4. You have prepared the project information that is given below: Activity Predecessor Normal Time Normal Cost Crash Cost Crash Time A B с D E F G A A A B с D, E, F 3 6 3 10 6 4 5 30 40 30 20 50 60 50 40 70 60 50 80 90 70 - What is the normal critical path? - What is the normal project duration? - What is the normal project cost? 1 2 1 1 3 3 1
Q: Write the objective function. Refer to a solved problem, and the chapter. What are you trying to…
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: Below matrix shows one of the important data used in project management, identify the name of the…
A: Name of the Matrix: The given matrix is the RACI matrix which is one of the project…
Q: The City Commission of Nashville has decided to build a botanical garden and picnic area in the…
A: Gantt chart Gantt chart is a visual representation of loading and scheduling process used in…
Q: Draw the following Network Diagram:
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. If the decision-maker knows nothing about the probabilities of the four states of nature, what is…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Describe. the history and purpose of the balanced scorecard
A: An indicator of managerial performance is a balanced scorecard. It is employed to ascertain the…
Q: In Exercises 9-20, use the simplex method to solve the given problem. (In each case the objective…
A: Given LP- Max Z = x1+ 2x2Subject to -x1+ 4x2≤8x1+x2≤12x1, x2≥0
Q: Problem 15-12 (Algo) Santa Cruz Bottling is a manufacturer of organic soft drinks on the coast of…
A: Given, Cities with the relevant x-coordinates, y-coordinates and number of cases. Let x coordinates…
Q: Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - -…
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: High-Price Oil corporation owns a network of pipelines that is used to transport oil from a drilling…
A: Formulate a spreadsheet as shown below:
Q: One of New England Air's top competitive priorities is on-time arrivals. Quality VP Clair Bond…
A: Given, Sample size n = 100 Total samples k = 30 Number of observations n*k = 100*30 = 3000 Sum of…
Q: ombro Industries is in the process of automating one of its plants and developing a flexible…
A: Given data: Month 1 2 3 4 Wait time /order before - start of production 9 10.9 12 14…
Q: Three decision makers have assessed utilities for the following decision problem (payoff in…
A: Given data: Payoff Table: Decision Alternative S1 S2 S3 d1 20 50 -20 d2 80 100 -100…
Q: Explain the role of TPS in Supply chain management
A: TPS stands for transaction processing system. This is an information system that is commonly used by…
Q: Indicate which of the following is an all-integer linear program and which is a mixed-integer linear…
A: Objective Functions: Max 70x1 + 65 x2 Constraints: Subject to 9x1 + 4.5 x2 ≤ 400 5…
Q: Employee Wanda Trews was working in the manufacturing facility at Coves Industrial. The employees of…
A: The detailed solution is given in Step 2
Q: Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are…
A: Also, the demand for 550 units of component 1 must be satisfied. Convert available hours in minutes…
Q: Read the summary below and answer the questions that follow: The Orange Girl – all the juice and…
A: Inventory carrying cost: - The cost incurred to the company for storing the products after…
Q: Sarah and Jennifer have just graduated from college at the University of Washington in Seattle and…
A: A minimum distance problem tends to seek minimum distance via only 1 route.
Q: Instructions - Outline the components of Total Quality Management [TQM] programs that have been…
A: Total quality management (TQM) is a corporate strategy that aims to meet and exceed customer…
Q: The following jobs are waiting to be processed at a small machine center JOB DUE DATE 10 20 30 40 50…
A: Given-
Q: Because of a backlog of orders for model A grates, Kane's manager had decided to produce at least…
A: Let model A units be x model B units be y Objective is to maximize the profits: Maximize Z = 4x +…
Q: Sarah and Jennifer have just graduated from college at the University of Washington in Seattle and…
A: A minimum distance problem tends to seek minimum distance via one of the many available routes.
Q: A well-known coffee shop sells about 300 gallons of its most popular product each week. The…
A: The (s, Q) policy is a continuous review system in which the order is placed when the inventory…
Q: Muffins are delivered daily to a cafeteria. Demand averages 40 muffins per day and has a standard…
A: Given data: Average Demand = 40 Muffins Standard Deviationσ = 5 Muffins/day Purchase price = 20…
Q: Tesla Corporation has three different factories (A, B and C) where they make Premium Electric…
A: Transshipment is a special category of linear programming problem wherein the optimal solution is…
Q: Please give fast answer. And give typed answer. I wil give positive rating. Economic Production…
A: Given data: Annual demand(D)= 50,000 units Production per day(P) =600 units Holding cost (H)= $1.00…
Q: Using a 95% confidence level, the upper and lower control limits are: Upper control limit…
A: Formulae used: σp =P -+ (1-P)n For control limit: UCLp =P + Z×σp
Q: 14. The demand for Krispee Crunchies is experiencing a decline. The company wants to monitor demand…
A: Formulae used: Regression Equation: Y=a +bX Slope (b) =N∑XY-∑X ∑YN∑X2-(∑X)2 Intercept a=∑ Y -b∑XN…
Q: Employee Wanda Trews was working in the manufacturing facility at Coves Industrial. The employees of…
A: The detailed solution is given in Step 2
Q: 17. The manager of a utility company in the Texas panhandle wants to develop quarterly forecasts of…
A: Firstly Average Demand per year: Quarter Year 1 Year 2 Year 3 Year 4 1 103.5 94.7 118.6 109.3…
Q: quality management facilitate the operation management ?
A: Operation management is the term used to describe the methods used by businesses to maximize…
Q: Explain why an effective budget requires an organisation to proper Strategic and operating plans in…
A: Creating and managing a financial plan that forecasts income and spending for some time is known as…
Q: Draw the network diagram making use of the Activity list information below, clearly indicating Early…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Edwards Machine Tools needs to purchase a new machine. The basic model is slower but costs less,…
A: Find the Calculations below: The maximum and minimum values for each model are shown in the above…
Q: a) Draw and label a precedence diagram for the production process b) Compute the cycle time, number…
A: Project schedule helps in calculating different values all related to the production cycle like the…
Q: Johnson Peters holds the position of operations manager for a small container and bottle…
A: Given data: Annual Demand (D) =8,000 units/day Unit cost = $150 Holding cost (H)=$15% of unit price…
Q: Given: Demand = 1248 items per year, Inventory period or Time between orders = 13 weeks. Q5.1.…
A: Economic order quantity (EOQ) is the optimal order quantity that helps in minimizing the total…
Q: What is Dynamic Programming (DP)? Provide two main components of DP.
A: Dynamic Programming is an approach to solving a problem by dividing the main problem into sub-parts…
Q: Case study below: Shoprite nets $10 million from sale of Uganda, Madagascar and Nigeria unitsSouth…
A: Introduction: Corporate Strategy A long-term strategy that an organization implements to build a…
Q: The activity list shown below represents the activities, the job logic and activities’ durations of…
A: Activity On Arrow (AOA) network is a type of convention used to present network diagram i.e., to…
Q: ment is a skill that needs to be constantly developed. Identify one skill required in this scenario…
A: A combination of talents called project management abilities is required to start, plan, and carry…
Q: a) Sequence the jobs according to LPT. According to the LPT rule, the sequence of jobs should be 10,…
A: Scheduling is the process of arranging production activities in order to complete the manufacturing…
Q: Fernando Garza's firm wishes to use factor rating to help select an outsourcing provider of…
A: Find the Calculation methods below: Weighted average Score = ∑ (Score * Ratings) Given details:…
Q: he Digital Firm, 15th Edition What things should Target Canada have done differently to
A: What Target Canada Needs to Do Differently to Succeed
Q: Argue why “attractiveness of the company” and “reputation and image” are fundamental for…
A: A brand's reputation is how its customers, competitors, stakeholders, and the general public…
Q: What is one advantage of doing the work within the organization instead of outsourcing it?
A: Many companies aim to spend as little as possible on overhead expenses in order to increase their…
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements…
A: Formulae used: To determine ending inventory & Subcontract Units Ending inventory = (Previous…
Q: a. Let X, number of skirts produced, X₂= number of dresses produced, X₂ = number of sport coats…
A: The objective is to maximize the total profit. Profit per unit of X1 = $ 10 Profit per unit of X2…
Q: NiceShoes retail store sells one model of casual shoes all around the year. The demand for this…
A: Given data: Demand =750 pairs every three months. Then Annual Demand (D)= 750×4 = 3000 units…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- #3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost (Direct) Cost (Direct) A None 3 2 $300 $408 B A 3 3 $100 $100 C A 1 1 $200 $200 D B and C 3 2 $400 $550 E D 2 1 $500 $900 F E 3 3 $200 $200 G F 2 2 $200 $200 The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $408, 15 days they will be $350, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect) project cost?Using the information in Table-1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Task Description Duration (WorkingDays) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I Handover and Go-Live 5 H (i) Determine the critical path of the project (ii) Calculate the planned duration of the project in weeks (iii) Identify any non-critical tasks and the float (free slack) on each.
- ANSWER THE FOLLOWING QUESTIONS ( SHOW ALL WORKINGS) 1. Determine and state the critical path for this project. 2. What are the expected time and the variance of the project? 3. What is the probability that the project is completed in 22 or fewer weeks 4. What date should be set such that there is a 94% chance of completion within that time?2. A small software development project at Krishna Dhir's firm has five major activities. The times (in days) are estimated and provided in the table below: Activity Immediate Predecessor a m b A − 2 5 8 B − 3 6 9 C A 4 7 10 D B 2 5 14 E C 3 3 3 a) The expected completion time for this project is ___ days (enter your response as a whole number). b) The project variance of completion time is ___ days (enter your response as a whole number). c) The probability that this projectbe can be completed in 17 days or less is ____ (keep two decimal places). d) The probability that it will take more than 17 days to complete this projectbe is __ (keep two decimal places). e) The due date that yields a 98% chance of completion is ____ days (keep two decimal places).You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…
- Draw CPM network of activities tabulated below: 1. Calculate the expected duration and the standard deviation for the critical path. 2. Compute the followings: (a) The probability that the project will finish by the end of day 50 (b) The probability that the project will finish at day 52 (c) The probability that the project will finish before the start of day 49. (d) The completion date with at least a 95% confidence level1)Draw the project network. 2)Calculate the early start, early finish, late start, late finish times of the project. 3)Find the critical path of the project. 4)Calculate the time required to complete the project. 5)Calculate the free time in the project network. (Also, show the times you want on the table you will create.)A project consists of five activities listed below. The project network is shown for the activities. The critical path is B-C-E and the expected completion time is 8. Optimistic Most Probable Pessimistic Activity Time (hr) Time (hr) Time (hr) A Floor sanding 3 4 5 B Paint mixing 0.5 1 1.5 C Ceiling painting 1 5.5 7 D Wall painting 1 2 9 E Floor buffing 1 2 3 What is the probability that the project can be completed within 9 hr.?
- A small project consisting of eight activities has the following characteristics: Time estimate (in weeks) Activity Preceding activity Most Optimistic time (a) Most likely time (m) Most Pessimestic time (b) A None 2 4 12 B None 10 12 26 C A 8 9 10 D A 10 15 20 E A 7 7.5 11 F B,C 9 9 9 G D 3 3.5 7 H E,F,G 5 5 5 What is the project standard deviation?You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…a. What is the project's duration if only normal times are used? b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is ____day(s).?