An analyst has started preparing a spreadsheet as shown below. Column A contains the headings for various parameters and Column B contains the analyst's range names to be used in Excel. A B 1 Price per Unit 2 Cost per Unit Price_Per_Unit CostPerUnit Profit_per_Unit 3 Profit per Unit 4 5 Fixed Costs FixedCosts VariableCosts$ 6 Variable Costs Label each of the following range names as "Correct" if is a valid range name in Excel or "Incorrect" if the range name is not valid for use in Excel. Proposed Range Name Price Per Unit CostPerUnit Profit_per_Unit FixedCosts VariableCosts$
Q: A company produces and sells luxury goods and is able to control the demand for the product by…
A: A company produces and sells luxury goods and can control the demand for the product by varying the…
Q: The setting is a Ralph Lauren outlet store, and the product line is Polo golf shirts. A product…
A: The complete values of given spreadsheet is as follows - Quantity Price Total Rev…
Q: A company has 5 jobs to be done. The table below shows the cost of assigning the ith machine,…
A: We are using the Hungarian method to solve above given problem- The Hungarian strategy is a…
Q: A machine shop has an order for 12 000 pcs of a machine part that requires anti-corrosive…
A: Below is the solution:-
Q: An analyst is constructing a simple model to determine the gross and net profit of a product, given…
A: Gross Profit =Profit per unit times quantity = 2×19400 =…
Q: Grass MixMix RequirementsWrigleyNo more than 50% tall fescue At least 20% mustang fescuePastureAt…
A: ANSWER : Now we need to create this question as an assignment problem. The mixes will be in column…
Q: A manager wants to know how many units of each product to produce on a daily basis in order…
A: A = quantity of product A B = quantity of product B C = quantity of product C
Q: XYZ Corporation manufactures two products, Simple and Complex. The following annual information was…
A: Given data Total annual fixed cost = P18000 Plant capacity = 12000 hours
Q: Leach Distributors packages and distributes industrial supplies. A standard shipment can be packaged…
A: Linear programming problem: Max 6x1 + 10x2 + 8x3 s.t 2x1 + x2 + 3x3 <= 180 2x1 + 6x2 + 4x3 = 240…
Q: A local printing company provides a custom printing service. Since each job is differ- ent, demand…
A: Period 1 2 3 4 5 Total Sales Forecast 100 100 100 100 100 500 Planned Production 105 105 105 105…
Q: Determine the overhead application rates for the producing departments using each of the three…
A: THE OVERHEAD APPLICATION RATES UNDER THREE METHODS ARE AS BELOW:
Q: A person sells and installs A, B and C. The table shows, for example, that it takes 3 hours to sell…
A: Product No. of Units Selling Hours per Unit Installation Hours per Unit Profit per Unit A x 1 1…
Q: 3-2) The optimal quantity of the three products and resulting revenue for Taco Loco is: A) 28 beef,…
A: Given, Max R = 14Z + 13Y + 17Xsubject to:Beef 2Z + 3Y + 4X ? 28Cheese 9Z + 8Y + 11X ? 80Beans 4Z +…
Q: Leach Distributors packages and distributes industrial supplies. A standard shipment can be packaged…
A: Based on the data given, we understand it is a Linear Programming Problem. The decision variables…
Q: FarmFresh Foods manufactures a snack mix called TrailTime by blending three ingredients: a dried…
A: Given Information: D = Number of ounces of dried fruit mix in the blend N = Number of ounces of nut…
Q: Suppose a certain manufacturing company produces connecting rods for 4- and 6-cylinder automobile…
A: Letx4 = the amount of 4-cylinder connecting rods produced next week. x6 = the amount of 6-cylinder…
Q: Using the attached template answer the following question. (Note that the data from P06_40.xlsx is…
A: Given data is Available to invest = $25 million per year
Q: Formulate a linear integer program that generates a feasible production plan to maximize the total…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: An analyst is constructing a simple model to determine the gross and net profit of a product, given…
A: Given that - Profit per unit $5 Quantity 18,200 Gross profit ? Total costs 8,300 Net…
Q: The company wants to determine how much of each paint to produce to maximize its gross income. The…
A: THE ANSWER IS AS BELOW:
Q: RMC, Inc., is a small firm that produces a variety of chemical products. In a particular production…
A: i. value of objective function = $1633.33 Dual price: highlighted in yellow: note: dual price…
Q: 2. A company has to minimize its cost = 200X + 300Y, subject to the following constraints: X + Ys 50…
A:
Q: Two alloys, A and B, are made from four metals, I, II, III, and IV, according to the follow- ing…
A: Let, xij be tons of ore i allocated to j where i = 1,2,3,4 j = A, B wj is the tons of alloy j…
Q: Leach Distributors packages and distributes industrial supplies. A standard shipment can be packaged…
A: The detailed solution is given in Steps ahead.
Q: Based on the following sensitivity analysis, which of the following products would be considered…
A: Using the sensitivity report:
Q: Note: This problem requires Excel. A firm offers two different prices on its products, depending…
A: Let, P1 = Number of units of product 1 to be produced Q1 = Number of units of product 1 to be…
Q: Barlow Company manufactures three products—A, B, and C. The selling price, variable costs, and…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: A. Compute the current break-even sales (units). B. Compute the anticipated break-even sales…
A: Break even point sale units = (Fixed cost / Contribution margin per unit ) Contribution margin per…
Q: The following data pertain to the operating budget of a certain manufacturing company Capacity per…
A: Given data, Sales- $681,00 Fixed cost- $294,000 Variable cost- $313,260
Q: A company produces a single type of product. The product sells for $9 per unit. The customer demands…
A: Given data: Month Demand (units) Holding cost Production cost Production capacity M1 55 0.1…
Q: What should be the production volume for that quarter?
A: Material requirement plan will helps the management to identify the timely ordering of items with…
Q: In the spreadsheet model shown below, an analyst makes the following data entries. Cell ВЗ В4 В5 B6…
A: Find the Given details below: Given details: Cell B3 B4 B5 B6 Value 113000 90000 119000…
Q: The ABC Company makes two products that can be produced on two different production lines. Both…
A: Given data is, Objective function: Max Z==500x1+700x2 Subject to: 1.) 3x1+2.50x2≤8002.) 5x1+4x2≤600…
Q: Bahrain International Company has 1400 KG of Raw Material to make two products: X1 and X2. There are…
A: The question is related to maximization of linear programming.
Q: Hello, Below is the question from Statistic Chapter Linear Programming and the solution is required…
A: Following is the excel model:
Q: Bullseye Shirt Company makes three types of shirts: athletic, varsity, and surfer. The shirts are…
A: Decision Variable: Suppose- Xij be the yards of fabric of the ith ingredient used in the jth…
Q: A Make-or-Buy DecisionTriple X Company manufactures and sells refrigerators. It makes some of the…
A: If part has been manufactured: Fixed cost: $50,000 Labor cost: $1,25,000 Factory overhead: $60,000…
Q: A firm is considering importing some products to sell in a local market. The unit price and cost for…
A:
Q: An appliance manufacturer produces two models of microwave ovens: H and W. Both modelsrequire…
A: Given Information: Oven – H Oven-W Total Fabrication (hours) 4 2 600…
Q: A manufacturing firm closed down the production of a certain unprofitable product line. This…
A: Decision variables: Let ; Number of units of A to be produced=x1 Number of units of B to be…
Q: company operates a farm on which sheep are raised. The farm manager has determined that for the…
A:
Q: Taxes The function T(x) represents the tax bill T of a single person whose adjusted gross income is…
A: Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Budgeted direct labor costs for the current month would be
A: budgeted labor cost indicating the total value of planned direct labor cost based n total planned…
Q: A company manufactures two types of products. Each product type needs a turning process at the lathe…
A: Here we have (A) Decision Variables :Number of Type 1 Products = T1Number of Type 2 Products = T2
Q: RMC, Inc., is a small firm that produces a variety of chemical products. In a particular production…
A: given,
Q: Friendly Waste Co. runs three different factories and is required by law to safely dispose of…
A: THE ANSWER IS AS BELOW:
Q: In research, it is very important to identify the different types of variable. Variables may assume…
A: Below is the solution:-
Q: A paper published in the Harvard Business Review points out a new way to calculate economic profit…
A: An individual's productivity is how much work they can do in a given measure of time. It's a…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- 19. What combination of x and y will yield the optimum for this problem? Maximize $3x + $15y, subject to (1) 2x + 3y ≤ 12 and (2) 5x + 2y ≤ 10 and (3) x, y ≥ 0. Part 2 A. x = 0, y = 3 B. x = 2, y = 0 C. x = 0, y = 0 D. x = 0, y = 4 E. x = 1, y = 5Variable cells Cell Name Final Value Reduced Cost Objective Coefficient Allowable Increase Allowable Decrease $B$6 Activity 1 0 425 500 1E+30 425 $C$6 Activity 2 27.5 0.0 300 500 300 $D$6 Activity 3 0 250 400 1E+30 250 Constraints Cell Name Final Value Shadow Price Constraint R.H. Side Allowable Increase Allowable Decrease $E$2 Benefit A 110 0 60 50 1E+30 $E$3 Benefit B 110 75 110 1E+30 46 $E$4 Benefit C 137.5 0 80 57.5 1E+30 If the coefficient for Activity 1 in the objective function changes to $50, then the objective function value: Multiple Choice will decrease by $450. is $0. will decrease by $2750. will remain the same. can only be discovered by resolving the problem.3. Elana owns a consulting business that helps software companies market their services to school districts. She earns an average of $4635.7 for every contract one of her client companies signs with her help. In order to be able to run her business, she needs to cover $7,000/month (rent, licenses, etc.). The average costs associated with each contract are $1676.6. How many contracts must she facilitate each month in order to break even? a. -2.37 b. 2.37 c. 10966.14 d. 1.51 e. -1675.09 f. None of the other options.
- A4) Finance 15. Which of the following are restrictions on use of property? (i) Council zoning regulations (ii) How accessible the property is to public transport (iii) Clauses in the property title (iv) Locality aesthetic environment Select one: a. (i) & ( iii) only b. (i), (iii) & (iv) c. all of themQuestion for reference: For the linear program Max 2A + 3Bs.t. 1A+2B <= 6 5A+3B <= 15 A, B >= 0 find the optimal solution using the graphical solution procedure. What is the value of the objective function at the optimal solution? **See image for answer to the above question** Required: Please explain & show the algebra/working for the determination of the corner points A =12/7 and B =15/7.What is Dynamic Programming (DP)? Provide two main components of DP.
- pls answer the 2nd question: The Montemar Company is considering contracting with a market research firm to do a survey to determine future market conditions. The results of the survey will indicate either positive or negative market conditions. There is a 0.60 probability of a positive report, given favorable conditions; a 0.30 probability of a positive report, given stable conditions; and 0.10 probability of a positive report; given unfavorable conditions. There is a 0.90 probability of negative report, given unfavorable conditions; a 0.70 probability given stable conditions; and a 0.40 probability, given favorable conditions. d & e, as per the guidelinespls answer the 2nd question: The Montemar Company is considering contracting with a market research firm to do a survey to determine future market conditions. The results of the survey will indicate either positive or negative market conditions. There is a 0.60 probability of a positive report, given favorable conditions; a 0.30 probability of a positive report, given stable conditions; and 0.10 probability of a positive report; given unfavorable conditions. There is a 0.90 probability of negative report, given unfavorable conditions; a 0.70 probability given stable conditions; and a 0.40 probability, given favorable conditions. a b & c, as per the guidelinesProblem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $11 $12 $13 2 $9 $10 $9 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as Edwards provides sufficient advance orders, each supplier can devote its capacity to component 1, component 2, or any combination of the two components, if the total number of units ordered is within its capacity. Supplier capacities are as follows: Supplier 1 2 3 Capacity 500 900 700 If the Edwards production plan for the next period includes 900 units of component 1 and 700 units of component 2, what purchases do you recommend? That is, how many units of each…
- Subject: Logistic Management Q#6) What is Porters Power Model explain with example? Q#7) What is risk management & mitigation explain with example?Mo5. 1. Using the previous case: It would be necessary to make a production capacity restriction if, for example, five hours are required to produce each unit and only 40 hours per week are available. a.A+B b.5X(560) c. 5x ≤ 40 d. 5x=Z 2. Linear programming is a method: a. A formula for obtaining a program. b. To use design software. c. A tool of excel. d. Is a troubleshooting method developed to help managers to make decisions. 3. Quantitative analysis is a tool that is used: a. Calculate the distance between 2 points b. To the decision-making process at the managerial level. c. Model for calculating formulas for excel d. System for designing cars. 4. The probability is a. Get the reality. b. Analyzes the uncertainties associated with past events c. Analyzes the uncertainties associated with future events d. Make the analysis for the moment.This is question 24 under section 3.5. It is missing Mr. Meadows Cookie Company makes a variety of chocolate chip cookies in the plant in Albion, Michigan. Based on orders received and forecasts of buying habits, it is estimated that the demand for the next four months is 850, 1,260, 510, and 980, expressed in thousands of cookies. During a 46-day period when there were 120 workers, the company produced 1.7 million cookies. Assume that the number of workdays over the four months are respectively 26, 24, 20, and 16. There are currently 100 workers employed, and there is no starting inventory of cookies. a.What is the minimum constant workforce required to meet demand over the next four months? b.Assume that inventory cost is 10 cents per cookie per month; hiring cost is $1000 per worker, and firing cost is $2000 per worker, payroll cost is $75 per day per worker. Evaluate the cost of the plan derived in part (a). c. Formulate as a linear programming problem. Be sure to define…