Draw up a table including activity, expected time and variance and then construct the project network. b. Find the critical path. c. Determine the expected completion time for the project.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The Center for Information Technology at State University has outgrown its office in Bates (B)
Hall and is moving to Allen (A) Hall, which has more space. The move will take place during the
3-week break between the end of summer semester and the beginning of fall semester. Movers will
be hired from the university's physical plant to move the furniture, boxes of books, and files that
the faculty will pack. The center has hired a local retail computer firm to move its office comput-
ers so they won't be damaged. Following is a list of activities, their precedence relationships, and
probabilistic time estimates for this project:
Activity Description
Predecessor
Optimistic
estimate (a)
Most likely
estimate (m)
Pessimistic
estimate (b)
a
Pack A offices
1
3
5
b
Network A offices
2
3
5
с
Pack B offices
2
4
7
d
Movers move A
a
1
3
4
offices
Paint and clean A
d
2
5
8
offices
Move computers
b, e
1
2
g
Movers move B
b, c, e
3
6
8
offices
h
Computer
f
2
4
5
installation
Faculty move and
g
3
4
6
unpack
J
h, i
1
2
4
Faculty set up
computers and
offices
a. Draw up a table including activity, expected time and variance and then
construct the project network.
b. Find the critical path.
Determine the expected completion time for the project.
d. Calculate the probability that the project will be completed within 3 weeks.
e
f
100
26
Transcribed Image Text:The Center for Information Technology at State University has outgrown its office in Bates (B) Hall and is moving to Allen (A) Hall, which has more space. The move will take place during the 3-week break between the end of summer semester and the beginning of fall semester. Movers will be hired from the university's physical plant to move the furniture, boxes of books, and files that the faculty will pack. The center has hired a local retail computer firm to move its office comput- ers so they won't be damaged. Following is a list of activities, their precedence relationships, and probabilistic time estimates for this project: Activity Description Predecessor Optimistic estimate (a) Most likely estimate (m) Pessimistic estimate (b) a Pack A offices 1 3 5 b Network A offices 2 3 5 с Pack B offices 2 4 7 d Movers move A a 1 3 4 offices Paint and clean A d 2 5 8 offices Move computers b, e 1 2 g Movers move B b, c, e 3 6 8 offices h Computer f 2 4 5 installation Faculty move and g 3 4 6 unpack J h, i 1 2 4 Faculty set up computers and offices a. Draw up a table including activity, expected time and variance and then construct the project network. b. Find the critical path. Determine the expected completion time for the project. d. Calculate the probability that the project will be completed within 3 weeks. e f 100 26
Expert Solution
steps

Step by step

Solved in 5 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.