12. Lead time for completion of a job is a function of capacity and
Q: Referring to the above problem, solve it by the vogel approximation method
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: Where did you get service rate from?
A: Service rate is the amount of customers served per unit time in any system
Q: 6. A business hands out promotional fliers to 15,000 people. It is estimated that of those they…
A: Number of people to whom promotional fliers are handed = 15000 people Percentage of individuals who…
Q: 6. Marina also wants to insert a PivotTable that includes other Customer information so that she can…
A: The given excel sheet is prepared in excel as follows. Please note that only visible data (up to row…
Q: a. A loan processing operation that processes an average of 7 loans per day. The operation has a…
A: The utilization ratio is the percentage of time that a system is running. The efficiency ratio is…
Q: c) Choose the correct Pareto chart for the type of defects that have occurred. O A. 50- 40- 30- 20…
A: Here, from the above table, we could see that there are various reasons for defective shipment,…
Q: What is the probability that no customers are in the system (Po)? b. What is the average number of…
A: Note: We are allowed to solve first question only with all its sub-parts. Given: Arrival rate…
Q: How would you measure project success?
A: The phrase "project success" refers to the particular standard decided upon by the customer and the…
Q: The Brew House needs to decide which of two coffee maker designs is better environmentally. Using…
A: Revenue is limited to earnings from core company operations. Because it is the large figure at the…
Q: Northcutt manufactures high-end racing bikes and is looking for a source of gear sprocket sets.…
A: Supplier selection is a strategic decision in supply chain management. Total landed cost refers to…
Q: Explain the push-pull based supply chain system and argue why Ikea should adopt this system.
A: In the push-based system of the supply chain, production begins on the basis of forecasted or actual…
Q: enterprise wide risk management system (EWRMS) with particular emphasis on how this differs from a…
A: Basic risk management Organizations with…
Q: rent capabilities in terms o
A: Input needs, conversion processes, and output are taken into account during production system design…
Q: what is the Multi-Factor Productivity for Susan's orders processed if she costs $200 in Labor Costs?…
A: Productivity is about how much a person produces during the time they work. The productivity of an…
Q: S and S thester company wabts a 3-month moving average forecast. Ticket sales over the past 3 months…
A: Given data are stated below, Month Ticket sales Month 1 30000 Month 2 40000 Month 3 37500…
Q: Calculate the mean absolute percentage error (MAPE) for the cost equation you developed above.
A: MAPE stands for mean absolute percentage error. MAPE = (|(actual-forecast)/actual|*100)
Q: Reconstruct the given Business Process. Identify process that can be grouped into a sub-process.…
A:
Q: The Figure above shows the graphical solution for a linear programming with objective function Min.…
A: The graphical method is used to solve linear programming problems visually. Using the graphs, the…
Q: generates Monday through Thursday sales of $150, $125, $75, and $180. What sales on Friday would…
A: Let sales on Friday be x.
Q: 1.What are the decision variables 2.What is the objective functions 3. What are the 11 constraints…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: Labor utilization of clerks: % Labor utilization of typists: % Where is the bottleneck in…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Maximize C = 16A +218 subject to 9A +15B ≤ 22 10A + 3B ≤ 29 and A≥0, B20. What is the optimal value…
A: The graphical method of solving linear programs is a technique that uses graph paper and pencils to…
Q: 1. Supplier management in a lean system A. means an increase in the number of suppliers for each…
A: Supplier management is one of the most important aspects of manufacturing. It is a critical part of…
Q: ) Use excel to solve the following linear program. Max. 4X + 5Y s.t 10X + 2Y ≤ 30 3X + 2Y ≤ 12…
A: Given data is Objective function: Max Z=4X+5Y Subject to constraints: 1.) 10X+2Y≤302.) 3X+2Y≤123.)…
Q: A health and nutrition store stocks a multivitamin with an annual demand of 1,000 bottles has Co =…
A: Given information is: Annual demand = D = 1000 units Cost of ordering = Co = 24.50 Cost of holding =…
Q: WEEK 1 maner 234567 ∞ 8 FORECAST DEMAND 135 135 135 134 134 144 155 156 Week 1 2 3 4 5 6 7 8 ACTUAL…
A: MAD is the proportion between total absolute error values and the number of weeks considered to…
Q: Two independent methods of forecasting based on judgment and experience have been prepared each…
A: Given data is
Q: Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9,…
A: The late start time in the critical path can be solved by starting work on the project earlier than…
Q: The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to…
A: A critical path is a linear sequence of tasks that must be completed for completion of a project. A…
Q: Letz Products has two decisions to make, with the second decision dependent on the outcome of the…
A: Expected payoff at chance node = Probability 1 X Expected payoff event 1 + Probability 2 X Expected…
Q: Year Year Forecast (000) 1 2 3 4.00 7.00 5.00 1 5.00 Registrations (000) a) Calculate the forecasted…
A: The exponential smoothing forecast is a form of time series forecasting that is used to predict…
Q: The Barberton Municipal division of Road Maintenance is charged with road repair in the city of…
A: The operations level workforce plan is an important component of the overall business strategy. It…
Q: t one example of delivering poor quality on an IT project. What happened? What would you have done…
A: Studying and the use of facts era isn't a smooth subject. For the system to be implemented…
Q: the recommendation for this case study
A: The case describes a company from its initial stage to how it grew. The operations and functions of…
Q: 1.Differentiate between international and global sourcing management 2. Critically discuss the…
A: "Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Which is a viable strategy to manage an intermittent flow system better?
A: Note: We are required to do one question only. The intermittent flow system is different from the…
Q: The average daily demand and standard deviation of daily demand for a product is 800 and 12…
A: Daily demand = d = 800 units Standard deviation of daily demand = σ = 12 Replenishment lead time = L…
Q: If the actual cost for a WBS item is $ 9000, and its earned value is $ 6000, what is its cost…
A: Given data: Actual cost for = $ 9000, Earned value is = $ 6000,
Q: Compute the (s,Q) ordering policy that gives a 95% service level and the annual cost of the safety…
A:
Q: Calculate Show critical slack float ock / path 7
A: A project might have slack time if the project manager and the team can do something else while…
Q: Given the situation above with an output rate of five units per hour, a) Draw the network precedence…
A: Project schedule helps in calculating different values all related to the production cycle like the…
Q: You may need to use the appropriate technology to answer this question. Management Decision Systems…
A: Critical path is the takes the longest time to complete the project in an organisation.
Q: Disucss the functions of operation management in the manufacturing and production in any company.…
A: The role of operation management is to see that resources are properly transformed into goods and…
Q: The NextGen distribution is working on improving inventory management by performing an ABC Analysis.…
A: Find the Given details below: Given details: Item Hits Criticality 1 A B 2 C B 3 B C 4…
Q: A grocery store manager must decide how to best present a limited supply of milk and cookies to its…
A: The detailed solution is given in Step 2
Q: A manufacturing company produces single item product. The production manager decide to arrange 6…
A: Find the Given details below: Period 1 2 3 4 5 6 Forecast 112 157 126 176 124 181 Customer…
Q: What is the crossover point in miles between the hybrid vehicle and the alternative vehicle from a…
A: The Cost of the two cars must equal zero at the crossover point. Any vehicle's total Cost is the sum…
Q: Develop a Pareto chart of the following causes of poor grades on an exam: Number 1 2 3 4 5 Choose…
A: I have entered the given Data: Now Arrange the above data from High to low, i.e. Highest Frequency…
Q: Imagine a company that has a corporate strategic goal of operating a new food delivery service line.…
A: Imagine a company that has a corporate strategic goal of operating a new food delivery service line.…
Q: Min 3X+3Y s.t. 12X+4Y>=60 10X+5Y>=60 4X+8Y>=36 X,Y>=0 (X,Y) = ( )
A: Note : As no specific method is given I solved it using Graphical method. MIN zx = 3 x + 3…
Step by step
Solved in 3 steps
- Which of the following is not an MRP input? a. Forecast demand b. Sales orders c. Customer orders d. Bill of materials __________ Magnitude of the operations in one of the factors determining the Production Control Select one: True False _______ Deming Circle is not used for Continuous Quality Improvement. Select one: True False _______ Employee motivation is one of the personnel management function. Select one: True False ________ 2. Which of the following is an objective of scheduling? a. Increase Productivity b. Increase time of operation c. Increase Production cost d. Increase storage cost __________ Linear Programming is not suitable for problems only with objectives and constraints . Select one: True FalseA 2011 study published in the Harvard Business reported an average cost overrun of ... Select one: a. 70% b. 27% c. 15% d. 88% On of them is not consider tool or techniques to assist in schedule development: Select one: a. PERT b. Critical chain scheduling c. Gant chart d. MTA matrix tractability array cost is “ a resource sacrificed or foregone to achieve a specific objective Select one: True False Intangible costs or benefits are ...... Select one: a. easy to measure in monetary terms such as gold b. difficult to measure in monetary terms c. easy to measure in monetary terms such as dollar d. easy to measure in term of time planTh3 task is pr0vided in th3 pictur3. (creat3 a DATA FLOW DIAGRAM for the Creat3 a DATA FLOW DIAGRAM for the CASH RECEIPTS SYSTEM that is pr0vided in the pictur3 I WILL RAT3 TH3 TUT0R H3LPFUL IF ANSW3RED ASAP
- 1. In an assemble-to-order company, at which level should master scheduling take place? a. The end item level b. The raw material/component level c. None of the above levels d. It does not matter, any level will do e. The component/subassembly level 2. The final assembly schedule (FAS) a. Schedules customer orders as they are received based on components planned in the MPS b. None of the above c. Is used with make-to-stock products d. Is used with make-to-order products e. A and b above 3. The functions of a master production schedule are to: I. Plan material components. II. Plan capacity requirements. III. Keep priorities valid a. II, III and not I b. None of the above is a function of the MPS c. I, II and III d. I, II and III e. I, III and not II 4.The information needed to develop a master production schedule will be got from a. Inventory levels for individual end items b. None of the above c. The production plan d. The forecast of individual end…J as a Production Planner is highly concerned about the capacity for various reasons. Select which ones are valid reasons that J needs to be concerned about.. Multiple choice. Sufficient capacity in place to meet the customers demand on time. Capacity affects the cost efficiency of operations and the scheduling system. Capacity creation does require further investments. Capacity planning is the first step when an organization decides to produce more or new products.Wal Mart, although they are not a manufacturing company, uses sophisticated computer software to forecast sales and order products to be stocked in their stores so that they do not run out of the things shoppers are looking for. What kind of software system does Wal Mart likely use? Group of answer choices a) Inventory control b) Just-in-time ordering c) E-procurement d) Materials Requirement Planning (MRP)
- A processor makes two components, A and B, which are then packaged together as thei nal product (each product sold contains one A and one B). The processor can do onlyone component at a time: Either it can make As or it can make Bs. There is a setup timewhen switching from A to B.Current plans are to make 100 units of component A, then 100 units of component B,then 100 units of component A, then 100 units of component B, and so forth, where thesetup and run times for each component are given below.Component Setup/Changeover Time Run Time/UnitA 5 minutes 0.2 minuteB 10 minutes 0.1 minuteAssume the packaging of the two components is totally automated and takes onlytwo seconds per unit of the i nal product. This packaging time is small enough that youcan ignore it. What is the average hourly output, in terms of the number of units of packagedproduct (which includes one component A and one component B)?Up, Up, and Away is a producer of kites and wind socks.Relevant data on a bottleneck operation in the shop for theupcoming fiscal year are given in the following table:Item Kites Wind SocksDemand forecast 30,000 units/year 12,000 units/yearLot size 20 units 70 unitsStandard processing time 0.3 hour/unit 1.0 hour/unitStandard setup time 3.0 hours/lot 4.0 hours/lotThe shop works two shifts per day, 8 hours per shift, 200 daysper year. Currently, the company operates four machines,and desires a 25 percent capacity cushion. How many ma-chines should be purchased to meet the upcoming year’s de-mand without resorting to any short-term capacity solutions?WAI knows from historical records that approximately 40percent of its labor is used in Department 101 and 60 percentis used in Department 102. Th e reverse is true of machine time;60 percent is used in Department 101 and 40 percent is used inDepartment 102.(a) Calculate the labor and machine hours needed inDepartment 101 for each period of the MPS developed inProblem 4.(b) Calculate the labor and machine hours needed inDepartment 102 for each period of the MPS developed inProblem 4.
- Sized Rite is trying to determine how best to produce itsnew line of shoes for expanded feet. Demand for its w-i-d-eproducts is uncertain. Given the alternative processes andcosts below, determine at what level of demand you wouldchoose each process. Fixed Cost Variable CostProcess A $20,000 $ 5Process B $10,000 $10Supplier C $ 0 $202-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”, and “inspect”. If the capacity of activity “cook” determines the process capacity, which of the following statements are true? a- Activity “cook” is a bottleneck activity. b- The activity time of all the other five activities is shorter than activity "cook". c- Cycle time of the process of making hotdogs is equal=1/capacity of activity “cook”. d- Increasing the capacity of activity “grind” can increase the capacity of the process of making hotdogs. All statements are correct Only statement 'b' is correct Only statements 'a' and 'b' are correct Only statements 'a', 'b' and 'c' are correct Only statement 'a' is correct Only statement 'd' is correctSpikLock makes several lines of metal items. The most recent order has been for 1200 door lock units for an apartment complex developer. The sales and production departments must work together to determine delivery schedules. Each lock unit consists of three components: the knob and faceplate, the actual lock itself, and a set of two keys. Although the processes used in the manufacture of the three components vary, there are three areas where the production manager is concerned about the availability of resources. These three areas, their usage by the three components, and their availability are detailed in the table. Resource Knob and Plate Lock Key (each) Available Brass Alloy 12 5 1 15000 units Machining 18 20 10 36000 minutes Finishing 15 5 1 12000 minutes A quick look at the amounts available confirms that SpikLock does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each…