a) Given the following assignment matrix of processing costs for four jobs at four machine centres: Machine Centres Job I II IV A 15 14 12 16 23 22 25 24 31 34 32 33 D 21 32 44 53 i) Find an allocation of jobs to the machine centres so that the total processing cost is minimum. B.
Q: 2. CREATE A NETWORK DIAGRAM FOR FOLLOWING ACTIVITIES GIVENIN THE TABLE. (2.5 MARKS) S. NO ACTIVITY…
A:
Q: 8. Operations times of servicing of Washing Machines are given below. The first operation involves…
A: a.
Q: a. Draw a precedence diagram. b. Compute for the cycle time. c. Compute for the theoretical minimum.
A: WE ARE ALLOWED TO DO THE FIRST THREE SU-PARTS ONLY AT A TIME. THE ANSWER IS AS BELOW:
Q: Time (week) Activity Dependency Resource b a m A 1.5 2 2.5 3 B 2 2.5 6 1 3 2 А, В B 1.5 0.5 2.5 2…
A: Expected time of each activity, Activity to tm tp te=to+4⋅tm+tp6 σ2=(tp-to6)2 A…
Q: the routing M1 M2, determine the optin Job Pa Pa 6. 6. 3. 11 7. 3. 2. %in
A: Given - Job 1 2 3 4 5 6 Machine M1 5 6 11 1 7 2 Machine M2 4…
Q: 1. What's the cycle time for this production line? 2. What's the theoretical minimum number of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 3. A producer of inkiet printers is planning to add a new line of Rrinters, and xou haxs been asked…
A: Given:
Q: I need help with chapter 17, problem 2 (17.2) Question is A-D
A: a)Arrange the activities into two logical sequences:
Q: a. Construct an arrow diagram for this problem b. Determine the critical path and compute the…
A: ANSWER IS AS BELOW:
Q: 5. Management wants to design an assembly line that will turn out 800 videotapes per day. There will…
A: Note- We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: - In a sagittal diagram, the minimum number of imaginary activities is .
A:
Q: The operations manager of an instruments company is balancing an assembly line. The company needs to…
A: given,
Q: What factors would you take into account in deciding whether to split a job?
A: Splitting larger jobs into smaller lots is termed as job splitting. This is used to reduce the…
Q: 14. The following precedence network is used for assembling a product. You have been asked to…
A: Find the Given details below: Given details: Task Time(mins) a 2.0 b 3.0 c 3.0 d 6.0…
Q: You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their…
A: "Since you have posted a question with multiple sub-parts, we will solve the first 3 sub-parts for…
Q: 3. A product line consists of four items processed through one of four machines. The machines are…
A: Find the Given Details below: Given Details Machine Job M1 M2 M3 M4 A 20 90 40 10 B 40…
Q: A. Instruction: 1. Construct both AOA diagram for the following data. a) b) Identify the paths and…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Chapter Six Process Selection and Facility Layout The tasks shown in the following precedence…
A: a) Cycle time= Operating time/ Desired output = 440 minutes per day/ 275 units per day = 1.6…
Q: 4. Draw the precedence diagram for this problem. 5. How many workstations should be set up in this…
A: Cycle time is the total time incurred to manufacture a particular item of the product by the team…
Q: As part of a major plant renovation project, the industrial engineering department has been asked to…
A: a. Precedence Diagram
Q: Pane Grammar As part of a major plant renovation project, the industrial engineering department has…
A: Given data: *As per guideline 3 subparts are answerable, repost the remaining part
Q: Problem #2 A contractor has six jobs awaiting processing at a workstation that is also a bottleneck…
A: Total no. of jobs = 6 Current day = 7 Flow time (Current) = Flow time (Previous) + Duration…
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: A network diagram is a visual representation of a project which identify the activity relationship…
Q: ABC Company is an accounting firm that has 3 new clients. Project leaders will be assigned to the…
A:
Q: 9. At a local university, the Student Commission on Programming and Entertainment (SCOPE) is…
A: Note: - Since the exact that has to be answered is not specified, we will answer the first…
Q: 5. Develop a resource schedule in the loading chart that follows. Use the parallel method and…
A: Given Details: Given details: ID RES DUR ES LF SL 1 2 3 4 5 6 7 8…
Q: Q2: For the information shown in table below, draw the resources allocation diagram depending on…
A: In the question, we have been given the activity table, for each activity, we have predecessor…
Q: 17.6. Decenture has four new IT hires available for assignment to ERP implementation projects. Their…
A:
Q: a) Draw a precedence diagram and mark the workstation assigned to each task. b) Assuming a 10 hours…
A: Cycle time is the total time spent on a particular activity by the workers to manufacture a product.…
Q: The following table contains information concerning four jobs that are awaiting processing at awork…
A: According to FCFS (First Come, First Served), the sequence is A-B-C-D. According to SPT (Shortest…
Q: a) Construct the network and find the duration. b) Find critical path and slacks for all…
A: Below is the solution:-
Q: Question in comments
A: (A) Following formula can be used to calculate the cycle time: Consider production time be 3600…
Q: Time (week) Activity Dependency Resource a m 1.5 2 2.5 2 2.5 6 A 3 B C 2 3 А, В B D 1.5 2 2.5 2 0.5…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Q. A few relationships between activities can be applied in precedence network. From Table 1,…
A: Given Details: Gantt Chart (Model) : This Gantt chart (Manual) prepared for understanding purpose.
Q: Management wants to design an assembly line that will turn out 800 videotapes per day. There will be…
A: N=Desired outputOperating time=8000.2+0.2+0.4+0.1+0.3+0.2+0.1+0.2+0.68×60=800×2.3480=3.83~4…
Q: a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this…
A: Tasks are assigned to workstations on the basis of total cycle time and minimum number of…
Q: 5. As part of a major plant renovation project, the industrial engineering department has been asked…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: As part of a major plant renovation project, the industrial engineering department has been asked to…
A: Assembly operation to achieve an output of 260 units per 8-hour day Task a b c d e f g Duration…
Q: Task Follow Task Weeks (Duration) Task Description Manning Level A Start 1.0 Site Cleaning 3 Obtain…
A: Given data is
Q: The following schedule was prepared by the production manager of Marymount Metal Shop:Determine a…
A:
Q: Q5: Identify the most cost effective solution set in the following Job/Resource Matrix using…
A: Given that: Jobs\Resource 1 2 3 4 5 6 7 8 A 12 7 14 15 6 8 11 9 B 9 13 7 12 7 5 19 10 C 11…
Q: MACHINE JOB A 12 16 14 10 8 13 7 15 12 11 12 3
A: Find the Given details below: Given details: Machine Job A B C D 1 12 16 14 10 2 9 8…
Q: I. Gannt Chart. For the precedence relationships of the activities, assume the following:…
A: Forward Pass-Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish =…
Q: Q6: Identify the most cost effective solution set in the following Job/Resource Matrix using…
A: Work\Job 1 2 3 4 5 6 7 8 A 12 7 14 15 6 8 11 9 B 9 13 20 12 7 5 14 10 C 11 10 6 15 10 7 12 11…
Q: 2. Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of…
A: Time variance is a distinction between the standard hours and genuine hours appointed to a task. The…
Q: Tasks Employee Ali 1 3\ 10 16 32 Sami 14 22 40 34 Rami 22 24 Using the Hungarian Method to find the…
A: In the Hungarian method, find the smallest element in each row and subtract the smallest element…
Q: Schedule the following six jobs through two machines in sequence to minimize the l owtime using…
A:
Q: E F G H Consider the following job 1 TOTAL TASK DAYS UNTIL CRITICAL Estimated Days ASSEMBLY 2 3 JOB…
A: lateness is the difference of flowtime and due date FCFS assigns task as per the order they come…
Step by step
Solved in 2 steps
- Refer again to Problems( Using the information in Problem(The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure. ), construct agross material requirements plan. ). In addition to100 units of S, there is also a demand for 20 units of U, which isa component of S. The 20 units of U are…The Campus Bookstore's inventory of books is as follows. Hardcover: textbooks, 5085; fiction, 1914; nonfiction, 2364; reference, 1807Paperback: fiction, 2622; nonfiction, 1496; reference, 2278; textbooks, 1901 The College Bookstore's inventory of books is as follows. Hardcover: textbooks, 6041; fiction, 2090; nonfiction, 1975; reference, 1996Paperback: fiction, 3067; nonfiction, 1723; reference, 2947; textbooks, 2202 (a) Represent Campus's inventory as a matrix A. A = Textbooks Fiction Nonfiction Reference Hardcover Paperback (b) Represent College's inventory as a matrix B. B = Textbooks Fiction Nonfiction Reference Hardcover Paperback (c) Suppose that the two companies decide to merge. Write a matrix C that represents the total inventory of the newly amalgamated company. C = Textbooks Fiction Nonfiction Reference Hardcover…Colete Trucks, Inc., a builder of high quality road cement has about 5,000 items in its inventory. They hire Kevin, IE intern for the summer assign as inventory clerk. The firm determined that it has 500 A items, 1750 B items, and 2,750 C items. Company policy is to count all A items every month (every 20 working days), all B items every quarter (every 60 working days), and all C items every 6 months (every 120 working days). Kevin has been counting 80 items for each day. Is his daily inventory count accurate? Why or Why not? If not, how many should be its stocktaking? *
- The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure.2. Bob is considering to rent a space to sell lunch box. His rent would be $5,000/month. Each lunch box would incur $4 material cost and $5 labor cost. If Bob wants to break-even by selling 500 lunch boxes per month, how much should he charge for each lunch box? Select one: a. $10 b. $1 c. $14 d. $19Using the information in Problem (The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure. ), construct a netmaterial requirements plan using the following on-hand inventory.
- A manager has the option of purchasing one, two, or three machines. Fixed costs and potential volumes are as follows:Number ofMachinesTotal AnnualFixed CostsCorrespondingRange of Output1 $ 9,600 0 to 3002 15,000 301 to 6003 20,000 601 to 900Variable cost is $10 per unit, and revenue is $40 per unit.a. Determine the break-even point for each range.b. If projected annual demand is between 580 and 660 units, how many machines shouldthe manager purchase?not certain how to calculate because it says each item sells for 17,000. also, I wouldnt be sure which numbers to graph with 1. A small producer of machine tools wants to move to a larger building, and has identified twoalternatives. Location A has annual fixed costs of $800,000 and variable costs of $14,000 perunit; location B has annual fixed costs of $920,000 and variable costs of $13,000 per unit1.The finished items sell for $17,000 each.A) State the total-cost formula:B) Calculate a second point for each location: Set a selected quantity = ____ Use q=150 units C) Sketch the total-cost lines for the locations on a single graph.Mick Karra is the manager of MCZ Drilling products which produces a variety of especially valves for oil field equipment. Recent activity in the oil fields has cause demand to increase drastically, and a decision has been made to open a new manufacturing facility. Three locations are being considered, and the size of the facility would not be the same in each location Thus, overtime might be necessary at times. The folowing table gives the total monthly cost (in 1000s) for each possible location under each demand posibility. The probabilities for the demand levels have been determined to be 20% for low demand, 30% for medium demand, and 50% for high demand Demand is Low Demand is medium Demand is High Ardmore, OK 85 110 150 Sweetwater, TX 90 100 120 Lake Charles, LA 110 120 130 (a) Which location would be selected based on the optimistic criterion? (b) which location would be selected based on the pessimistic criterion? (c) which location would be selected based on the…
- please solve D only (a) What is the cycle time necessary to achieve the desired rate of production? =12min(b) Using the longest element rule, create workstations to balance the line,attempting to get as close as possible to the theoretical minimum numberof workstations.(c) What is the efficiency and idle time of the line balance? =72.22%(d) The company considers that if the lamps are successful with the publicit may need to increase production to 30,000 units. The company thinksthe simplest solution is to obtain two more production lines, thus havingtriple capacity. Another option is to re-balance the line. Considering thata single worker is assigned to a work station, determine which option(more production lines or re-balancing) yields the smallest labour size.The Doan Modianos Manufacturing Company isputting out seven new electronic components. Each ofModianos'eight plants has the capacity to add one more product to its currentline of electronic parts. The unit manufacturing costs forproducing the different parts at the eight plants are shown in theaccompanying table. How should Modianos assign the new productsto the plants in order to minimize manufacturing costs?I need solution of 2.34 as possible as please