2. A Production line is to be designed to assemble a product. The assembly of this product requires three tasks, one of which requires 0.3 minutes to complete, one of which requires 1.7 minutes to complete, and one of which requires 0.9 minutes to complete. 1)What is the minimum possible cycle time of this assembly line? 2)What is the maximum possible cycle time of this assembly line?
Q: An assembly plant for the Blood Pressure RX, a portable blood pressure device, has 400 minutes…
A: Given - Task Performance Time (minutes) Task Must Follow Task Listed Below A 4 -…
Q: 3- A production process at Kenneth Day Manufacturing is shown in the following Figure The drilling…
A: Given- Sawing operation = 6 units/hrSanding operation = 6 units/hrDrilling operation = 2.4…
Q: Management has decided to cut down 3 seconds from each operation (operation 1 - 8) to improve…
A:
Q: how many stations are required for the line to produce the desired output.
A: Required number of workstation for producing a desired unit demand based on the available time is…
Q: snip
A: The efficiency of a production unit is not assessed with the quantity of work done. It is assessed…
Q: a) The cycle time for the production of a PDA = enter your response here
A: Project schedule helps in calculating different values all related to the production cycle like the…
Q: 1. What's the cycle time for this production line? 2. What's the theoretical minimum number of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 14. A production line is to be designed to assemble a product. The assembly of this product requires…
A: Given data is Task time of first task = 0.3 mins Task time of second task = 1.4 mins Task time of…
Q: snip
A: Balance Delay: Balance delay time is the amount of idle time on production assembly lines caused by…
Q: What is the total load times distance (load X distance) for each chef with this kitchen…
A:
Q: b) The cycle time for the production of a chair = 9.23 minutes (round your response to two decimal…
A: Cycle time is the actual time that a worker spends in the workstation to produce an item.
Q: snip
A: Various products cannot be produced in one step altogether. These products are manufactured in steps…
Q: a) What is the cycle time? b) What is the theoretical minimum for the number of work- stations that…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: A producer of inkjet printers is planning to add a new line of printers, and you have been asked to…
A: Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Three products go through a two step process of pre-production and final assembly. The processing…
A: We will find out the sequence by finding out the minimum amongst all the values in pre production as…
Q: The desired daily output for an assembly line is 300 units. This assembly line will operate 375…
A: Assembly line balancing is the process of assigning each task to a workstation in order to meet the…
Q: Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new…
A: Distance = work × load This formula is used to compute the distance. To compute the same, two tables…
Q: A product is completed when 18 tasks are done. These tasks are assigned to 6 workstations (each…
A: From the beginning of the first task to the finish of the last task, cycle time is the amount of…
Q: a machine installation job can be finished by 40 men in 40 days. how long will it take for 50 men to…
A: The details are as under 40 men complete installation in 40 days Time required by 50 men if work…
Q: Marilyn Hart, operations manager at Hart Electronics,faces assembly-line balancing problems. She has…
A: given information,
Q: This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the…
A:
Q: Mr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean…
A: This question is about assembly line balancing, here, There are 10 steps to produce the piece of…
Q: Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the…
A: Given - Task Time (Sec) Immediate Predecessor A 11 − B 15 A C 7 A D 4 B, C E 20 D
Q: 4. Draw the precedence diagram for this problem. 5. How many workstations should be set up in this…
A: Cycle time is the total time incurred to manufacture a particular item of the product by the team…
Q: Mega Corp. is designing a product layout for a new electronic product. They plan to use this…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the…
A: Assembly line balancing is a quantitative approach where there are infeasible options are given for…
Q: Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new…
A: Given, The flow matrix and distance matrix. The distance matrix can be mirrored to get the other…
Q: A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table…
A: Note: - Since we can answer only up to 3 sub-questions we will answers questions a, b, and c for…
Q: An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the totaltime…
A: Minimum cycle time = length of the longest task Therefore, the minimum cycle time = 2.4 minutes
Q: An assembly line must be designed to produce 50 packagesper hour. Th e following data in Table 10-17…
A: Note: As per the Bartleby guidelines, only the first three parts of the question have been answered.…
Q: 1.DG Fast Food has four activities in serving a customer: greet customer, take order, process order,…
A: As per Bartleby's guidelines, we only answer the first question in case multiple questions are asked…
Q: Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro…
A: Activity Immediate Predecessors Duration A - 10 B A 12 C A,B 8 D…
Q: Stanford Rosenberg Computing wants to establish anassembly line for producing a new product, the…
A: Note: As per the Bartleby guidelines, only the first three parts have been answered.
Q: Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the…
A: Given information Task Time Immediate Predecessors A 12 B 15 A C 8 A D 5 B, C E 20…
Q: Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro…
A: Given information Activity Duration Immediate predecessors A 10 B 12 A C 8 A, B D…
Q: snip
A: Product layout is opposite of process layout. In product layout, there is no specific section for…
Q: Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly line…
A: Given data: The firm ought to complete 96 instruments per 24-hour day. *As per guideline of…
Q: computer manufacturing assembly line the manager said that he wanted to produce 50 computers per…
A: Introduction: The term Business refers to an exchange of goods and services between the buyer and…
Q: The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new…
A: Total Production time per day=8 hour or 480 minutes Total demand per day=1440 cases
Q: (1) What is the theoretical minimum number of workstations? (2) Using the longest-task-time rule to…
A: As per the given data: Available time is 55 minutes and the number of units is 50 units, therefore…
Q: Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.…
A: This question is related to the topic of Production Management (Assembly line Balancing), this topic…
Q: Explain the importance of PQRST Key in designing a warehouse, your answer should contain a proper…
A: To do facility planning in a warehouse there are five key input data required to understand that is…
Q: Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new…
A: Materials processing is characterized as the series of steps or "unit tasks" utilized in the…
Q: A production assembly line of 7 seven activities designed to produce 120 units per hour and you have…
A: A line balancing is a process which helps to allot the right activities to the right workstation…
Q: snip
A: Assembly lines are the part of the production process which controls the material flow in the…
Q: What is the theoretical minimum for the smallest number of workstations that Helms can achieve in…
A: Task Time (min) Immediate Predecessors A 10 - B 12 A C 8 A, B D 6…
Q: 18. If station #2 is replaced with two parallel stations, each one performing tasks C and E what…
A: Cycle time is a proportionate time available to complete each unit of time. Here, we can identify…
Q: A manufacturing company is designing an assembly lineto produce its main product. Th e line should…
A: A bottleneck arises in a production system when workloads exceed the capacity of the manufacturing…
Q: The three-station work cell illustrated in Figure $7.7 has a product that must go through one of the…
A: In process operations bottleneck refers to the condition that a station or a task in the entire…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: Task a Time (min. .2 .2 .4 .1 .3 .2 .1 .2 Immediate Predecessor none a none none c, d be none £ g (A) Determine the maximum and minimum cycle time. (B) Determine the optimum cycle time. (C) What is the minimum number of stations needed? (D) Draw the precedence diagram. (E) Assign tasks to stations in order of most following tasks first.Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 15 A C 7 A D 4 B, C E 20 D Rosenberg's goal is to produce 175 PDAs per hour. a) The cycle time for the production of a PDA = nothing seconds (round your response to two decimal places). B) what's the minimum number of workstations in the assembly line? C) Can the minimum actually be reached when workstations are assigned?
- Management wants to design an assembly line that will turn out 800videotapes per day. There will be eight working hours in each day. The industrial engineeringstaff has assembled the information below: Task Time (min.) Immediate Follower a .2 b,d b .2 f c .4 b,e d .1 e e .3 f f .2 h g .1 h h .2 i i .6 none A) Determine the optimum cycle time (i.e., actual operating time/desired output).B) What is the minimum number of stations needed?C) Assign tasks to work stations.D) What is the efficiency of this assembly line?Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 15 A C 7 A D 4 B, C E 20 D Rosenberg's goal is to produce 170 PDAs per hour. a) The cycle time for the production of a PDA = enter your response here seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line=enter your response here (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to…A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,d
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow:Task Information for Kiko Teddy BearWorkElementTask Description ImmediatePredecessorTask Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C 15F Sew on mouth C 35G Attach manufacturer’s label B 15H Inspect and pack teddy bear D,E,F,G 40 d. What is the theoretical minimum number of workstations using the cycle time computed in” b “above? e. Assign tasks to workstations using the cycle time in “b” above. f. Calculate the efficiency and idle time percentage of the line.Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 14 A C 8 A D 4 B, C E 20 D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). Part 3 b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line=3(round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to Workstation 1 A ▼…Professional Image Briefcases is an exclusive producer ofhandcrafted, stylish cases. The company assembles eachcase with care and attention to detail. This laborious processrequires the completion of the six primary work elementslisted here a. Construct a precedence diagram for the manufacturingof briefcases.b. Compute the flow time required for assembling onebriefcase and the cycle time necessary to assemble 50cases in a 40-hour week.c. Balance the line and compute its efficiency.d. How would you change the line to produce 80 casesper week?
- Professional Image Briefcases is an exclusive producer ofhandcrafted, stylish cases. The company assembles eachcase with care and attention to detail. This laborious processrequires the completion of the six primary work elementslisted here.a. Construct a precedence diagram for the manufacturingof briefcases.b. Compute the flow time required for assembling onebriefcase and the cycle time necessary to assemble 50cases in a 40-hour week.c. Balance the line and compute its efficiency.d. How would you change the line to produce 80 casesper week? Work Element Precedence Time (min)A Tan leather — 30B Dye leather A 15C Shape case B 10D Mold hinges and fixtures — 5E Install hinges and fixtures C, D 10F Assemble case E 10Francis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: Task Performance Time (mins) Task Must Follow Task Listed Below A 8 − B 11 A C 10 A, B D 9 B, C E 8 C F 4 D, E A C F B E D In the diagram, there are 6 circles labeled using the letters from A to F. There are 8 of arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: A to B, A to C, B to C, C to D, B to D, C to E, D to F, and E to F. Part 2 a) The theoretical minimum number of workstations=55 (round your response up to the…