a. Construct the project network b. Determine the critical path C Find the completion time of the proiect
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: __________2a) What steps comprise the “critical path”? __________2b) What is the minimum completion…
A: A project network is a graphical network that shows the duration of project activities and their…
Q: PM.57 The activities needed to develop a new software application are listed in the following table…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Construct a network diagram for this project?
A: Find the Duration Calculation below:
Q: Constant time network The times are shown below for each activity. a. What is the…
A:
Q: a. Draw a project network. b. Identify the critical path. e Develop the activity schedule for the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: a. Construct the network diagram for this project. b. Determine the earliest and latest start times…
A: Below is the solution:-
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: a) Explain the purposes of a dummy activity in a network diagram. (b) Table 1 shows the activities…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers…
A: Critical path examination is an undertaking arranging technique that spotlights on recognizing…
Q: 1. Draw the project network 2. What is the expected time for activity B? 3. What is the variance for…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Lonstruct the project network. Determine the critical path.
A: In project management critical path refers to the longest sequence of tasks that needs to concluded…
Q: a. Draw a project network b. Identify the critical path c. Develop the activity schedule for the…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: 1. Draw a project network given the following information. 2. Complete the forward and backward pass…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a) Create an activity network diagram that shows the sequential logic the project tasks. b) Identify…
A: The critical path method (CPM) is a method for determining schedule flexibility and identifying…
Q: (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for booking a…
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. Activity Preceding activity Activity duration A - 6 B - 3 C B 1 D A, C 2 E…
A: Given Information:
Q: A project has been defined to contain the following list of activities, along with their required…
A: The a, b and c part answers are shown in the diagram below-
Q: *1. Determine the critical path for the project network in Figure 6.43.
A: A critical path is the sequence of project activities that adds up the longest duration to complete.
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: The aritical path for the network activities shown below is with completion time of weeks. Activity…
A: Answer: For determining the critical path, we have to draw the network diagram of the mentioned…
Q: 1. Draw the network diagram for the project below. 2. What is the critical path and completion…
A:
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A:
Q: Table 1 Activities Immediate Predecessors Time (In Days) A 9. -- В A C A 9. B,C 6. E В, С 7 F 10 G E…
A:
Q: Given the following information, a. Draw a project network. b. Complete the forward and backward…
A: Note: - Since we can answer only up to three subparts we will answer the first three(a, b, and c)…
Q: В- using the table below, Activity Predecessor Duration A A A D E 1 В E,C F D,B 1- How many paths…
A: The project network diagram is the visual representation of project tasks and their duration to…
Q: QI: Draw the arrow diagram for the following activities and show the critical path: activity…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES = maximum…
Q: Example 4: The details of the project network are given in table below, if indirect cost (overhead)…
A: critical path: A-B-E
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: 4. Using below data for an army practice : A. Construct a project network B. Determine the length or…
A: A project network diagram gives the sequential and logical relationship between various task…
Q: a) Determine the expected completion time and variance for each activity. b) Determine the total…
A: To calculate the Mean or Expected completion time for each activity is- [tA+4(tM)+tB]/6 Similarly,…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: (a). Draw the Activity on Node (AoN) network diagram. (b). Find the critical path and write that…
A: Below is the solution:-
Q: a) Construct a network for this project b) Find a project schedule to minimize the completion time…
A: Given data is
Q: Consider the following project schedule and respond to the requirements that follow (all times are…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: Draw up a table including activity, expected time and variance and then construct the project…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Immediate Estimated Activity Predecessors Duration A t+5 months В t+1 month C В t+2 months A, C t+4…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for planning a…
Q: a) Draw the network diagram for this project b) Calculate for the slack time c) Find the critical…
A: Find the Given details below: Activity Normal Time(days) Crash Time(days) Immediate…
Q: Activity Preceding Time A 8 -- B 3 -- A 7 D А, В 3 E C 4 F 6 a. Draw the network diagram. b.…
A: given, Activity Preceding Time A - 8 B - 3 C A 7 D A,B 3 E C 4 F D 6
Q: Determine a) The slack available of every activity. b) The critical path c) The duration of the…
A: Project network is the diagram that shows the project tasks or activities and their duration to…
Q: Activity Immediate Predecessor(s) Estimated Activity Duration (in days) NONE 2 B A 4 A B 5 E C,D 8.…
A: The network diagram based on the given information is as follows:
Q: Draw a project network. b. What are the critical activities? c. What activity has the most slack…
A: The Path is mentioned in red path
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: A project has been defined to contain the following list of activities along with their required…
A: D. Even if there is change in activity 6 to take 6 weeks instead of 1 week there is no change in the…
Solve the following problem using PERT or CPM.
Step by step
Solved in 2 steps with 2 images
- ASAP!! ANSWER PLEASE Consider the following project. Task Description Duration (Weeks) Immediate Predecessors A Select office site - 3 B Create organizational and financial plan - 5 C Determine personnel Requirements B 3 D Design Facility A, C 4 E Construct interior D 8 F Select personnel to move C 2 G Hire new employees F 4 H Move Records, Key Personnel, etc. F 2 I Make Financial arrangement B 5 J Train new personnel H, E, G 3 Draw a project network What are the critical activities? Develop the activity schedule for the project What activity has the most slack time?Where can I to find Microsoft Project. And hoe can I Describe its utility, including strengths and weaknesses.Following are the activities of a project: Activity time in weeks Immediate Most Most MostActivity Precedence Optimistic Likely PessimisticA None 4 7 13B A 6 9 11C A 5 7 09D B 3 5 07E C 7 8 10F D 2 3 05G E 6 7 08H F&G…
- https://www.space.com/nasa-picksspacex-blue-origin-private-moon-lander-companies.html Project Managers are often tasked with the responsibility to select potential projects and tomotivate their selection to senior management in order to procure commitment of funds andresources.a. Establish and highlight the importance of project management as a key enabler of organisational strategy and identify how this relates to NASA as per the case study.You happen to be the Project Manager for a new project to create anacademic programme ininprojeDepartment of Construction Technology and Management (CTM), KNUST, Kumasi. This p was authorized by the request of some key industry players in the Oil and Gas Industry. Themanagemenare hosted by academicprogramme is purposed to cover other disciplines in engineering, surveying, business r and computer applications. The academic training in these disciplinesdepartments outside the CTM Department but within KNUST. Your selection as the Project Manager (PM) was done by the Dean of your Faculty via a Project Charter. Other persons weree unfamiliar to you. The effortof you and your team would be counted as "Service" to the University, meaning you will not be the charter mandates you to use any resource of KNUST (vehicles etc.) found to be necessary for receiving any remuneration for your input or effort. To facilitate your work under the assignment, the work. The project is not expected to cost…ASAP!! Consider the following project. Task Immediate Predecessors Optimistic Most probable Pessimistic Crash Time Normal Cost (100) Crash Cost (100) A - 5 6 7 4 10 19 B - 7 8 15 7 10 18 C A, B 3 4 5 2 15 27 D C 9 10 23 8 20 32 E C 8 10 12 7 50 80 F E 5 6 7 4 30 41 G C 5 6 19 5 80 102.5 H D, F, G 5 6 7 4 50 64 I D, F 3 6 15 4 100 124 J H 2 4 6 3 40 44 K I, J 3 4 5 3 50 55 Draw a project network Find the critical path and expected project completion time. Assuming that management desire a 21 weeks project completion time. What activity should be crashed? Activity schedule table after crashing. Find total project cost after crashing.
- As a project manager of construction industry, (a) Describe THREE (3) typical issues, with ONE (1) example each, that hinder the project success in construction industry.Explain briefly and include example (b) Suggest TWO (2) approaches to reduce those issues in1 (a) .Explain briefly and include exampleConsider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Activity Description Immediate Predecessor(s) Optimistic (Weeks) Most Likely (Weeks) Pessimistic (Weeks) A --- 4 7 10 B A 2 8 20 C A 8 12 16 D B 1 2 3 E D, C 6 8 22 F C 2 3 4 G F 2 2 2 H F 6 8 10 I E, G, H 4 8 12 J I 1 2 3 A.What is the probability of completion of the project before week 42?What possible project do you anticipate that we can undertake to uplift the image of the school 1. Justify objectives 2.Develop a well WBS and its deliverables for the project 3. Establish relationships between activities, show predecessor and successor of the activities. 4. Draw a network diagram and determine durations. 5. Human resource capacity,teams, roles, responsibilities, and competencies. 6. Organizational structure that will be adopted and why.
- Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Activity Description Immediate Predecessor(s) Optimistic (Weeks) Most Likely (Weeks) Pessimistic (Weeks) A --- 4 7 10 B A 2 8 20 C A 8 12 16 D B 1 2 3 E D, C 6 8 22 F C 2 3 4 G F 2 2 2 H F 6 8 10 I E, G, H 4 8 12 J I 1 2 3 What is the expected time for activity B? What is the variance for activity B? Based on the calculation of estimated times, what is the critical path? What is the estimated time of the critical path? What is the activity variance along the critical path? What is the probability of completion of the project before week 42?Calculate the total float, free float andindependent float for the project whose activitiesare given below:Activity : 1-2 1-3 1-5 2-3 2-4 3-4Duration in weeks 8 7 12 4 10 3Activity : 3-5 3-6 4-6 5-6Duration in weeks 5 10 7 41. Was Linderman Industries’ adoption of project organization an appropriate one for getting the Mexican subsidiary started? 2. In consideration of Robert Linderman’s letting the division managers know that the project manager would be asking for some of their key people, why would Conway have any difficulty in getting the ones he wanted? 3. Would you expect that many people would turn down a chance to join a project organization, as Bert Mill did? 4. Why would Conway take his problem with the engineering vice president to Linderman and have it resolved in his favor, yet back down in two disputes with the manufacturing vice president? 5. What could Linderman Industries have done to assure good jobs for the people coming off Project Mexicano, including Carl Conway, the project manager?