a. Construct a precedence diagram and compute the lead time for the process. b. If the demand for pizzas is 120 per night (5:00 p.m. to 1:00 a.m.), what is the cycle time? c. Balance the line and calculate its efficiency.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
7.18. The Speedy Pizza Palace is revamping its order-processing and
pizza-making procedures. In order to deliver fresh pizza fast, six ele-
ments must be completed.
Work Element
Precedence
Time (Min)
A Receive order
-
B Shape dough
А
1
C Prepare toppings
A
D Assemble pizza
В, С
E
E Bake pizza
D
F
Deliver pizza
E
3
a. Construct a precedence diagram and compute the lead time
for the process.
b. If the demand for pizzas is 120 per night (5:00 p.m. to
1:00 a.m.), what is the cycle time?
c. Balance the line and calculate its efficiency.
d. How would the line change to produce 160 pizzas per night?
2]
3.
Transcribed Image Text:7.18. The Speedy Pizza Palace is revamping its order-processing and pizza-making procedures. In order to deliver fresh pizza fast, six ele- ments must be completed. Work Element Precedence Time (Min) A Receive order - B Shape dough А 1 C Prepare toppings A D Assemble pizza В, С E E Bake pizza D F Deliver pizza E 3 a. Construct a precedence diagram and compute the lead time for the process. b. If the demand for pizzas is 120 per night (5:00 p.m. to 1:00 a.m.), what is the cycle time? c. Balance the line and calculate its efficiency. d. How would the line change to produce 160 pizzas per night? 2] 3.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,