Chapter Six Process Selection and Facility Layout The tasks shown in the following precedence diagram are to be assigned to workstations with the intent of minimizing idle time. Management has designed an output rate of 275 units per day. Assume 440 minutes are available per day. a. Determine the appropriate cycle time. b. What is the minimum number of stations possible? c. Assign tasks using the "positional weight" rule: Assign tasks with highest following times (includ- ing a task's own time) first. Break ties using greatest number of following tasks. d. Compute efficiency. 0.3 minute 0.4 minute 0.2 minute 0.1 minute 0.5 minute 0.3 minute i. a e b 0.6 minute 1.2 minutes 0.6 minute

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Chapter Six Process Selection and Facility Layout
27
The tasks shown in the following precedence diagram are to be assigned to workstations with the
intent of minimizing idle time. Management has designed an output rate of 275 units per day. Assume
440 minutes are available per day.
SOLVED PROBLEMS
Problem
a. Determine the appropriate cycle time.
h What is the minimum number of stations possible?
c. Assign tasks using the "positional weight" rule: Assign tasks with highest following times (includ-
ing a task's own time) first. Break ties using greatest number of following tasks.
d. Compute efficiency.
0.3 minute
0.4 minute 0.2 minute 0.1 minute 0.5 minute 0.3 minute
a
0.6 minute
1.2 minutes
0.6 minute
Transcribed Image Text:Chapter Six Process Selection and Facility Layout 27 The tasks shown in the following precedence diagram are to be assigned to workstations with the intent of minimizing idle time. Management has designed an output rate of 275 units per day. Assume 440 minutes are available per day. SOLVED PROBLEMS Problem a. Determine the appropriate cycle time. h What is the minimum number of stations possible? c. Assign tasks using the "positional weight" rule: Assign tasks with highest following times (includ- ing a task's own time) first. Break ties using greatest number of following tasks. d. Compute efficiency. 0.3 minute 0.4 minute 0.2 minute 0.1 minute 0.5 minute 0.3 minute a 0.6 minute 1.2 minutes 0.6 minute
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Facility layout
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.