a. What is the Upper Control Limit? [ Select ] b. What is the Lower Control Limit? [ Select] c. Based on your evaluation, is the output of the Thompson-5000 under control? [ Select ] >

Glencoe Algebra 1, Student Edition, 9780079039897, 0079039898, 2018
18th Edition
ISBN:9780079039897
Author:Carter
Publisher:Carter
Chapter10: Statistics
Section10.4: Distributions Of Data
Problem 19PFA
icon
Related questions
Question

Answer A through F

Sample Avg. 956
1013
1001
977
987
1012
1067
1033
Calculate the UCL and LCL at a 99.73% (z-3) confidence level:
a. What is the Upper Control Limit?
[ Select ]
b. What is the Lower Control Limit?
[ Select ]
c. Based on your evaluation, is the output of the Thompson-5000 under control?
[ Select ]
After re-reviewing the documentation for the new machine, you realize that you made a minor mistake: the
standard deviation is supposed to be 20, not 5.
d. What is the upper control limit?
[ Select ]
e. What is the lower control limit? [Select ]
[ Select
f. Are the lots that Thompson-5000 is producing lots in control?
[ Select ]
>
>
<>
>
Transcribed Image Text:Sample Avg. 956 1013 1001 977 987 1012 1067 1033 Calculate the UCL and LCL at a 99.73% (z-3) confidence level: a. What is the Upper Control Limit? [ Select ] b. What is the Lower Control Limit? [ Select ] c. Based on your evaluation, is the output of the Thompson-5000 under control? [ Select ] After re-reviewing the documentation for the new machine, you realize that you made a minor mistake: the standard deviation is supposed to be 20, not 5. d. What is the upper control limit? [ Select ] e. What is the lower control limit? [Select ] [ Select f. Are the lots that Thompson-5000 is producing lots in control? [ Select ] > > <> >
It's your first day on the job as a new Operations Manager for a biopharmaceutical manufacturer. You are
currently overseeing the pilot plant, and need to ensure that output is consistent. A newly purchased
machine, called the Thompson-5000, produces bags with a standard deviation of 5 grams. The following
table contains the data for a sample size of four, taken daily over the past 8 days:
Day
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
Sample Avg. 956
1013
1001
977
987
1012
1067
1033
Calculate the UCL and LCL at a 99.73% (z=3) confidence level:
a. What is the Upper Control Limit? [Select ]
b. What is the Lower Control Limit? [ Select ]
c. Based on your evaluation, is the output of the Thompson-5000 under control?
[ Select ]
After re-reviewing the documentation for the new machine, you realize that you made a minor mistake: the
standard deviation is supposed to be 20, not 5.
d. What is the upper control limit? [Select ]
>
<>
Transcribed Image Text:It's your first day on the job as a new Operations Manager for a biopharmaceutical manufacturer. You are currently overseeing the pilot plant, and need to ensure that output is consistent. A newly purchased machine, called the Thompson-5000, produces bags with a standard deviation of 5 grams. The following table contains the data for a sample size of four, taken daily over the past 8 days: Day Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Sample Avg. 956 1013 1001 977 987 1012 1067 1033 Calculate the UCL and LCL at a 99.73% (z=3) confidence level: a. What is the Upper Control Limit? [Select ] b. What is the Lower Control Limit? [ Select ] c. Based on your evaluation, is the output of the Thompson-5000 under control? [ Select ] After re-reviewing the documentation for the new machine, you realize that you made a minor mistake: the standard deviation is supposed to be 20, not 5. d. What is the upper control limit? [Select ] > <>
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Ring
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill