Determine the Critical Path and Project Duration to complete the process. ii. Activity F cannot start immediately after activity C. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process.

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.3SD: Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling...
icon
Related questions
Question
2. a) The activity shown in Table Q2 (a) are processes carried out in a mechatronic company. Based on the table provided, (i) Determine the Critical Path and Project Duration to complete the process. ii. Activity F cannot start immediately after activity C. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process.
Table Q2 (a)
田
Activity
Processes
Predecessor
Duration
(Days)
Customer order
Service department
Raw material storage
Material inspection
Parts fabrication
Testing of parts
Modules assembly
Module assembly inspection
Fix faulty modules
Assembly
Fix faulty parts in product
QA/QC inspection
Approval and packaging
A
A
C
5
4
E
C
4
F
C
G
E, F
H
A
4
I
A
H, I
J
5
K
D
3
G
M
J,K,L
Transcribed Image Text:Table Q2 (a) 田 Activity Processes Predecessor Duration (Days) Customer order Service department Raw material storage Material inspection Parts fabrication Testing of parts Modules assembly Module assembly inspection Fix faulty modules Assembly Fix faulty parts in product QA/QC inspection Approval and packaging A A C 5 4 E C 4 F C G E, F H A 4 I A H, I J 5 K D 3 G M J,K,L
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning