Amy Xia's p lant was designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day because of the time needed to change equipment betweenstyles of hammers. What is the utilization?
Q: Robert produces 300 units of a product per hour and30 units are needed to fi ll a container. It…
A: N = No of KanbansD = 300T = 0.25SS = 0.1C = 30N = DT(1+SS)/CN = 300×0.25(1+0.1)/30N = 2.75
Q: A U.S. Postal Service supervisor is looking for ways to reduce stress in the sorting department.…
A: Given: Safety stock variable α = 0.25 Average waiting time + Material handling time= 30 minutes…
Q: . If the takt time increases, the operation requires:a. more workers.b. fewer workers.
A: The operation manager has the responsibility to keep an eye on working on the marketing manager so…
Q: Imagine that a GT parts cell is producing parts at the cycle time required by its downstream…
A: The employment of a step‐by‐step structured method to outline MCM cells more efficiently and produce…
Q: Describe four potential problems that might develop when operating a large number of processes at…
A: An operational unit or manufacturing unit consists of number of dependent and independent processes.…
Q: A company produces a line of golf putters composed of three models. The demandfor model A is 500 per…
A: In any organization, there is various production process operating at a point of time producing…
Q: Currently, Rock View Restaurant has a single window with one person who takes the order, gather the…
A: given,
Q: The process capacity- students/hour.(Difficulty Level-Hard)
A: The efficiency of any input, be it labor or machine is assessed based on its ability to produce or…
Q: A manufacturing process has a i xed cost of $150,000 per month. Each unit of product being produced…
A: The break-even point for any organization is the calculation o the point where the organization is…
Q: hundred picces will flow through from the first machinc A to the final machine 1 on the given…
A:
Q: For a batch size of 40 parts, what is the capacity of stage 1 in (parts per minute)? 0.57
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Rene steering makes 100 000 steering wheels per month. The firm works for 20 days in month, each day…
A: Given: Number of steering wheel = 1,00,000/ month Working days in a month = 20 total shifts in a day…
Q: A company that makes shopping carts for supermarkets and other stores recently purchased some new…
A: Company X makes shopping carts which is getting to buy new equipment. the subsequent is that the…
Q: In a sandwich production factory, making each ham and cheese sandwich consists of a number of…
A: Time Taken to complete the activity = 7 minutes each No. of Workers = 5 Working Hours = 12 hours a…
Q: A manufacturer has been shipping his product (moderately heavy machines), mounted only on skids…
A: Given:Car capacity load = 42 tonsManufacturer loaded previously = 30 tons in each carCarload freight…
Q: A manufacturer's average WIP inventory for Part #2934 is 900 parts. The workstation produces parts…
A: Little's law states lead time (aka flow time) = Work in progress / Thorughput this can also be…
Q: Guesstimate how much work-in-process inventory they would expect to see in a production line that…
A: Work-in-progress refers to the raw material which is used to produce the finished product.
Q: Which of the following items would be considered a resource in the operations of amovie theater?a.…
A: A movie theater is described as a place where people go for entertainment.
Q: The boss at the Precision Machine Shop needs to de-finish the personnel policy,which minimises all…
A: Given that: For junior attendant: λ = 8 μ = 10 For junior attendant: λ = 8 μ = 16
Q: Consider a highly automated processing plant having a capacity of 100 tons/day of 1-) · product and…
A: Given Data :- Highly automated processing plant capacity = 100 tons/ day Annual Operation = 300…
Q: A firm has redesigned its production process so that it now takes 8 hours for a unit to be made.…
A: Production process take time(T) = 8 hour Old process take time(t) = 15 hour Flow rate(R) = 2 units…
Q: Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and…
A: Productivity is that the ratio between the output volume and therefore the volume of inputs for a…
Q: In the Toyota Production System, jidoka refers to:(a) level production, where different models are…
A: Jidoka” is a Japanese word which has the meaning “automation”. The word says it as an “automation…
Q: A work center containing 7 machines with the same capacity operates 2 shifts per day 6 days per week…
A: Capacity management is the process of ensuring that a company maximises its potential operations and…
Q: For a particular operation, the setup time is 10 minutes and the run time is 50 minutes to produce a…
A: Formula:
Q: A manufacturing process has a fixed cost of $150,000 per month Each unit of product being produced…
A: Given Fixed cost = $ 150,000 contains material =$25 each unit labour per unit = $45 completed unit…
Q: 100 bars per hour
A: given, production = 180000 bars effort = 3 shifts per day 8 hrs. operate = 250days per year
Q: PROCESSING TIME PER UNIT (Minutes) Product Annual Demand Machine A Machine B 1 20,000 3 4 15,000 21…
A: Find the Given details below: Given details: Machine Cost ($) A 110000 B 40000…
Q: Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and…
A: (a)The productivity for 640 work hours is : given , Current Loaves per month = 1,600 loaves Total…
Q: Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and…
A: Given that, The output is 1,500 loaves per month andEmployees are paid $8 per hour. Productivity =…
Q: A process has a yield of 50 percent. How many units are needed as inflow to create anoutflow of 40…
A: Answer - (c) - 80 Given that, Yield percent = 50% Outflow = 40 units per day
Q: The Sime to assemble the first na production line is 19 hours. The leaming rate is 0.92.…
A: Given data: Time to assemble the first unit(T1) = 19hours Learning rate(p) = 0.92
Q: An Electric Motor manufacturer has an annual production of 10,000 units. The electric motor ends are…
A: A) Electric motor annual production = 10,000 units Aluminum die casting 1 batch = 2500 units Motor…
Q: Video One, a Blu-ray disc player manufacturer, produces two models of Blu-ray players. The mini-…
A:
Q: . Kinga Doll Company manufactures eight versions of its popular girl doll, Shari. Thecompany…
A: Process Capacity Process Capacity is the output magnitude of machines or workers. Process capacity…
Q: A process has 10 resources and two types of flow units. How many columns will therebe in the demand…
A: Columns = 102 = 5 There are 5 columns will there be in the demand table
Q: The casino is considering the purchase of a second coin-wrapping machine What impact would this have…
A: All the purchases of a business affect its operations in some way or the other.
Q: Use MOST to determine the number of TMUs associated with each of the following scenarios: A line…
A: Maynard operation sequence technique (MOST) is a pre-identified motion time method that is employed…
Q: A process has six resources and three types of flow units. How many rows will there bein the demand…
A: As process has six resources and three types of flow units Demand matrix=63…
Q: Rick Wing has a repetitive manufacturing plantproducing automobile steering wheels. Use the…
A: In the above mentioned question Rick wig has 305 working days and requirement is to determined the…
Q: Considering the constraint in processing, which combination of Products A and B maximizes the total…
A: The answer is as below:
Q: Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and…
A: Productivity is given as the ratio of output and total cost.
Q: Carlos Gonzales is production manager at an assembly plantthat manufactures cordless telephones. Th…
A: Formula:
Q: A company operates 8 hours per shift, two shifts per day, five days a week with 12 hours maintenance…
A: Operating hour(h) = 8 Number of per day shift(s) = 2 Days per week (d) = 5 Maintenance hour(M) = 12…
Q: When a patient enters the Valley Health Clinical Laboratory to have his blood drawn and a Chemistry…
A: Given information:Number of techs (N) = 3Operating time per day (H) = 8 hours…
Q: We would expect to see in a manufacturing cell layout which of the following
A: Cellular manufacturing, also known as work cell optimization, is a method for increasing efficiency,…
Q: The product is sold at $3 per unit. Assume that the cost of a drilling machine (fixed cost) is…
A: Below is the solution:-
Amy Xia's p lant was designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day because of the time needed to change equipment between styles of hammers. What is the utilization? |
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- A manufacturer's average WIP inventory for Part #762 is 882 parts. The workstation produces parts at the rate of 275 parts per day. Use the Excel template Little's Law to find the average time a part spends in this workstation. - Slugger, Inc. assembles Baseball Bats with aluminum handles in an assembly line using four workstations. Management wants an output rate of 550 bats per day using a 11.5-hour workday. What is the cycle time?Jason Carter works for a producer of soaps that come inpackages of 6 each. His job is to fi ll the packages with soap, andhe is expected to process 30 packages an hour. Th e facility whereJason works uses a kanban production system in which eachcontainer holds 5 packages of soap. It takes 20 minutes to receivethe packages he needs from the previous workstation. How manykanbans are needed for the fi lling process?. Aquatica makes underwater camera housings for divers. The process begins with a solid rectangular block of aluminum that is used to make a single housing. A computer numerically controlled (CNC) machine drills into the block to make the metal “frame” of the housing. Each block requires 15 minutes of drilling. The frame is then chemically treated in a series of baths. There is ample capacity in the treating stage. Finally, a worker must manually attach the various buttons and components to the metal housing. This assembly takes 120 minutes per housing per worker and Aquatica has 6 workers trained to do this task. The CNC machine requires a 30-minute setup time before the production of a batch can begin. a. If the CNC machine produces 14 housings between setups, what would be its capacity (in housings per hour)? b. Assuming the process is supply-constrained, what is the utilization (as a number between 0 and 1) of the CNC machine if it operates in batches of 14 housings? c. Assuming…
- 3. At Golf Co. product is automated to load golf balls into packaging. On an average day, the equipmentcan load 25 cases per hour, where each case contains 20 boxes and each box contains 12 balls.After maintenance, the machine is loading a little faster so that it takes 0.2 seconds less time to load onegolf ball into a box compared with the normal speed.How many cases per hour can the machine load at this new rate?Formtech Inc. produces transformers. Each order is custom designed and manufactured for the customer. Each order goes through 3 phases: Transformer Design, which takes 4 weeks. Procurement, which has a lead time of 8 weeks. Assembly and Testing, which takes 4 weeks The design group can handle only 4 projects at any given time. The other groups are not capacity constrained. How much total work-in-process (number of projects started but not yet completed) does the company typically have? (Hint: Little's Law)What is OEE and also calculate the OEE from the given data in below table Items Data Shift Length 8 Hours Breaks (2) 15 minute and (1) 30 minute Downtime 47 minutes ideal Cycle Time 1.0 seconds Total Count 19,271 widgets Reject Count 423 widgets
- Taco House Taco House has a special on Wednesday nights from 5:00-10:00 PM: $5 for a Mega Taco. There are two cooks on duty during this time. They have an 80% utilization and a 90% efficiency. If it requires 4 minutes to prepare a Mega Taco, approximately how many Mega Tacos is Taco House able to produce during the Wednesday night special? Group of answer choices 108 162 216 153 182 144A manufacturer's average WIP inventory for Part #1845 is 776 parts. The workstation produces parts at the rate of 255 parts per day. Use the Excel template Little's Law to find the average time a part spends in this workstation.XYZ Leather Company manufactures and sells two products, wallets and belts, in its two-department plant. Operating data pertaining to the two products are as follows: Wallets Belts Selling price per unit P30 P50 Cost per unit: Variable manufacturing costs P8 P15 Variable marketing costs P2 P3 Fixed manufacturing costs P5 P5 Fixed marketing costs P6 P1 Cutting Finishing…
- Is there a way to increase the machine's output while minimizing the time it requires maintenance?“How many dozen should I put in the proofer?” asked Elizabeth, the new baker at the Sands Cafeteria. Rami El‐Hussieny was the day shift operations manager, and, unfortunately, he did not know how to answer Elizabeth's question. What she wanted to know was simple enough: How many dozen rolls should be placed in the proofer in anticipation of the night's dinner business? The problem was that the frozen dinner roll dough used at the Sands Cafeteria needed to be proof for at least 2 hours prior to being baked for 15 minutes. If too many rolls were proofed, they would never be needed, but they would still have to be baked and made into bread dressing or even tossed out. If too few dozen were proofed and the night was busier than anticipated, they would run out of “Fresh Baked Rolls” (one of the restaurant's signature items), and Rami knew that the night manager would be really upset. It was a daily guess, and sometimes Rami missed the guess! He wondered if a prebaked roll with a shelf life…Rene steering makes 100 000 steering wheels per month. The firm works for 20 days in month, each day comprises of three 8 hour shifts. An assembly worker produces 10 steering wheels per hour; the firm needs ----- number of workers for each shift?