Activity 2: Consider the following immediate preceding activity table. Draw the network and calculate the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activity. Obtain the critical path. Activity Preceding Activity Estimated occurrence time B C A A 11 3. D. B. D. C,E G, I H. L. J.K.L 24606D365

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Hi there! Could you please help me at my activity. I kinda have difficulties in doing the network diagram. The question below is the thing that is about to have an answer. The image will show the table above and below that we need to consider to be able to solve the problem. Hope for soonest reply. Thanks!

 

ACTIVITY 2:

Consider the following immediate preceding activity table. Draw the network and calculate the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activity. Obtain the critical path.

 

Note: the things to consider in the picture is only the activity 2. No need to consider the summative test 3 below. Thanks a lot!

10:30 O & O
3O 100%
LP2 in CE 7_.docx.pdf
Slack
Critical
Activity
(LF - EF)
Path?
A
Yes
Yes
Yes
D
No
Yes
Yes
No
4
No
No
Yes
1
No
Yes
M
4.
No
Yes
Activity 2:
Consider the following immediate preceding activity table. Draw the network
and calculate the earliest start time, the earliest finish time, the latest start time
and the latest finish time of each of the activity. Obtain the critical path.
Estimated occurrence time
Activity
A
Preceding Activity
A
A
11
C
D
D
4
H.
C,E
F
K
G. I
3
H
6
J,K,L
LEARNING PACKET 2 Construction Methods and Project Management
16
1.2.5 Assessment
Summative Test 3
In a separate sheet of paper answer the following (hand-written):
1. Given below is the list of activities with respective durations of a single-
storey residential project, make a logical arrangement of activities by
filling out the column for Predecessor Activities.
2. Construct a Network Diagram.
3. What is the project duration if no delays will occur?
4. What are the activities in the Critical Path?
5. What is the Early Start and Early Finish of each activity?
6. What is the Late Start and late Finish of each activity?
Activities
Duration
Predecessors
1. Clearing and Grabbing
| 3 DAYS
II
Transcribed Image Text:10:30 O & O 3O 100% LP2 in CE 7_.docx.pdf Slack Critical Activity (LF - EF) Path? A Yes Yes Yes D No Yes Yes No 4 No No Yes 1 No Yes M 4. No Yes Activity 2: Consider the following immediate preceding activity table. Draw the network and calculate the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activity. Obtain the critical path. Estimated occurrence time Activity A Preceding Activity A A 11 C D D 4 H. C,E F K G. I 3 H 6 J,K,L LEARNING PACKET 2 Construction Methods and Project Management 16 1.2.5 Assessment Summative Test 3 In a separate sheet of paper answer the following (hand-written): 1. Given below is the list of activities with respective durations of a single- storey residential project, make a logical arrangement of activities by filling out the column for Predecessor Activities. 2. Construct a Network Diagram. 3. What is the project duration if no delays will occur? 4. What are the activities in the Critical Path? 5. What is the Early Start and Early Finish of each activity? 6. What is the Late Start and late Finish of each activity? Activities Duration Predecessors 1. Clearing and Grabbing | 3 DAYS II
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.