You are the project manager on a $1,000,000 housing development project that has an estimated duration of five month. You are at the end of month two. According to the project estimate, your team should be done with 40% of the work. As of today, the project is 45% complete while 50% budget has been used. Show your conclusion about the project performance below. Choose the right options from the drop-down list. BAC = AC = PV = EV = CPI = SPI = Since CPI is the project is budget. , the project is of schedule. And since SPI is

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

2.

EV =
CPI =
SPI =
Since CPI is
the project is
budget.
And since SPI is
,the project is
of schedule.
more than 1
$100,000
$400,000
ahead
less than 1
$1,000,000
above
equal to 1
$500,000
0.9
$10,000,000
1.125
$450,000
Transcribed Image Text:EV = CPI = SPI = Since CPI is the project is budget. And since SPI is ,the project is of schedule. more than 1 $100,000 $400,000 ahead less than 1 $1,000,000 above equal to 1 $500,000 0.9 $10,000,000 1.125 $450,000
If the BAC is 1002, the CPI is 0.9, and the SPI is 1.2, what is the EAC-1?
Round the answer to two decimal places.
Answer:
If the BAC is 868, the AC = 1000, EV=800, CPI=0.8, what is the EAC-2?
%3D
Round the answer to two decimal places.
Answer:
You are the project manager on a $1,000,000 housing development project that has an estimated
duration of five month.
You are at the end of month two. According to the project estimate, your team should be done with
40% of the work.
As of today, the project is 45% complete while 50% budget has been used. Show your conclusion about
the project performance below. Choose the right options from the drop-down list.
BAC =
AC =
PV =
EV =
CPI =
SPI =
Since CPI is
the project is
budget.
of schedule.
And since SPI is
, the project is
Transcribed Image Text:If the BAC is 1002, the CPI is 0.9, and the SPI is 1.2, what is the EAC-1? Round the answer to two decimal places. Answer: If the BAC is 868, the AC = 1000, EV=800, CPI=0.8, what is the EAC-2? %3D Round the answer to two decimal places. Answer: You are the project manager on a $1,000,000 housing development project that has an estimated duration of five month. You are at the end of month two. According to the project estimate, your team should be done with 40% of the work. As of today, the project is 45% complete while 50% budget has been used. Show your conclusion about the project performance below. Choose the right options from the drop-down list. BAC = AC = PV = EV = CPI = SPI = Since CPI is the project is budget. of schedule. And since SPI is , the project is
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,