At Little Green Apple Produce the owner is considering buying a new large walk in cooler for fruits and vegetables. The new cooler cost $150,000. The annual maintenance cost will be $7,000 starting in year two (the first year will be covered under warrantee). An additional employee will be needed to stock the cooler. The employee will make $16/hr, and start part-time at 20 hours per week. Sale of produce will increase by $100,000 in year one and an additional 10% in year two and 15% in year three. The cost of produce will increase $30,000 in year one and is variable with sales. The part-time employees hours will vary based on additional sales in years two and three. The employee will receive raises of 4% annually and electricity will increase 3% a year. There is no inflation on any other item.  Based on this information prepare a pro forma and calculate the project NPV using a 9% discount rate/hurdle rate and calculate the IRR. State if the project should be expected or rejected.    please use excel formula to solve the problem

Essentials Of Business Analytics
1st Edition
ISBN:9781285187273
Author:Camm, Jeff.
Publisher:Camm, Jeff.
Chapter11: Monte Carlo Simulation
Section: Chapter Questions
Problem 3P
icon
Related questions
Question
100%

At Little Green Apple Produce the owner is considering buying a new large walk in cooler for fruits and vegetables. The new cooler cost $150,000. The annual maintenance cost will be $7,000 starting in year two (the first year will be covered under warrantee). An additional employee will be needed to stock the cooler. The employee will make $16/hr, and start part-time at 20 hours per week. Sale of produce will increase by $100,000 in year one and an additional 10% in year two and 15% in year three. The cost of produce will increase $30,000 in year one and is variable with sales. The part-time employees hours will vary based on additional sales in years two and three. The employee will receive raises of 4% annually and electricity will increase 3% a year. There is no inflation on any other item. 

Based on this information prepare a pro forma and calculate the project NPV using a 9% discount rate/hurdle rate and calculate the IRR. State if the project should be expected or rejected. 

 

please use excel formula to solve the problem

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 3 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Business Analytics
Essentials Of Business Analytics
Statistics
ISBN:
9781285187273
Author:
Camm, Jeff.
Publisher:
Cengage Learning,
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Entrepreneurial Finance
Entrepreneurial Finance
Finance
ISBN:
9781337635653
Author:
Leach
Publisher:
Cengage
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning