The production planner for Rienzo, Inc. produces two chemicals: Alpha (A) and Delta (D). Two of his resources are constrained: Jaya, of which he can get at most 8,400 litres per week; and Sanga, of which he can get at most 4,600 litres per week. Each unit of Alpha chemical requires 16 litres of Jaya and 7 litres of Sanga, while a unit of Delta chemical uses 8 litres of each type of raw material. Profits for the Alpha blend are £3.00 per unit, and profits for the Delta blend are £5.00 per unit. Question 10 What is the objective function? A £1 A + £5 D = Z B £8 A + £16 D = Z C I do not wish to answer this question. D £3 A + £5 D = Z E £16 A + £8 D = Z F £7 A + £8 D = Z
The production planner for Rienzo, Inc. produces two chemicals: Alpha (A) and Delta (D). Two of his resources are constrained: Jaya, of which he can get at most 8,400 litres per week; and Sanga, of which he can get at most 4,600 litres per week. Each unit of Alpha chemical requires 16 litres of Jaya and 7 litres of Sanga, while a unit of Delta chemical uses 8 litres of each type of raw material. Profits for the Alpha blend are £3.00 per unit, and profits for the Delta blend are £5.00 per unit. Question 10 What is the objective function? A £1 A + £5 D = Z B £8 A + £16 D = Z C I do not wish to answer this question. D £3 A + £5 D = Z E £16 A + £8 D = Z F £7 A + £8 D = Z
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 107P
Related questions
Question
The production planner for Rienzo, Inc. produces two chemicals: Alpha (A) and Delta (D). Two of his resources are constrained: Jaya, of which he can get at most 8,400 litres per week; and Sanga, of which he can get at most 4,600 litres per week. Each unit of Alpha chemical requires 16 litres of Jaya and 7 litres of Sanga, while a unit of Delta chemical uses 8 litres of each type of raw material. Profits for the Alpha blend are £3.00 per unit, and profits for the Delta blend are £5.00 per unit.
Question 10
What is the objective function?
-
A£1 A + £5 D = Z
-
B£8 A + £16 D = Z
-
CI do not wish to answer this question.
-
D£3 A + £5 D = Z
-
E£16 A + £8 D = Z
-
F£7 A + £8 D = Z
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,