Draw the network diagram, and find out the critical path and project duration?
Q: e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a…
A: Below is the solution:-
Q: 2) Draw the network corresponding to the following information. Also, complete the table, identify…
A: Critical Path : B----D----G----H Critical Path Duration : 30
Q: a) Draw network diagram representing the project b) Find total float & free float for each activity…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: . Draw the network diagram and determine the critical path for the project below:
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Ken Johnston, the data processing manager for Stanley Morgan Bank, is planning a project to install…
A: LS= Late Start LF = Late Finish EF = Early Finish ES = Early Start Slack = LF-EF
Q: Draw the Project Network
A: A network diagram is a visual picture of a project which helps to identify the activity relationship…
Q: Draw the CPM network and identify the critical path. How many weeks will the projec require under…
A: A network diagram is a representation of a project which helps to know the activity relationship…
Q: hat is the best way to draw a project network?
A: THE ANSWER IS AS BELOW:
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Set up a table and calculate Early Event Times (TE), Late Event Times (TL), Activity Free Slack…
A: THE ANSWER IS AS BELOW:
Q: A competitor of Kozar International Inc. has begun marketing a new, instant-developing film project.…
A: Given data, Activity Immediate Predecessors Optimistic Time Most Probable Time Pessimistic Time…
Q: Using the data in the following table: a) Draw the network diagram b) List the network paths, the…
A: Given data is
Q: Develop an activity schedule for this project using early and late start and finish times, compute…
A: A forward and backward passing network diagram including 5 different time dimension for a project…
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: A critical path indicating the longest duration path which representing minimum time required to…
Q: Draw a suitable network for the following. Activities G & H are the final activities for this…
A:
Q: Two international banks are integrating two financial processing software systems as a result of…
A: Activity Immediate Predecessors Activity Time A - 3 B A 1 C A 2 D…
Q: Create a Network Diagram and Critical Path using the Data. Determine the minimum project duration.…
A: Activity Duration Preceded A 4 - B 2 - C 3 - D 2 - E 5 A F 3 A,B,C G 3 C,D H 3 F,G…
Q: Draw a fully analyzed AON network diagram and determine the project duration. Be sure to include all…
A: Below is the solution:-
Q: Draw a network diagram that includes the project information above.
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Use the following project status information to calculate each of the requested EVM numbers below.…
A: Task Budget Cost Duration % Complete Actual Cost Planned Value Earned Value =% complete *PV A…
Q: Given the following table, construct a network diagram, either AOA or AON. Times are in days.a.…
A:
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: The network diagram for a new project your company is undertaking is as shown: Start +Einish a.…
A: Given data is
Q: Consider the below project information for questions 1-4. Activity Immediate Duration (days)…
A: Answer: A project consists of different activities. The project mentioned in the question is having…
Q: For the following schedule, draw the node network, perform the CPM calculations, mark the critical…
A: below is the solution:-
Q: Activity Predecessor Duration in Weeks А A 3 C A 2 D В 3 E 4 F D G B 1 H D 3 I C
A: Hi, we are supposed to answer three sub parts at a time. Since you have not mentioned which subpart…
Q: Draw the network diagram and determine the minimum total time (in weeks) using the concept of…
A: Project crashing is a process which helps to reduce the total project completion time using…
Q: 1. Determine the critical path for the project network in the following Figure:
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: (a) Construct a project network diagram for Table 1 using the Arrow-On-Nodes (AON) method with all…
A: In a project environment, a project schedule network diagram depicts the sequential and logical link…
Q: a. For each activity, calculate: ESD, EFD, LSD, LFD, FF, and TF. (Report your answers in the table…
A: A network diagram is a visual representation that helps to identify the activity relationship and…
Q: 1. Calculate the expected duration and the standard deviation for the critical path.
A: YOUR ANSWER IS GIVEN BELOW:
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given data is
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: 1. Compute the most probable or mean time, t. Indicate your answers in the table above. 2. Construct…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: Ql: For activitics shown in table below, find the new time of project after updating, if the project…
A: ANSWER IS AS BELOW:
Q: Use the following information in a table about the activities of an information technology project…
A: Activity Predecessors Days A -- 4 B A 5 C A 6 D B 5 E B, C 3 F D, E 7
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A:
Q: The following table contains a list of activities, with precedence requirements and crash costs. All…
A: a.
Q: 2. Draw an AON network diagram and calculate its early start, early finish, late start and late…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: For the project data in Table below, answer the following questions: a) Draw an AOA network of the…
A: ANSWER IS AS BELOW:
Q: Paul Silver, owner of Sculptures International, just initiateda new art project. The following data…
A: Given data is
Q: How is the terminal project balance equivalent to the net future worth of the project?
A: The terminal value determines the business project’s value beyond the forecast period when future…
Q: Draw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and…
A: Using the details given in the table, the following network diagram can be prepared.
Q: Q/ For the project data in Table below, answer the following questions: a) Draw an AOA network of…
A: Using the following format for the AOA diagram: Where Slack=|ES − LS| or |EF − LF|
Q: For the activity times and network model below, What is the expected completion time? ________ What…
A: Here is the network diagram with activity & time duration :
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- In reference to the attached image and data below: What are the final recommendations? Step A we know: Critical Path = A, B, H, I, J; Project Time = 40 Weeks; Total Cost = 364,000 Step B we know: To crash the critical path I would crash A by 1 week, B by 2 week, H by 2 week and C by 3 week. This would not alter the critical path, only the time line. Steps C we know: Modeling uncertainty in activity times. In this case I would use the activity times and determine the Variances and the Standard Deviation. Using “best case” (x) and “worst case” (y) scenarios for activity times the formula’s would be (x-y)/6 and (x-y)^2/36.You lead a family day project for welcoming the arrival of the new students to the campus. The accompanying Table 1 shows the activities, times and sequences required for the project planning and monitoring. Table 1 Activities Immediate Predecessors Time (In Days) A -- 9 B A 5 C A 9 D B,C 6 E B, C 7 F D 10 G E 12 H F,G 8 Based on the Table 1, using Critical Path Method (CPM) diagram, determine the ES, EF, LS & LF, identify the critical activities, critical path and the expected project completion time.Build a PERT Analysis for a 3-month project with 6 activities (A to F) and 5 nodes
- A project consists of five activities Optimistic Most Probable Pessimistic Activity Predecessor Time (hr) Time (hr) Time (hr) Floor sanding - 3 4 5 Floor buffing FL sanding 1 2 3 Paint Ceiling Paint mixing - 0.5 1 1.5 Paint Wall Paint Mix 1 2 9 Paint Ceiling Paint Mix 1 5.5 7 What is the Std Deviation of the Critical Path?Rich Cole Control Devices, Inc., producescustom-built relay devices for auto makers. The most recentproject undertaken by Cole requires 14 different activities.Cole’s managers would like to determine the total projectcompletion time (in days) and those activities that lie alongthe critical path. The appropriate data are shown in the fol-lowing table.a) What is the probability of being done in 53 days?b) What date results in a 99% probability of completion?Define WBS and work package. Draw WBS for a TV prototype manufacture project.How does WBS help the project manager? How do you integrate WBS with the OBS?
- A student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities “a” and “b” start on day 0. Draw the network diagram. Calculate ES/EF/LS/LF and Slack for all activities. Activity A: Immediate Predecessprs (-) Duration days (3) Activity B: Immediate Predecessprs (-) Duration days(5) Activity C: Immediate Predecessprs (a) Duration days(3) Activity D: Immediate Predecessprs (b) Duration days(7) Activity E: Immediate Predecessprs (C,D) Duration days(3)Problem 3: Kelly Melford Kelly Melford and her team are working on redesigning a client's home. The client requested Kelly for the project to be completed sooner. Kelly asked her assistant to collect information from her team on the project. Her assistant organized the information she got into a table. The information is given in weeks. Based on the information below, prepare a comprehensive report that includes the following: 3. Your insights on the cost-time trade-off for this project. 4. Your recommended strategy for crashing the project.please help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach?
- B. What is the expected project completion time? 7 weeks8 weeks9 weeks6 weeks C. Which are the critical activities? A, B, C, F, G and IA, B,C, G and IA, B, C, D, E, F and IA, B, C,D, F, G and Iplease help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited references.*SEE THE ATTACHED DPROBLEM REQUIRED Identify the critical path. (Write the letters without spaces and commas.) Determine the number of days for the entire activities to be completed.