The project is to construct a lateral canal that will provide irrigation for 150 ha production area along the ricefields of a town and it is being considered by the municipality. The locality has two (wet and dry) croppings. A one (1) ha ricefarm yields 90 cavans for rainfed areas. The following costs have been identified. 800 meters long x 6 meters parcel of land at Php 950.00 per ha Land: Construction: 4,500,000.00 500,000.00 250,000.00 17 cav/ha 500,000.00 22% Annual O&M (government): Annual O&M (farmer irrigators): Rental receipts from irrigators: Convenience to farmers: Yield increase: Neglecting other factors associated with production yield increase, determine the B/C ratio of the project with a MARR of 10% per year if the project is to be used for 25 years. Is the project acceptable?

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question
The project is to construct a lateral canal that will provide irrigation for 150 ha production area along the
ricefields of a town| and it is being considered by the municipality. The locality has two (wet and dry)
croppings. A one (1) ha ricefarm yields 90 çavans for rainfed areas. The following costs have been
identified.
Land:
800 meters long x 6 meters parcel of land
at Php 950.00 per ha
4,500,000.00
500,000.00
250,000.00
Construction:
Annual O&M (government):
Annual O&M (farmer irrigators):
Rental receipts from irrigators:
17 çav/ha
Convenience to farmers:
500,000.00
Yield increase:
22%
Neglecting other factors associated with production yield increase, determine the B/C ratio of the project
with a MARR of 10% per year if the project is to be used for 25 years. Is the project acceptable?
Transcribed Image Text:The project is to construct a lateral canal that will provide irrigation for 150 ha production area along the ricefields of a town| and it is being considered by the municipality. The locality has two (wet and dry) croppings. A one (1) ha ricefarm yields 90 çavans for rainfed areas. The following costs have been identified. Land: 800 meters long x 6 meters parcel of land at Php 950.00 per ha 4,500,000.00 500,000.00 250,000.00 Construction: Annual O&M (government): Annual O&M (farmer irrigators): Rental receipts from irrigators: 17 çav/ha Convenience to farmers: 500,000.00 Yield increase: 22% Neglecting other factors associated with production yield increase, determine the B/C ratio of the project with a MARR of 10% per year if the project is to be used for 25 years. Is the project acceptable?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Property Damage
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning