The Pee Tool Shop has four heavy presses it uses to stamp out prefabricated metal covers and housings for electronic consumer products. All four presses operate differently and are of different sizes. Currently the firm has a contract to produce three products. The contract calls for 400 units of product 1; 570 units of product 2; and 320 units of product 3. The time (in minutes) required for each product to be produced on each machine is as follows: Required: USE MS EXCEL BY SOLVING BE DETAILED WITH FORMULAS EXAMPLE (SUMPRODUCTB1:B2)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The Pee Tool Shop has four heavy presses it uses to stamp out prefabricated metal covers and housings for electronic consumer products. All four presses operate differently and are of different sizes. Currently the firm has a contract to produce three products. The contract calls for 400 units of product 1; 570 units of product 2; and 320 units of product 3. The time (in minutes) required for each product to be produced on each machine is as follows: Required: USE MS EXCEL BY SOLVING BE DETAILED WITH FORMULAS EXAMPLE (SUMPRODUCTB1:B2)
7:10 Sat, Jul 9 A A
The Pee Tool Shop has four heavy presses it uses to stamp out prefabricated metal covers and housings
for electronic consumer products. All four presses operate differently and are of different sizes.
Currently the firm has a contract to produce three products. The contract calls for 400 units of product
1; 570 units of product 2; and 320 units of product 3. The time (in minutes) required for each product
to be produced on each machine is as follows:
199
Product
1
2
3
1
35
40
38
Product
1
2
3
Machine
1
P78
67
84
2
41
36
37
Machine 1 is available for 150 hours, machine 2 for 240 hours, machine 3 for 200 hours, and machine
4 for 250 hours. The products also result in different profits, according to the machine they are
produced on, because of time, waste, and operating cost. The profit per unit per machine for each
product is summarized as follows:
Machine
3
34
32
33
2
P78
89
81
4
39
43
40
3
P82
92
90
4
P79
63
58
The company wants to know how many units of each product to produce on each machine to
maximize profit. Solve the model by using the computer.
<
25%
Transcribed Image Text:7:10 Sat, Jul 9 A A The Pee Tool Shop has four heavy presses it uses to stamp out prefabricated metal covers and housings for electronic consumer products. All four presses operate differently and are of different sizes. Currently the firm has a contract to produce three products. The contract calls for 400 units of product 1; 570 units of product 2; and 320 units of product 3. The time (in minutes) required for each product to be produced on each machine is as follows: 199 Product 1 2 3 1 35 40 38 Product 1 2 3 Machine 1 P78 67 84 2 41 36 37 Machine 1 is available for 150 hours, machine 2 for 240 hours, machine 3 for 200 hours, and machine 4 for 250 hours. The products also result in different profits, according to the machine they are produced on, because of time, waste, and operating cost. The profit per unit per machine for each product is summarized as follows: Machine 3 34 32 33 2 P78 89 81 4 39 43 40 3 P82 92 90 4 P79 63 58 The company wants to know how many units of each product to produce on each machine to maximize profit. Solve the model by using the computer. < 25%
Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.