Calculate early start, early finish, late start, late finish, activity float and activity duration for the following and draw an activity on node and activity on arrow diagram.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
 
 
Calculate early start, early finish, late start, late finish, activity float and activity duration for the following and draw an activity on node and activity on arrow diagram.
Milestone
A. Project Initiation
B. Stakeholder Identification
C. Collection of Research Data
D. Identification of Regulatory
Requirements
E. Facility Design
F. Vendor Selection for Equipment and
systems
G. Selection of Computer Systems
H. Selection of Security Systems
J. Completion of Facility Construction
K. Recruitment of Medical
Professionals
L. Recruitment of Administrative and
IT Staff
M. Procurement of Furniture and
Fixtures
N. Procurement of Medical Supplies
and Equipment
O. Staff Training
I. Selection of Power Backup Systems September 15, 2023
Q. Regulatory Compliance
Target Date
March 1, 2023
R. Soft Launch
March 15, 2023
March 30, 2023
S. Full Launch
April 15, 2023
May 15, 2023
June 15, 2023
July 15, 2023
August 15, 2023
October 15, 2023
November 15, 2023
December 15, 2023
January 15, 2024
P. System Testing and Commissioning April 15, 2024
February 15, 2024
March 15, 2024
May 15, 2024
June 15, 2024
July 1, 2024
Predecessor(s)
A. Project Initiation
B. Stakeholder Identification
C. Collection of Research Data
D. Identification of Regulatory Requirements
E. Facility Design
F. Vendor Selection for Equipment and systems
F. Vendor Selection for Equipment and systems
F. Vendor Selection for Equipment and systems
E. Facility Design, G. Selection of Computer Systems, H.
Selection of Security Systems, I. Selection of Power Backup
Systems
J. Completion of Facility Construction
J. Completion of Facility Construction
J. Completion of Facility Construction
J. Completion of Facility Construction
J. Completion of Facility Construction, K. Recruitment of
Medical Professionals, L. Recruitment of Administrative and
IT Staff, M. Procurement of Furniture and Fixtures, N.
Procurement of Medical Supplies and Equipment
O. Staff Training
N. Facility Construction P. System Testing and
Commissioning
Q. Regulatory Compliance
R. Soft Launch
Transcribed Image Text:Milestone A. Project Initiation B. Stakeholder Identification C. Collection of Research Data D. Identification of Regulatory Requirements E. Facility Design F. Vendor Selection for Equipment and systems G. Selection of Computer Systems H. Selection of Security Systems J. Completion of Facility Construction K. Recruitment of Medical Professionals L. Recruitment of Administrative and IT Staff M. Procurement of Furniture and Fixtures N. Procurement of Medical Supplies and Equipment O. Staff Training I. Selection of Power Backup Systems September 15, 2023 Q. Regulatory Compliance Target Date March 1, 2023 R. Soft Launch March 15, 2023 March 30, 2023 S. Full Launch April 15, 2023 May 15, 2023 June 15, 2023 July 15, 2023 August 15, 2023 October 15, 2023 November 15, 2023 December 15, 2023 January 15, 2024 P. System Testing and Commissioning April 15, 2024 February 15, 2024 March 15, 2024 May 15, 2024 June 15, 2024 July 1, 2024 Predecessor(s) A. Project Initiation B. Stakeholder Identification C. Collection of Research Data D. Identification of Regulatory Requirements E. Facility Design F. Vendor Selection for Equipment and systems F. Vendor Selection for Equipment and systems F. Vendor Selection for Equipment and systems E. Facility Design, G. Selection of Computer Systems, H. Selection of Security Systems, I. Selection of Power Backup Systems J. Completion of Facility Construction J. Completion of Facility Construction J. Completion of Facility Construction J. Completion of Facility Construction J. Completion of Facility Construction, K. Recruitment of Medical Professionals, L. Recruitment of Administrative and IT Staff, M. Procurement of Furniture and Fixtures, N. Procurement of Medical Supplies and Equipment O. Staff Training N. Facility Construction P. System Testing and Commissioning Q. Regulatory Compliance R. Soft Launch
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.