A highway bridge is being considered for replacement. The new bridge would cost $X and would last for 24 years. Annual maintenance costs for the new bridge are estimated to be $25,000. People will be charged pll of $0.29 per car to use the new bridge. Annual car traffic is estimated at 390,000 cars. The cost of collecting the toll consists of annual salaries for six collectors at $12,000 per collector. The existing bridge can b efurbished for $1,400,000 and would need to be replaced in 24 years. There would be additional refurbishing costs of $75,000 every five years and regular annual maintenance costs of $21,000 for the existing ridge. There would be no toll to use the refurbished bridge. If MARR is 15% per year, what is the maximum acceptable cost (X) of the new bridge? E Click the icon to view the interest and annuity table for discrete compounding when the MARR is 15% per year. Choose the correct answer below. OA. The maximum acceptable cost of the new bridge is $976,079. O B. The maximum acceptable cost of the new bridge is $2,166,975. OC. The maximum acceptable cost of the new bridge is $1,638,694. O D. The maximum acceptable cost of the new bridge is $1,496,573.

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter10: Capital Budgeting: Decision Criteria And Real Option
Section: Chapter Questions
Problem 17P
icon
Related questions
Question
A highway bridge is being considered for replacement. The new bridge would cost $X and would last for 24 years. Annual maintenance costs for the new bridge are estimated to be $25,000. People will be charged a
toll of $0.29 per car to use the new bridge. Annual car traffic is estimated at 390,000 cars. The cost of collecting the toll consists of annual salaries for six collectors at $12,000 per collector. The existing bridge can be
refurbished for $1,400,000 and would need to be replaced in 24 years. There would be additional refurbishing costs of $75,000 every five years and regular annual maintenance costs of $21,000 for the existing
bridge. There would be no toll to use the refurbished bridge. If MARR is 15% per year, what is the maximum acceptable cost (X) of the new bridge?
Click the icon to view the interest and annuity table for discrete compounding when the MARR is 15% per year.
Choose the correct answer below.
A. The maximum acceptable cost of the new bridge is $976,079.
O B. The maximum acceptable cost of the new bridge is $2,166,975.
OC. The maximum acceptable cost of the new bridge is $1,638,694.
O D. The maximum acceptable cost of the new bridge is $1,496,573.
O E. The maximum acceptable cost of the new bridge is $1,703,741.
Transcribed Image Text:A highway bridge is being considered for replacement. The new bridge would cost $X and would last for 24 years. Annual maintenance costs for the new bridge are estimated to be $25,000. People will be charged a toll of $0.29 per car to use the new bridge. Annual car traffic is estimated at 390,000 cars. The cost of collecting the toll consists of annual salaries for six collectors at $12,000 per collector. The existing bridge can be refurbished for $1,400,000 and would need to be replaced in 24 years. There would be additional refurbishing costs of $75,000 every five years and regular annual maintenance costs of $21,000 for the existing bridge. There would be no toll to use the refurbished bridge. If MARR is 15% per year, what is the maximum acceptable cost (X) of the new bridge? Click the icon to view the interest and annuity table for discrete compounding when the MARR is 15% per year. Choose the correct answer below. A. The maximum acceptable cost of the new bridge is $976,079. O B. The maximum acceptable cost of the new bridge is $2,166,975. OC. The maximum acceptable cost of the new bridge is $1,638,694. O D. The maximum acceptable cost of the new bridge is $1,496,573. O E. The maximum acceptable cost of the new bridge is $1,703,741.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Fundamentals Of Financial Management, Concise Edi…
Fundamentals Of Financial Management, Concise Edi…
Finance
ISBN:
9781337902571
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage