A department works on 8 hours shift, 288 days a year and has the usage data of a machine, as given below: Annual Demand Processing time (Standard time in hours) Product (units) A 325 B 450 4 550 6 Calculate: (a) Processing time needed in hours to produce products A, B and C (b) Annual production capacity of one machine in standard hours (c) Number of machines required

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question
100%
A department works on 8 hours shift, 288 days a year and has the usage
data of a machine, as given below:
Processing time
(Standard time in hours)
Annual Demand
Product
(units)
A
325
5
B
450
4
550
6
Calculate:
(a) Processing time needed in hours to produce products A, B and C
(b) Annual production capacity of one machine in standard hours
(c) Number of machines required
Transcribed Image Text:A department works on 8 hours shift, 288 days a year and has the usage data of a machine, as given below: Processing time (Standard time in hours) Annual Demand Product (units) A 325 5 B 450 4 550 6 Calculate: (a) Processing time needed in hours to produce products A, B and C (b) Annual production capacity of one machine in standard hours (c) Number of machines required
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,