
Cengage Learning