Assuming the company ONLY uses overtime and/or subcontract production if regular production capacity is not sufficient, answer the following questions: What is the regular production cost (over the six months from January through June) for a CHASE production plan? (Display your answer to the nearest whole number.) 11340000 What is the total overtime production cost for this production plan? (Display your answer to the nearest whole number.) 48000 What is the total subcontract cost for this production plan? (Display your answer to the nearest whole number.) 167400 What is the total holding cost for this production plan? (Display your answer to the nearest whole number.) What is the total hire cost for this production plan? (Display your answer to the nearest whole number.) Number What is the total fire cost for this production plan? (Display your answer to the nearest whole number.) Number What is the total cost (sum of all costs) for this production plan? (Display your answer to the nearest whole number.) Number

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.5: Shortest Path Models
Problem 34P
icon
Related questions
Question
Assuming the company ONLY uses overtime and/or subcontract production if regular production capacity is not sufficient, answer the following questions:
What is the regular production cost (over the six months from January through June) for a CHASE production plan? (Display your answer to the nearest
whole number.)
11340000
What is the total overtime production cost for this production plan? (Display your answer to the nearest whole number.)
48000
What is the total subcontract cost for this production plan? (Display your answer to the nearest whole number.)
167400
What is the total holding cost for this production plan? (Display your answer to the nearest whole number.)
What is the total hire cost for this production plan? (Display your answer to the nearest whole number.)
Number
What is the total fire cost for this production plan? (Display your answer to the nearest whole number.)
Number
What is the total cost (sum of all costs) for this production plan? (Display your answer to the nearest whole number.)
Number
Transcribed Image Text:Assuming the company ONLY uses overtime and/or subcontract production if regular production capacity is not sufficient, answer the following questions: What is the regular production cost (over the six months from January through June) for a CHASE production plan? (Display your answer to the nearest whole number.) 11340000 What is the total overtime production cost for this production plan? (Display your answer to the nearest whole number.) 48000 What is the total subcontract cost for this production plan? (Display your answer to the nearest whole number.) 167400 What is the total holding cost for this production plan? (Display your answer to the nearest whole number.) What is the total hire cost for this production plan? (Display your answer to the nearest whole number.) Number What is the total fire cost for this production plan? (Display your answer to the nearest whole number.) Number What is the total cost (sum of all costs) for this production plan? (Display your answer to the nearest whole number.) Number
PP.52 A manufacturer of solid state drives (SSDS) has projected the next six months of demand to be as shown the table below:
Supply/Demand Info
Beginning
Jan
Feb
Mar
Apr
May
Jun
Forecast (demand)
59,600
51,600
62,600
57,200
47,800
48,800
Regular production
Overtime production
Subcontract production
Ending inventory
Hired employees
4,800
Fired employees
Total employees
220
Cost variables are as follows:
Cost Variables
Labor cost/hour
$18
Overtime cost/unit
$30
Subcontracting cost/unit
Holding cost/unit/month
Hiring cost/employee
$27
$12
$3,800
Firing cost/employee
$5,700
Here is some additional relevant (capacity) information:
Capacity Information
Total labor hours/SSD
2
Regular production units/employee/month
Max regular production/month
200
56,000
Max overtime production/month
Max subcontractor production/month
4,800
5,000
Transcribed Image Text:PP.52 A manufacturer of solid state drives (SSDS) has projected the next six months of demand to be as shown the table below: Supply/Demand Info Beginning Jan Feb Mar Apr May Jun Forecast (demand) 59,600 51,600 62,600 57,200 47,800 48,800 Regular production Overtime production Subcontract production Ending inventory Hired employees 4,800 Fired employees Total employees 220 Cost variables are as follows: Cost Variables Labor cost/hour $18 Overtime cost/unit $30 Subcontracting cost/unit Holding cost/unit/month Hiring cost/employee $27 $12 $3,800 Firing cost/employee $5,700 Here is some additional relevant (capacity) information: Capacity Information Total labor hours/SSD 2 Regular production units/employee/month Max regular production/month 200 56,000 Max overtime production/month Max subcontractor production/month 4,800 5,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,